ex itplan1





CSPS Iteration Plan 1.0


backPath = './../../';






Collegiate Sports Paging Service
Iteration Plan
 Version 1.0
 Revision
History




Date


Version


Description


Author



October 6, 1999
1.0
Initial version
Context Integration


Table of Contents

Introduction
Plan
Resources
Use Cases
Evaluation Criteria

Introduction
Purpose
This Iteration Plan describes the detailed plans for the Preliminary
Iteration of the Project. During this iteration, the requirements of the system
will be defined and the high level plan for execution of the full project will
be developed. This first iteration will conduct a thorough analysis on the
business case for the system and will result in a decision on whether the
project will proceed.
Scope
The Preliminary Iteration Plan applies to the project being developed by
Context Integration for WebNewsOnLine. This document will be used by the Project
Manager and by the project team.
Definitions, Acronyms and Abbreviations
See Glossary document.
References

CSPS Vision 1.0
CSPS Requirements Management Plan 1.0

Plan
The Preliminary Iteration will develop the product requirements and establish
the business case for the Collegiate Sports Paging System. The major use cases
will be developed as well as the high level Project Plan. At the end of this
iteration, will decide whether to fund and proceed with the project based upon
the business case.
Iteration Tasks
The following table illustrates the tasks with their planned start and end
dates.




Task


Start


End



INCEPTION
Fri 10/1/99
Mon 10/25/99


Begin Inception
Fri 10/1/99
Fri 10/1/99


Inception Kick-off
Mon 10/4/99
Wed 10/6/99


Add tasks to project plan for specific project
technology using ContextWISE cartridges
Mon 10/4/99
Mon 10/4/99


Assemble Change Control Board
Mon 10/4/99
Tue 10/5/99


Create and baseline Change Control Plan
Tue 10/5/99
Tue 10/5/99


Obtain Sign-off
Tue 10/5/99
Tue 10/5/99


Inception Kick-off Meeting
Tue 10/5/99
Wed 10/6/99


Prepare for inception kick-off meeting
Tue 10/5/99
Wed 10/6/99


Hold Inception Kick-off Meeting
Wed 10/6/99
Wed 10/6/99


Inception Kick-off Completed
Wed 10/6/99
Wed 10/6/99


Inception Deliverables
Wed 10/6/99
Thu 10/14/99


Hold Requirements Workshop
Wed 10/6/99
Thu 10/7/99


Project Vision created, reviewed, and signed
off
Wed 10/6/99
Thu 10/7/99


Preliminary Use Case Model (10-20% complete)
created and placed under revision control
Thu 10/7/99
Mon 10/11/99


Preliminary Use Case Survey created, reviewed,
and signed off
Mon 10/11/99
Tue 10/12/99


Preliminary Supplementary Specifications
created, reviewed, and signed off
Tue 10/12/99
Tue 10/12/99


Business Case created, reviewed, and signed off
Tue 10/12/99
Tue 10/12/99


Preliminary Project Glossary created, reviewed,
and signed off
Tue 10/12/99
Tue 10/12/99


Preliminary Creative Design Brief created,
reviewed, and signed off
Wed 10/6/99
Thu 10/7/99


Preliminary Site Map & Use-Case Navigation
Mapping created, reviewed, and signed off
Thu 10/7/99
Fri 10/8/99


Creative Design Comps created, reviewed, and
signed off
Fri 10/8/99
Mon 10/11/99


Preliminary Content Plan created, reviewed, and
signed off (if applicable)
Wed 10/6/99
Wed 10/6/99


User Interface Prototype (optional) created,
reviewed, and signed off
Wed 10/6/99
Wed 10/6/99


Reports Prototype (optional) created, reviewed,
and signed off
Tue 10/12/99
Thu 10/14/99


Develop Preliminary Technology Alternatives
Wed 10/6/99
Thu 10/7/99


Establish contact with appropriate Context
Gurus
Tue 10/12/99
Wed 10/13/99


Preliminary Knowledge Transfer Plan &
Schedule created, reviewed, and signed off
Wed 10/13/99
Wed 10/13/99


Validate/Invalidate Assumption from Inception
proposal
Wed 10/13/99
Thu 10/14/99


Obtain Sign-off
Thu 10/14/99
Thu 10/14/99


Inception Deliverables Complete
Thu 10/14/99
Thu 10/14/99


Inception Wrap-up
Thu 10/14/99
Mon 10/25/99


Conduct Quality Check Meeting with Client
Thu 10/14/99
Thu 10/14/99


Conduct Quality Assurance
Thu 10/14/99
Fri 10/15/99


Hold Context Lessons Learned Meeting
Thu 10/14/99
Thu 10/14/99


First project estimates created, reviewed, and
signed off (+75%, -60%)
Thu 10/14/99
Mon 10/18/99


Full Project Iterative Delivery Plan created,
reviewed, and signed off
Mon 10/18/99
Tue 10/19/99


Create proposal for Elaboration Phase
Thu 10/14/99
Fri 10/15/99


Create Software Project Log
Fri 10/15/99
Fri 10/15/99


Prepare for Inception Checkpoint
Fri 10/15/99
Mon 10/18/99


Have team, including client project manager,
complete the work release sign-off form
Mon 10/18/99
Tue 10/19/99


Deliver proposal for Elaboration Phase
Tue 10/19/99
Thu 10/21/99


Inception Checkpoint Review and Go/No Go
Decision
Thu 10/21/99
Fri 10/22/99


Move appropriate deliverables from Project
Homepage to IAN Artifacts
Fri 10/22/99
Mon 10/25/99


Inception Complete
Mon 10/25/99
Mon 10/25/99


The following deliverables or artifacts will be generated and reviewed during
the Preliminary Iteration:



Artifact Set
Deliverable
Responsible
Owner


Business Modeling Set
Glossary
Brian Egler
Brian Egler
Brian Egler
Brian Egler


Requirements Set
Vision Document
Use Case Specifications
Supplementary Specification
Use Case Model (and Model Survey)
Brian Egler
Brian Egler
Ed Post
Ken Perch
Ken Perch


Management Set
Preliminary Iteration Plan
Project Plan
Project Schedule
Project Risk List
Status Assessment
Preliminary Iteration Assessment
Configuration Management Plan
Mary Durham
Mary Durham
Mary Durham
Mary Durham
Mary Durham
Mary Durham
Mary Durham
Mary Durham
Ken Perch


Standards and Guidelines
Configuration Management Environment
Ken Perch


Resources
The project staffing for this iteration can be viewed as follows:

Financial Resources
The budget for this iteration is $150,000. WebNewsOnLine has secured this
funding.
Use Cases
During the Preliminary Iteration, all significant use cases and actors will
be identified. The basic flows and key alternative flows of each use case will
be determined and documented in the Use Case Specifications. The design and
implementation of use cases will begin in the next iteration.
Evaluation Criteria
The primary goal of the Preliminary Iteration is to define the system to the
level of detail required to make a sound business judgment on the viability of
the project from a business prospective. At the completion of the iteration, a
review of the Business Case will arrive at a Go / No Go decision for the
project.
Each deliverable developed during the iteration will be peer reviewed and
subject to approval from the team.
Criteria for evaluation can be found in the Test Plan.

Copyright 
1987 - 2003 Rational Software Corporation













Wyszukiwarka

Podobne podstrony:
ex itplan4
ex itplan2
ex itplan3
ex uc prtadrpt1
ex uc subsc1
La porte de l etre d eveil (ex Le Soutra de Lotus)
Ex Oblivione
Joint Venture Scheiß auf?ine Ex
ROZG EX
ex
ex tstpln
WentyleVentureTD EX
RM 1 ewaluacja ex post NPR
ex uc sndpg2

więcej podobnych podstron