var nodeInfo=[{view: "view:_LVCagP5WEdmAzesbYywanQ", path: ["_LVCagP5WEdmAzesbYywanQ", "_4U33kAILEdq-_NKqZM1EhA", "_qIh6UABuEdqrKcHWz1HoWw", "{EE97A8CD-66CA-4A9B-9871-E3B94CCED528}", "{DBD235AB-EEEF-4C9E-A83E-5B87DAD70E33}"]}, {view: "view:_LVCagP5WEdmAzesbYywanQ", path: ["_LVCagP5WEdmAzesbYywanQ", "_4U33kAILEdq-_NKqZM1EhA", "_nB0hwAITEdqu-LkyOdB8SQ", "_yeA1y9nmEdmO6L4XMImrsA", "{DBD235AB-EEEF-4C9E-A83E-5B87DAD70E33}"]}, {view: "view:_FCx1oN7CEdmsEI4YDGX2ag", path: ["_FCx1oN7CEdmsEI4YDGX2ag", "_f6_YwN7DEdmsEI4YDGX2ag", "_qIh6UABuEdqrKcHWz1HoWw", "{EE97A8CD-66CA-4A9B-9871-E3B94CCED528}", "{DBD235AB-EEEF-4C9E-A83E-5B87DAD70E33}"]}, {view: "view:_FCx1oN7CEdmsEI4YDGX2ag", path: ["_FCx1oN7CEdmsEI4YDGX2ag", "_kC0pcN7GEdm8G6yT7-Wdqw", "_yeA1y9nmEdmO6L4XMImrsA", "{DBD235AB-EEEF-4C9E-A83E-5B87DAD70E33}"]}];
contentPage.preload(imgPath, backPath, nodeInfo, '', true, false, false);
Task: Assess Iteration
This Task describes how to evaluate the results of an iteration assess related project information, and decide on appropriate changes.
Disciplines: Project Management
Purpose
The purpose of this task is to:
Determine success or failure of the iteration
Capture lessons learned to modify the project or improve the process
Relationships
RolesPrimary Performer:
Project Manager
Additional Performers:
InputsMandatory:
Iteration Plan
Test Evaluation Summary
Optional:
Business Case
Development Process
Software Development Plan
Status Assessment
Vision
Outputs
Iteration Assessment
Process Usage
Project Management
>
Manage Iteration
>
Assess Iteration
Main Description
One of the primary advantages of the iterative approach over the waterfall approach is that the iterations
provide natural milestones for evaluating progress and bounding risk. Within the iteration, progress and risk must
continue to be assessed (if informally) to ensure that difficulties do not derail the project.
Steps
Collect metrics
Purpose
Collect quality and progress information on the project for status, and improvements
This step involves the following work, based on the project's measurement plan:
Collect the primitive metrics
Calculate, verify and validate the metrics
Include the metrics in the status assessment report
During an iteration assessment, metrics are examined, and any actions are decided, which may involve replanning,
re-tooling, training, reorganizing, etc... including revisiting the measurement plan. Similarly at the end of a cycle,
a "post mortem review" can make sure that some of the metrics collected can be exploited to improve the process, or for
estimation purposes. For more information on metrics, see Guideline: Metrics.
For iterations that span weeks or even months, metrics collection and reporting will be a continuing task, with
periodic Artifact: Status Assessments capturing the intermediate results.
Assess the Results Of the Iteration
Purpose
To compare the actual and expected results of the iteration.
Near the end of each iteration, the core project team should meet to assess the iteration, focusing on the following:
Was the iteration successful in meeting its goals?
Were risks reduced or eliminated?
Did the release meet its functionality and quality goals? Performance and Capacity goals?
Are changes to the project and future iteration plans required?
Have any of the findings captured in the Artifact: Development Organization Assessment been invalidated by
changes during the iteration (as a consequence requiring changes to other work products, such as the project's Development Process)?
Were there any difficulties with the project's Development Process during the iteration?
What portion of the current release will be baselined? Reworked?
Have new risks been identified?
Have external changes occurred (changes in the marketplace, in the user community, or in requirements)?
Assess the results of the iteration relative to the evaluation criteria that were established for the iteration plan:
functionality, performance, capacity, quality measures. Use metrics resulting from the testing tasks and the step Collect Metrics as the basis for the assessment, when available, to quantify the
assessment; qualitative measures are adequate for inception and perhaps early iteration, while later elaboration,
construction and transition must rely upon specific test measurements to assess quality, performance, capacity, etc.
Address other unresolved issues that were captured in the status assessments performed during the iteration, and any
others in the Project Manager's Issues List.
If all risks have been reduced to acceptable levels, all functionality has been implemented, and all quality objectives
have been met, the product is complete. Good planning and execution are essential to making this occur at the end of
the Transition phase.
Consider External Change
Purpose
To ensure the project stays connected with the "outside world"
It is easy for the project team to become so inwardly focused that they are not aware of changes in the world outside
the project team. The business may change, adding, changing or removing key requirements. Or a competitor may enter the
market with a similar product, causing a change in market timing requirements, features, or target product cost.
Given the current state of the external environment, is the project plan (including milestones) still valid? Have the
risks changed, forcing a reconsideration of the iteration plans? Is the right product being built and is the vision
still valid? Is the product team on track to deliver that product? Are process changes necessary because of changing
external circumstances?
Use the results of these discussions to generate change requests for the Vision, Risk List, the Software Development Plan, the Iteration Plan,
or the project's Development Process.
Examine the Evaluation Criteria
Purpose
To ensure that the evaluation criteria are realistic.
Sometimes an iteration will fall short of expectations because the objectives were set too high. Setting high goals is
important, but there is sometimes a fine line between aggressive and unrealistic. Project teams are motivated by goals
that cause them to stretch their abilities, but tend to become demoralized if objectives are consistently beyond their
reach. Defining goals so that the project team is challenged without being overwhelmed sometimes takes a few iterations
in itself, as the team learns to work together and learns its limits.
Examine the evaluation criteria to determine whether they were realistic. Sometimes the benefit of the iteration is in
revealing that a particular requirement is not as important as originally thought has tremendous value in itself.
Projects are often crushed by complex but low-value requirements imposed by over-eager users enthralled by the latest
technology; an iteration or two can re-set their expectations and get them to focus on the functionality which provides
real value.
Sometimes the iteration will reveal that a particular feature is very expensive to implement or creates an
unmaintainable architecture. The business case for this feature should be revisited to see if the feature should remain
in-scope, or perhaps revised to make the requirement reachable in a cost-effective way.
Create Change Requests
Purpose
To update the project planning work products.
Based on the results of the assessment, generate change requests for the Vision, Risk List, the Software Development Plan, the Iteration Plan,
the project's Development Process, and Software Requirements.
More Information
Guidelines
Reviews
© Copyright IBM Corp. 1987, 2006. All Rights Reserved.
contentPage.onload();
Wyszukiwarka
Podobne podstrony:
assess iterationZ29E9EFcsps iteration assessmentrup iteration assessment?108D56rup iteration assessment?D86F8Diteration assessment informal representationb8F638Brup iteration assessment?8C6F7plan for next iteration?CDF5ABplan for next iteration?855DCDplan for next iteration?CDF5ABAssessment of cytotoxicity exerted by leaf extractsiterator?tegorymanage iteration+95C965prepare environment for an iteration@2D3B0Aassessmentofexamplesfront insert iteratorwięcej podobnych podstron