Microsoft Office Project Project1 id 299062

background image

ID

Task Name

Duration

Start

Finish

Predecessors

1

START

0 days

Fri 11-05-13

Fri 11-05-13

2

BUILDING SITE PREPARATION WORKS

5 days

Fri 11-05-13

Thu 11-05-19

3

Mechanical stubbing

5 days

Fri 11-05-13

Thu 11-05-19

4

Erecting fencing with wickets and gates

2 days

Fri 11-05-13

Mon 11-05-16

5

Erecting gateways

0,5 days

Fri 11-05-13

Fri 11-05-13

6

Timber wickets with lath and posts, steel posts - erecting

0,5 days

Fri 11-05-13

Fri 11-05-13

7

EARTHWORKS

3 days

Fri 11-05-20

Tue 11-05-24 2

8

Removal of humus with use of dozers, thickness of the layer up to 15 cm

0,5 days

Fri 11-05-20

Fri 11-05-20

9

Measurement during foundation trench, terrain low-lying and plain

0,5 days

Fri 11-05-20

Fri 11-05-20 8

10

Earthworks with push shovel with transport of excavated material by trucks, excavator 0,4m^3, soil category I-II

2 days

Mon 11-05-23

Tue 11-05-24 9

11

FOUNDATION

14,5 days

Wed 11-05-25

Tue 11-06-14 7

12

Formwork assembling

1 day

Wed 11-05-25

Wed 11-05-25

13

Concrete subfloor on the subsoil, concrete delivery with use of wheel-barrow

1 day

Thu 11-05-26

Thu 11-05-26 12

14

Formwork disassembling

1 day

Wed 11-06-01

Wed 11-06-01 13FS+3 days

15

Foundation made of bricks with cement mortar

2 days

Thu 11-06-02

Fri 11-06-03 14

16

Damp insulation, double layer of building paper

1 day

Mon 11-06-06

Mon 11-06-06 15

17

Foundation walls made of bricks, common brick, cement mortar, thickness of 2 brick

4 days

Tue 11-06-07

Fri 11-06-10 16

18

Damp insulation of vertical surface, bulding paper, 1 layer

1 day

Mon 11-06-13

Mon 11-06-13 17

19

Backfilling of excavation with bulldozers, replacing on the distance up to 10 m , soil category I-II, bulldozer 74 kW (100 KM)

0,5 days

Tue 11-06-14

Tue 11-06-14 18

20

GROUND FLOOR

23,5 days

Tue 11-06-14

Fri 11-07-15 11

21

Floor on the soil

11,5 days

Tue 11-06-14

Wed 11-06-29

22

Subfloor made of compacted loose materials on the soil, sand

3 days

Tue 11-06-14

Fri 11-06-17

23

Formwork assembling

1 day

Fri 11-06-17

Mon 11-06-20 22

24

Concrete subfloor on the soil, concrete delivery by pump

2 days

Mon 11-06-20

Wed 11-06-22 23

25

Reinforcement of the concrete elements of the building, round ribbed steel bars, Fi 8-14 mm

1 day

Wed 11-06-22

Thu 11-06-23 24

26

Reinforced slab, concrete delivery by pump

0,5 days

Thu 11-06-23

Thu 11-06-23 25

27

Formwork disassembling

1 day

Wed 11-06-29

Wed 11-06-29 26FS+3 days

28

Walls

12 days

Thu 11-06-30

Fri 11-07-15 21

29

Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks

12 days

Thu 11-06-30

Fri 11-07-15

30

Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 1-brick

1,5 days

Thu 11-06-30

Fri 11-07-01

31

Posts and fillars made of common brick , dimension: 2x2 of brick, cement - lime mortar

1 day

Thu 11-06-30

Thu 11-06-30

32

Lintels made by using PERI formwork, ratio perimeter/cross-section: up to 8 m/m2, version 1

1 day

Thu 11-06-30

Thu 11-06-30

33

Chimney ducts made of hollow bricks

0,5 days

Thu 11-06-30

Thu 11-06-30

34

Stairs

0,5 days

Thu 11-06-30

Thu 11-06-30 21

35

Buildings made of elements OWT-67N : staircase landing

0,5 days

Thu 11-06-30

Thu 11-06-30

36

Buildings made of elements OWT-67N : flight of the stairs

0,5 days

Thu 11-06-30

Thu 11-06-30

37

FLOOR

22,5 days

Mon 11-07-18

Wed 11-08-17 20

38

Slab

10,5 days

Mon 11-07-18

Mon 11-08-01

39

Formwork assembling

1,5 days

Mon 11-07-18

Tue 11-07-19

40

DZ type slab, hollow brick DZ-3, prefabricated beams

3,5 days

Tue 11-07-19

Fri 11-07-22 39

41

DZ type slab, hollow brick DZ-3, prefabricated beams, monolithic ring beam in the external walls with thickness up to 30 cm

0,5 days

Mon 11-07-25

Mon 11-07-25 40

42

Overconcrete pouring, concrete delivery by pump

1 day

Mon 11-07-25

Mon 11-07-25 40

43

Formwork disassembling

1,5 days

Fri 11-07-29

Mon 11-08-01 42FS+3 days

44

Buildings made of elements OWT-65N: gravel concrete slab

0,5 days

Tue 11-07-19

Tue 11-07-19 39

45

Walls

12 days

Mon 11-08-01

Wed 11-08-17 38

46

Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks

12 days

Mon 11-08-01

Wed 11-08-17

47

Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks

1,5 days

Mon 11-08-01

Tue 11-08-02

48

Posts and fillars made of common brick , dimension: 2x2 of brick, cement - lime mortar

1 day

Mon 11-08-01

Tue 11-08-02

49

Lintels made by using PERI formwork, ratio perimeter/cross-section: up to 8 m/m2, version 1

1 day

Mon 11-08-01

Tue 11-08-02

50

Chimney ducts made of hollow bricks

1 day

Mon 11-08-01

Tue 11-08-02

51

ATTIC

12,5 days

Wed 11-08-17

Fri 11-09-02 37

52

Slab

10,5 days

Wed 11-08-17

Wed 11-08-31

53

Formwork assembling

1,5 days

Wed 11-08-17

Thu 11-08-18

54

DZ type slab, hollow brick DZ-3, prefabricated beams

3,5 days

Fri 11-08-19

Wed 11-08-24 53

55

DZ type slab, hollow brick DZ-3, prefabricated beams, monolithic ring beam in the external walls with thickness

0,5 days

Wed 11-08-24

Wed 11-08-24 54

56

Overconcrete pouring, concrete delivery by pump

1 day

Wed 11-08-24

Thu 11-08-25 54

57

Formwork disassembling

1,5 days

Tue 11-08-30

Wed 11-08-31 56FS+3 days

58

Wall beam

2 days

Thu 11-09-01

Fri 11-09-02 52

59

Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks

2 days

Thu 11-09-01

Fri 11-09-02

60

Chimney ducts made of hollow bricks

0,5 days

Thu 11-09-01

Thu 11-09-01

61

ROOF

8 days

Mon 11-09-05

Wed 11-09-14 51

62

Rafter framing

3,5 days

Mon 11-09-05

Thu 11-09-08

63

Collar roof with wall beam under plain tile double layered, rafter framing with span 12 m

3,5 days

Mon 11-09-05

Thu 11-09-08

64

Covering

4,5 days

Thu 11-09-08

Wed 11-09-14 62

65

Damp and water-proof insulation made of wide polyethylene sheeting, horizontal insulaton uder flooring

2 days

Thu 11-09-08

Mon 11-09-12

66

Thermal and acoustic insulation made of mineral wool, vertical 1,5 days

Thu 11-09-08

Fri 11-09-09

67

Placing asphalt shingles with width 8 cm

4,5 days

Thu 11-09-08

Wed 11-09-14

68

Roof gutter made of galvanized iron, semicircular with diameter 15 cm

1 day

Thu 11-09-08

Fri 11-09-09

69

Downpipe made of galvanized iron, semicircular with diameter 15 cm

1 day

Thu 11-09-08

Fri 11-09-09

70

Different treatment made of galvanized iron with width up to 25 cm2 days

Thu 11-09-08

Mon 11-09-12

71

Erecting chimney bench

0,5 days

Thu 11-09-08

Thu 11-09-08

72

Placing windows in the roof slope

1 day

Thu 11-09-08

Fri 11-09-09

73

FINISHING WORKS

24,5 days

Thu 11-09-15

Wed 11-10-19 67

74

Partition walls

1,5 days

Thu 11-09-15

Fri 11-09-16

75

Partition walls of the mutli-storey buildings with thickness 12 cm, made of lime - sand blocks, type: 2NFD

1,5 days

Thu 11-09-15

Fri 11-09-16

76

Woodwork

2 days

Thu 11-09-15

Fri 11-09-16 67

77

External door frame, double painting on the building site

0,5 days

Thu 11-09-15

Thu 11-09-15

78

External door leaf panel, prefabricated up to 2 m2

0,5 days

Thu 11-09-15

Thu 11-09-15 77

79

Windows and balcony doors made of timber, composite

2 days

Thu 11-09-15

Fri 11-09-16

80

Casement window, without ventilator, 0,5-0,7 m2

0,5 days

Thu 11-09-15

Thu 11-09-15

81

Casement window, without ventilator, 0,7-1,0 m2

0,5 days

Thu 11-09-15

Thu 11-09-15

82

Casement window, without ventilator, 1,0-1,5 m2

2 days

Thu 11-09-15

Fri 11-09-16

83

Casement window, without ventilator, 1,5-2,0 m2

1,5 days

Thu 11-09-15

Fri 11-09-16

84

Casement window, without ventilator, 2,0-3,0 m2

0,5 days

Thu 11-09-15

Thu 11-09-15

85

Door frame with expansion slot

1 day

Thu 11-09-15

Thu 11-09-15

86

Portcullises to the garage, welded to concrete door frame

1 day

Fri 11-09-16

Fri 11-09-16 85

87

Horizontal insulation

11 days

Mon 11-09-19

Mon 11-10-03 76

88

Damp and water-proof insulation, made of wide polyethylene sheeting, horizontal insulaton uder flooring

3,5 days

Mon 11-09-19

Thu 11-09-22

89

Horizontal thermal and acoustic insulation made of polystyrene7,5 days

Thu 11-09-22

Mon 11-10-03 88

90

Facade

7 days

Mon 11-09-19

Tue 11-09-27 76

91

Horizontal thermal and acoustic insulation made of polystyrene , vertical insulation with mortar with metal lath

4 days

Mon 11-09-19

Thu 11-09-22

92

Gypsum plaster of category II, external walls, mechanically made3 days

Fri 11-09-23

Tue 11-09-27 91

93

Ironwork

1 day

Thu 11-09-15

Thu 11-09-15 67

94

Stairs railing made of steel bars

0,5 days

Thu 11-09-15

Thu 11-09-15

95

Balcony railing with steel handrail

1 day

Thu 11-09-15

Thu 11-09-15

96

Internal plasters

5 days

Tue 11-10-04

Mon 11-10-10 87

97

Common plasters, mechanically made, walls, category II, buildings up to 8 floors

4 days

Tue 11-10-04

Fri 11-10-07

98

Common plasters, mechanically made, slabs , category II, buildings up to 8 floors

5 days

Tue 11-10-04

Mon 11-10-10

99

Flooring

6,5 days

Tue 11-10-11

Wed 11-10-19 96

100

Leveling layers under flooring , made of cement mortar with thickness 20 mm, trowelled

6,5 days

Tue 11-10-11

Wed 11-10-19

101

Wood flooring

5,5 days

Tue 11-10-11

Tue 11-10-18

102

Lacquering of flooring and parquets

2 days

Tue 11-10-11

Wed 11-10-12

103

Flooring made of articial stones, preparing the base

0,5 days

Tue 11-10-11

Tue 11-10-11

104

Flooring made of articial stones, plates 15x15 cm, common method

3,5 days

Tue 11-10-11

Fri 11-10-14

105

KONIEC

0 days

Wed 11-10-19

Wed 11-10-19 73

05-13

10-19

T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

09

'11 May 16

'11 May 23

'11 May 30

'11 Jun 06

'11 Jun 13

'11 Jun 20

'11 Jun 27

'11 Jul 04

'11 Jul 11

'11 Jul 18

'11 Jul 25

'11 Aug 01

'11 Aug 08

'11 Aug 15

'11 Aug 22

'11 Aug 29

'11 Sep 05

'11 Sep 12

'11 Sep 19

'11 Sep 26

'11 Oct 03

'11 Oct 10

'11 Oct 17

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 1

Project: Project1
Date: Fri 11-05-27


Wyszukiwarka

Podobne podstrony:
Microsoft Office Project Project1 strony id 299064
BYT 2005 Microsoft Office Project 2003 Professional
Microsoft Office Project Project1 siatka
Microsoft Office Project Harmonogram
Microsoft Office Project harmonogram OSTATECZNY
w aaaa1904 Microsoft Excel or Microsoft Project Why Microsoft Office Project 2007 is Easier and Mor
Microsoft Office Project harmonogram
Microsoft Office Project Project1
Cenniki bud ~$wy Dokument programu Microsoft Office Word
Nowy Dokument programu Microsoft Office Word (2)
Nowy Dokument programu Microsoft Office Word (16)
Nowy Dokument programu Microsoft Office Word (3)
Nowy Dokument programu Microsoft Office Word (19)
Nowy Dokument programu Microsoft Office Word (2)
Nowy Dokument programu Microsoft Office Word
Nowy Dokument programu Microsoft Office Word 6

więcej podobnych podstron