ID
Task Name
Duration
Start
Finish
Predecessors
1
START
0 days
Fri 11-05-13
Fri 11-05-13
2
BUILDING SITE PREPARATION WORKS
5 days
Fri 11-05-13
Thu 11-05-19
3
Mechanical stubbing
5 days
Fri 11-05-13
Thu 11-05-19
4
Erecting fencing with wickets and gates
2 days
Fri 11-05-13
Mon 11-05-16
5
Erecting gateways
0,5 days
Fri 11-05-13
Fri 11-05-13
6
Timber wickets with lath and posts, steel posts - erecting
0,5 days
Fri 11-05-13
Fri 11-05-13
7
EARTHWORKS
3 days
Fri 11-05-20
Tue 11-05-24 2
8
Removal of humus with use of dozers, thickness of the layer up to 15 cm
0,5 days
Fri 11-05-20
Fri 11-05-20
9
Measurement during foundation trench, terrain low-lying and plain
0,5 days
Fri 11-05-20
Fri 11-05-20 8
10
Earthworks with push shovel with transport of excavated material by trucks, excavator 0,4m^3, soil category I-II
2 days
Mon 11-05-23
Tue 11-05-24 9
11
FOUNDATION
14,5 days
Wed 11-05-25
Tue 11-06-14 7
12
Formwork assembling
1 day
Wed 11-05-25
Wed 11-05-25
13
Concrete subfloor on the subsoil, concrete delivery with use of wheel-barrow
1 day
Thu 11-05-26
Thu 11-05-26 12
14
Formwork disassembling
1 day
Wed 11-06-01
Wed 11-06-01 13FS+3 days
15
Foundation made of bricks with cement mortar
2 days
Thu 11-06-02
Fri 11-06-03 14
16
Damp insulation, double layer of building paper
1 day
Mon 11-06-06
Mon 11-06-06 15
17
Foundation walls made of bricks, common brick, cement mortar, thickness of 2 brick
4 days
Tue 11-06-07
Fri 11-06-10 16
18
Damp insulation of vertical surface, bulding paper, 1 layer
1 day
Mon 11-06-13
Mon 11-06-13 17
19
Backfilling of excavation with bulldozers, replacing on the distance up to 10 m , soil category I-II, bulldozer 74 kW (100 KM)
0,5 days
Tue 11-06-14
Tue 11-06-14 18
20
GROUND FLOOR
23,5 days
Tue 11-06-14
Fri 11-07-15 11
21
Floor on the soil
11,5 days
Tue 11-06-14
Wed 11-06-29
22
Subfloor made of compacted loose materials on the soil, sand
3 days
Tue 11-06-14
Fri 11-06-17
23
Formwork assembling
1 day
Fri 11-06-17
Mon 11-06-20 22
24
Concrete subfloor on the soil, concrete delivery by pump
2 days
Mon 11-06-20
Wed 11-06-22 23
25
Reinforcement of the concrete elements of the building, round ribbed steel bars, Fi 8-14 mm
1 day
Wed 11-06-22
Thu 11-06-23 24
26
Reinforced slab, concrete delivery by pump
0,5 days
Thu 11-06-23
Thu 11-06-23 25
27
Formwork disassembling
1 day
Wed 11-06-29
Wed 11-06-29 26FS+3 days
28
Walls
12 days
Thu 11-06-30
Fri 11-07-15 21
29
Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks
12 days
Thu 11-06-30
Fri 11-07-15
30
Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 1-brick
1,5 days
Thu 11-06-30
Fri 11-07-01
31
Posts and fillars made of common brick , dimension: 2x2 of brick, cement - lime mortar
1 day
Thu 11-06-30
Thu 11-06-30
32
Lintels made by using PERI formwork, ratio perimeter/cross-section: up to 8 m/m2, version 1
1 day
Thu 11-06-30
Thu 11-06-30
33
Chimney ducts made of hollow bricks
0,5 days
Thu 11-06-30
Thu 11-06-30
34
Stairs
0,5 days
Thu 11-06-30
Thu 11-06-30 21
35
Buildings made of elements OWT-67N : staircase landing
0,5 days
Thu 11-06-30
Thu 11-06-30
36
Buildings made of elements OWT-67N : flight of the stairs
0,5 days
Thu 11-06-30
Thu 11-06-30
37
FLOOR
22,5 days
Mon 11-07-18
Wed 11-08-17 20
38
Slab
10,5 days
Mon 11-07-18
Mon 11-08-01
39
Formwork assembling
1,5 days
Mon 11-07-18
Tue 11-07-19
40
DZ type slab, hollow brick DZ-3, prefabricated beams
3,5 days
Tue 11-07-19
Fri 11-07-22 39
41
DZ type slab, hollow brick DZ-3, prefabricated beams, monolithic ring beam in the external walls with thickness up to 30 cm
0,5 days
Mon 11-07-25
Mon 11-07-25 40
42
Overconcrete pouring, concrete delivery by pump
1 day
Mon 11-07-25
Mon 11-07-25 40
43
Formwork disassembling
1,5 days
Fri 11-07-29
Mon 11-08-01 42FS+3 days
44
Buildings made of elements OWT-65N: gravel concrete slab
0,5 days
Tue 11-07-19
Tue 11-07-19 39
45
Walls
12 days
Mon 11-08-01
Wed 11-08-17 38
46
Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks
12 days
Mon 11-08-01
Wed 11-08-17
47
Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks
1,5 days
Mon 11-08-01
Tue 11-08-02
48
Posts and fillars made of common brick , dimension: 2x2 of brick, cement - lime mortar
1 day
Mon 11-08-01
Tue 11-08-02
49
Lintels made by using PERI formwork, ratio perimeter/cross-section: up to 8 m/m2, version 1
1 day
Mon 11-08-01
Tue 11-08-02
50
Chimney ducts made of hollow bricks
1 day
Mon 11-08-01
Tue 11-08-02
51
ATTIC
12,5 days
Wed 11-08-17
Fri 11-09-02 37
52
Slab
10,5 days
Wed 11-08-17
Wed 11-08-31
53
Formwork assembling
1,5 days
Wed 11-08-17
Thu 11-08-18
54
DZ type slab, hollow brick DZ-3, prefabricated beams
3,5 days
Fri 11-08-19
Wed 11-08-24 53
55
DZ type slab, hollow brick DZ-3, prefabricated beams, monolithic ring beam in the external walls with thickness
0,5 days
Wed 11-08-24
Wed 11-08-24 54
56
Overconcrete pouring, concrete delivery by pump
1 day
Wed 11-08-24
Thu 11-08-25 54
57
Formwork disassembling
1,5 days
Tue 11-08-30
Wed 11-08-31 56FS+3 days
58
Wall beam
2 days
Thu 11-09-01
Fri 11-09-02 52
59
Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks
2 days
Thu 11-09-01
Fri 11-09-02
60
Chimney ducts made of hollow bricks
0,5 days
Thu 11-09-01
Thu 11-09-01
61
ROOF
8 days
Mon 11-09-05
Wed 11-09-14 51
62
Rafter framing
3,5 days
Mon 11-09-05
Thu 11-09-08
63
Collar roof with wall beam under plain tile double layered, rafter framing with span 12 m
3,5 days
Mon 11-09-05
Thu 11-09-08
64
Covering
4,5 days
Thu 11-09-08
Wed 11-09-14 62
65
Damp and water-proof insulation made of wide polyethylene sheeting, horizontal insulaton uder flooring
2 days
Thu 11-09-08
Mon 11-09-12
66
Thermal and acoustic insulation made of mineral wool, vertical 1,5 days
Thu 11-09-08
Fri 11-09-09
67
Placing asphalt shingles with width 8 cm
4,5 days
Thu 11-09-08
Wed 11-09-14
68
Roof gutter made of galvanized iron, semicircular with diameter 15 cm
1 day
Thu 11-09-08
Fri 11-09-09
69
Downpipe made of galvanized iron, semicircular with diameter 15 cm
1 day
Thu 11-09-08
Fri 11-09-09
70
Different treatment made of galvanized iron with width up to 25 cm2 days
Thu 11-09-08
Mon 11-09-12
71
Erecting chimney bench
0,5 days
Thu 11-09-08
Thu 11-09-08
72
Placing windows in the roof slope
1 day
Thu 11-09-08
Fri 11-09-09
73
FINISHING WORKS
24,5 days
Thu 11-09-15
Wed 11-10-19 67
74
Partition walls
1,5 days
Thu 11-09-15
Fri 11-09-16
75
Partition walls of the mutli-storey buildings with thickness 12 cm, made of lime - sand blocks, type: 2NFD
1,5 days
Thu 11-09-15
Fri 11-09-16
76
Woodwork
2 days
Thu 11-09-15
Fri 11-09-16 67
77
External door frame, double painting on the building site
0,5 days
Thu 11-09-15
Thu 11-09-15
78
External door leaf panel, prefabricated up to 2 m2
0,5 days
Thu 11-09-15
Thu 11-09-15 77
79
Windows and balcony doors made of timber, composite
2 days
Thu 11-09-15
Fri 11-09-16
80
Casement window, without ventilator, 0,5-0,7 m2
0,5 days
Thu 11-09-15
Thu 11-09-15
81
Casement window, without ventilator, 0,7-1,0 m2
0,5 days
Thu 11-09-15
Thu 11-09-15
82
Casement window, without ventilator, 1,0-1,5 m2
2 days
Thu 11-09-15
Fri 11-09-16
83
Casement window, without ventilator, 1,5-2,0 m2
1,5 days
Thu 11-09-15
Fri 11-09-16
84
Casement window, without ventilator, 2,0-3,0 m2
0,5 days
Thu 11-09-15
Thu 11-09-15
85
Door frame with expansion slot
1 day
Thu 11-09-15
Thu 11-09-15
86
Portcullises to the garage, welded to concrete door frame
1 day
Fri 11-09-16
Fri 11-09-16 85
87
Horizontal insulation
11 days
Mon 11-09-19
Mon 11-10-03 76
88
Damp and water-proof insulation, made of wide polyethylene sheeting, horizontal insulaton uder flooring
3,5 days
Mon 11-09-19
Thu 11-09-22
89
Horizontal thermal and acoustic insulation made of polystyrene7,5 days
Thu 11-09-22
Mon 11-10-03 88
90
Facade
7 days
Mon 11-09-19
Tue 11-09-27 76
91
Horizontal thermal and acoustic insulation made of polystyrene , vertical insulation with mortar with metal lath
4 days
Mon 11-09-19
Thu 11-09-22
92
Gypsum plaster of category II, external walls, mechanically made3 days
Fri 11-09-23
Tue 11-09-27 91
93
Ironwork
1 day
Thu 11-09-15
Thu 11-09-15 67
94
Stairs railing made of steel bars
0,5 days
Thu 11-09-15
Thu 11-09-15
95
Balcony railing with steel handrail
1 day
Thu 11-09-15
Thu 11-09-15
96
Internal plasters
5 days
Tue 11-10-04
Mon 11-10-10 87
97
Common plasters, mechanically made, walls, category II, buildings up to 8 floors
4 days
Tue 11-10-04
Fri 11-10-07
98
Common plasters, mechanically made, slabs , category II, buildings up to 8 floors
5 days
Tue 11-10-04
Mon 11-10-10
99
Flooring
6,5 days
Tue 11-10-11
Wed 11-10-19 96
100
Leveling layers under flooring , made of cement mortar with thickness 20 mm, trowelled
6,5 days
Tue 11-10-11
Wed 11-10-19
101
Wood flooring
5,5 days
Tue 11-10-11
Tue 11-10-18
102
Lacquering of flooring and parquets
2 days
Tue 11-10-11
Wed 11-10-12
103
Flooring made of articial stones, preparing the base
0,5 days
Tue 11-10-11
Tue 11-10-11
104
Flooring made of articial stones, plates 15x15 cm, common method
3,5 days
Tue 11-10-11
Fri 11-10-14
105
KONIEC
0 days
Wed 11-10-19
Wed 11-10-19 73
05-13
10-19
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
09
'11 May 16
'11 May 23
'11 May 30
'11 Jun 06
'11 Jun 13
'11 Jun 20
'11 Jun 27
'11 Jul 04
'11 Jul 11
'11 Jul 18
'11 Jul 25
'11 Aug 01
'11 Aug 08
'11 Aug 15
'11 Aug 22
'11 Aug 29
'11 Sep 05
'11 Sep 12
'11 Sep 19
'11 Sep 26
'11 Oct 03
'11 Oct 10
'11 Oct 17
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 1
Project: Project1
Date: Fri 11-05-27