var nodeInfo=[{view: "view:_LVCagP5WEdmAzesbYywanQ", path: ["_LVCagP5WEdmAzesbYywanQ", "_4U33kAILEdq-_NKqZM1EhA", "_qIh6UABuEdqrKcHWz1HoWw", "{EE97A8CD-66CA-4A9B-9871-E3B94CCED528}", "{18DB40A1-6272-467A-AC68-B2C4BE1DCD6C}"]}, {view: "view:_LVCagP5WEdmAzesbYywanQ", path: ["_LVCagP5WEdmAzesbYywanQ", "_4U33kAILEdq-_NKqZM1EhA", "_U8LVkAIUEdqEutyfYo0quQ", "_C49xgP_UEdmVCcs_BRqacA", "{18DB40A1-6272-467A-AC68-B2C4BE1DCD6C}"]}, {view: "view:_FCx1oN7CEdmsEI4YDGX2ag", path: ["_FCx1oN7CEdmsEI4YDGX2ag", "_f6_YwN7DEdmsEI4YDGX2ag", "_qIh6UABuEdqrKcHWz1HoWw", "{EE97A8CD-66CA-4A9B-9871-E3B94CCED528}", "{18DB40A1-6272-467A-AC68-B2C4BE1DCD6C}"]}, {view: "view:_FCx1oN7CEdmsEI4YDGX2ag", path: ["_FCx1oN7CEdmsEI4YDGX2ag", "_Jvt1cAIaEdqEutyfYo0quQ", "_EOvXUN7HEdm8G6yT7-Wdqw", "_C49xgP_UEdmVCcs_BRqacA", "{18DB40A1-6272-467A-AC68-B2C4BE1DCD6C}"]}, {view: "view:_FCx1oN7CEdmsEI4YDGX2ag", path: ["_FCx1oN7CEdmsEI4YDGX2ag", "_Jvt1cAIaEdqEutyfYo0quQ", "_jijhYAIaEdqEutyfYo0quQ", "_qUsPIN7REdmjRZts2c4ZjQ", "{18DB40A1-6272-467A-AC68-B2C4BE1DCD6C}"]}];
contentPage.preload(imgPath, backPath, nodeInfo, '', false, false, false);
Artifact: Work Order
This artifact is the Project Manager's means of communicating what is to be done, and when, to the responsible staff. It becomes an internal contract between the Project Manager and those assigned responsibility for completion.
Domains: Project Management
Work Product Kinds: Project Data
Purpose
The purpose is to turn planning into action within Iterations.
Relationships
RolesResponsible:
Project Manager
Modified By:
Project Manager
TasksInput To:
Output From:
Initiate Iteration
Schedule and Assign Work
Process Usage
Configuration & Change Management
>
Manage Baselines & Releases
>
Work Order
Configuration & Change Management
>
Change and Deliver Configuration Items
>
Work Order
Configuration & Change Management
>
Manage Change Requests
>
Work Order
Project Management
>
Monitor & Control Project
>
Work Order
Project Management
>
Manage Iteration
>
Work Order
Test
>
Define Evaluation Mission
>
Work Order
Description
Main Description
The work order is a negotiated agreement between the Project Manager and the staff to perform a
particular task, or set of tasks, under a defined schedule and with certain deliverables, effort, and resource
constraints.
Work Orders become internal contracts between the Project Manager and those assigned responsibility for their
completion.
Brief Outline
1. Identification
Uniquely identifies the project and the work order.
2. Work Breakdown Structure (WBS) identification
Identifies the activity (in the project plan) associated with this work order. Effort expended on this work order
will be allocated to this activity for tracking.
3. Responsibility
Organizational positions responsible for fulfilling the work order.
4. Associated Change Requests
References to Change Requests that are associated with this work order (those that were the stimulus for it or
those that will be fixed coincidentally).
5. Schedule
The schedule covers the estimated start and completion dates, and the critical path completion date.
6. Effort and other resources
Addresses the staff-hours, total and over time, as well as other resource budgets; for example, development
environment time, test environment time.
7. Description of work and expected outputs
Describes what is to be done and what is to be produced-references the Rational Unified Process description of the
tasks to be performed and work products to be produced, or the development case, as appropriate.
8. Indication of agreement between Project Manager and responsible staff
The work order should be signed and dated by the holder of the responsible position (usually a team lead) and the
Project Manager.
Tailoring
Representation Options
The work order is the mechanism by which the Project Manager communicates plans to project members. On small projects
this could be as simple as discussing a plan on a whiteboard and then confirming agreements through e-mail. On large,
very structured projects perhaps some form of automated activity management is used, where the Project Manager injects
formal directions that appear to the team members in to-do lists (maybe with some protocol for agreement).
Another option is to use an automated change request management system, extended so that all work on a project
(not just defects) is described in change requests, and the directions to perform work are implemented as actions
(through, say email, or through an integration with an automated activity management system) that are triggered by
state changes in the change request management process. See the Tool Mentor: Establishing a Change Request Process Using Rational ClearQuest for an example of how an automated change management process, which triggers external actions, can be
set up.
More Information
Guidelines
Estimating Effort Using the Wide-Band Delphi Technique
Work Order â€" Informal Representation
© Copyright IBM Corp. 1987, 2006. All Rights Reserved.
contentPage.onload();
Wyszukiwarka
Podobne podstrony:
rup work order?1CF834rup work orderN93887Awork order informal representation?794F54rup work order95F104rup process engineerQCC276E121010141958?c english at work episode6rup stakeholder11D446120702094621 english at work episode! finalrup test manager?449E26więcej podobnych podstron