var nodeInfo=[{view: "view:_LVCagP5WEdmAzesbYywanQ", path: ["_LVCagP5WEdmAzesbYywanQ", "_4U33kAILEdq-_NKqZM1EhA", "_qIh6UABuEdqrKcHWz1HoWw", "{EE97A8CD-66CA-4A9B-9871-E3B94CCED528}", "{50A77708-4FD4-42F5-B6D1-4DC751C7EBBE}"]}, {view: "view:_LVCagP5WEdmAzesbYywanQ", path: ["_LVCagP5WEdmAzesbYywanQ", "_4U33kAILEdq-_NKqZM1EhA", "_nB0hwAITEdqu-LkyOdB8SQ", "_yeA1y9nmEdmO6L4XMImrsA", "{50A77708-4FD4-42F5-B6D1-4DC751C7EBBE}"]}, {view: "view:_FCx1oN7CEdmsEI4YDGX2ag", path: ["_FCx1oN7CEdmsEI4YDGX2ag", "_f6_YwN7DEdmsEI4YDGX2ag", "_qIh6UABuEdqrKcHWz1HoWw", "{EE97A8CD-66CA-4A9B-9871-E3B94CCED528}", "{50A77708-4FD4-42F5-B6D1-4DC751C7EBBE}"]}, {view: "view:_FCx1oN7CEdmsEI4YDGX2ag", path: ["_FCx1oN7CEdmsEI4YDGX2ag", "_kC0pcN7GEdm8G6yT7-Wdqw", "_yeA1y9nmEdmO6L4XMImrsA", "{50A77708-4FD4-42F5-B6D1-4DC751C7EBBE}"]}];
contentPage.preload(imgPath, backPath, nodeInfo, '', true, false, false);
Task: Initiate Iteration
This task describes how to allocate staff and other resources to the activities identified for the current iteration.
Disciplines: Project Management
Relationships
RolesPrimary Performer:
Project Manager
Additional Performers:
InputsMandatory:
Iteration Plan
Software Development Plan
Optional:
None
Outputs
Work Order
Process Usage
Project Management
>
Manage Iteration
>
Initiate Iteration
Main Description
In the Initiate Iteration task the project manager allocates the staff and non-personnel resources of the project to
each of the activities that will be completed this iteration, as defined in the current Iteration Plan.
Steps
Assign Staff to Activities
For each activity, the project manager assigns staff with appropriate skills to carry out the work. Remember to follow
sound project management practice and balance the overall workload for each individual assigned.
Acquire and Assign Non-Personnel Resources
Some activities will require the use of specialized non--personnel resources (e.g. dedicated CPU time on a mainframe,
use of specialized testing hardware). For each of these activities, the project manager should secure the availability
of the necessary resources and establish a schedule for their usage
Issue Work Orders
Once the staff and other resources have been allocated to the activities for the current iteration, the project manager
documents these assignments in a series of work orders. The work orders are then issued to the project team for
execution.
© Copyright IBM Corp. 1987, 2006. All Rights Reserved.
contentPage.onload();
Wyszukiwarka
Podobne podstrony:
Plan Remainder of Initial Iteration?FF0FA5Plan Remainder of Initial Iteration?FF0FA5Plan Remainder of Initial Iteration?FF0FA5initiate iteration?7F1824Plan Remainder of Initial Iteration?FF0FA5initialcontentinitialcontentplan for next iteration?CDF5ABplan for next iteration?855DCDplan for next iteration?CDF5ABiterator?tegorymanage iteration+95C965InitialContextFactoryBuilderprepare environment for an iteration@2D3B0Afront insert iteratorplan for next iterationU840038więcej podobnych podstron