Task: Report Status
var backPath = './../../';
var imgPath = './../../images/';
var nodeInfo=[{view: "view:_LVCagP5WEdmAzesbYywanQ", path: ["_LVCagP5WEdmAzesbYywanQ", "_4U33kAILEdq-_NKqZM1EhA", "_qIh6UABuEdqrKcHWz1HoWw", "{EE97A8CD-66CA-4A9B-9871-E3B94CCED528}", "{F77A1270-3F63-4B44-894D-37316D046445}"]}, {view: "view:_LVCagP5WEdmAzesbYywanQ", path: ["_LVCagP5WEdmAzesbYywanQ", "_4U33kAILEdq-_NKqZM1EhA", "_nB0hwAITEdqu-LkyOdB8SQ", "_yeA1y9nmEdmO6L4XMImrsA", "{F77A1270-3F63-4B44-894D-37316D046445}"]}, {view: "view:_FCx1oN7CEdmsEI4YDGX2ag", path: ["_FCx1oN7CEdmsEI4YDGX2ag", "_f6_YwN7DEdmsEI4YDGX2ag", "_qIh6UABuEdqrKcHWz1HoWw", "{EE97A8CD-66CA-4A9B-9871-E3B94CCED528}", "{F77A1270-3F63-4B44-894D-37316D046445}"]}, {view: "view:_FCx1oN7CEdmsEI4YDGX2ag", path: ["_FCx1oN7CEdmsEI4YDGX2ag", "_kC0pcN7GEdm8G6yT7-Wdqw", "_yeA1y9nmEdmO6L4XMImrsA", "{F77A1270-3F63-4B44-894D-37316D046445}"]}];
contentPage.preload(imgPath, backPath, nodeInfo, '', true, false, false);
Task: Report Status
This task describes how to provide periodic updates on the project status.
Disciplines: Project Management
Purpose
Provide regular updates on project status for review by the Project Review Authority (PRA)
Escalate issues beyond the project manager's authority for resolution by the PRA
Relationships
RolesPrimary Performer:
Project Manager
Additional Performers:
InputsMandatory:
None
Optional:
Risk List
Status Assessment
Outputs
Status Assessment
Process Usage
Project Management
>
Monitor & Control Project
>
Report Status
Steps
Prepare Status Assessment
Purpose
Document the current project status for review by the PRA
Status Assessment can be conveyed through the Artifact: Status Assessment drawn from the Issues List and the Project Measurements that result from the Task: Monitor Project Status. Status Assessment should address the
following:
Technical progress:
Work completed during this reporting period (e.g. tasks completed, work products delivered). Highlight any
slippage.
For the current iteration, report any possible change in scope or quality (in terms of discovered
defects that will not be rectified) required to keep the iteration to the planned end date (i.e. to
keep it 'timeboxed').
Budget progress:
Spending to date. Highlight any cost over-runs.
Progress against scheduled milestones:
Were scheduled milestones achieved?
Total project/product scope:
Report on the revised estimate for the project scope based on work done and estimates to complete work in
progress.
Personnel/staffing status:
Status of personnel. Report any issues or concerns.
Risk status:
Are any risks becoming realized?
Issues arising:
Project issues requiring PRA resolution. Recommend potential solutions for consideration.
Action items:
A list of action items from previous status assessments and their current status.
The Status Assessment report is usually published to the PRA and reviewed during the PRA Project Review.
© Copyright IBM Corp. 1987, 2006. All Rights Reserved.
contentPage.onload();
Wyszukiwarka
Podobne podstrony:
report statusf1264A5monitor report configuration status?386928monitor report configuration status?386928report review work statusT297CBDStatus reportingSmolensk Crash Status Reportmonitor report configuration status?386928monitor report configuration status?D3A3A4monitor report configuration status?D3A3A4monitor report configuration status?386928report?fect trends status45B6B16report?fect trends status45B6B16Status Reportwięcej podobnych podstron