October 6, 1999 1.0 Initial version Context Integration
October 27, 1999 2.0 Updated at start of Elaboration Context Integration
Table of Contents
Introduction Plan Resources Use Cases Evaluation Criteria Iteration Plan Introduction Purpose This Iteration Plan describes the detailed plans for the Elaboration Iteration of the Collegiate Sports Paging System Project. During this iteration, the design of the system will be defined and the high level plan for execution of the full project will be refined. Scope The Elaboration Iteration Plan applies to the Collegiate Sports Paging System project being developed by Context Integration for WebNewsOnLine. This document will be used by the Project Manager and by the project team. Definitions, Acronyms and Abbreviations See Glossary document. References
CSPS Iteration Plan 1.0.doc
Plan The Elaboration Iteration will complete the analysis of requirements. The analysis and design for all use cases will be completed. The architectural prototype will be developed to test the feasibility and performance of the architecture that is required for Release 1.0. Iteration Tasks The following table illustrates the tasks with their planned start and end dates.
Task
Start
End
ELABORATION Mon 10/25/99 Fri 11/26/99
Begin Elaboration Mon 10/25/99 Tue 10/26/99
Elaboration Kick-off Tue 10/26/99 Fri 10/29/99
Add tasks to project plan for specific project technology using ContextWISE cartridges Fri 10/29/99 Fri 10/29/99
Detailed requirements development Tue 11/2/99 Thu 11/4/99
Complete Elaboration Use Case Model Wed 11/3/99 Wed 11/3/99
Use-Case-Model Survey created, reviewed, and signed off Wed 11/3/99 Wed 11/3/99
Supplementary Specifications updated, reviewed and baselined Tue 11/2/99 Tue 11/2/99
Project Glossary updated, reviewed, and signed off Tue 11/2/99 Wed 11/3/99
Site Map & Use-Case Navigation Mapping updated, reviewed, and signed off Tue 11/2/99 Wed 11/3/99
Content Plan updated, reviewed, and signed off (if applicable) Tue 11/2/99 Wed 11/3/99
Detailed user-interface prototype created, reviewed, and signed off Tue 11/2/99 Wed 11/3/99
Detailed reports prototype created, reviewed, and signed off Tue 11/2/99 Wed 11/3/99
User Manual/Specification/Help and Training created, reviewed, and signed off Wed 11/3/99 Wed 11/3/99
Obtain Sign-off Wed 11/3/99 Thu 11/4/99
Detailed requirements development complete Thu 11/4/99 Thu 11/4/99
Plans revised and updated Thu 11/4/99 Fri 11/5/99
Iterative Delivery Project Plan updated, reviewed, and signed off Thu 11/4/99 Thu 11/4/99
Software Development Plan created, reviewed, and signed off Thu 11/4/99 Thu 11/4/99
Knowledge Transfer Plan & Schedule updated, reviewed, and signed off Thu 11/4/99 Thu 11/4/99
Project estimates updated (accurate to +65%, -40%) Thu 11/4/99 Thu 11/4/99
Revise Business Case Thu 11/4/99 Thu 11/4/99
Reduce documentation staff (unless other significant documentation products will be produced) Thu 11/4/99 Thu 11/4/99
Documentation staff reduced after completing User Manual/Specification/Help (unless other significant documentation products will be produced) Thu 11/4/99 Fri 11/5/99
Have team, including client project manager, complete the work release sign-off form Thu 11/25/99 Thu 11/25/99
Elaboration Checkpoint Review and Go/No Go Decision Thu 11/25/99 Thu 11/25/99
Move appropriate deliverables from Project Homepage to IAN Artifacts Thu 11/25/99 Fri 11/26/99
Elaboration Complete Fri 11/26/99 Fri 11/26/99
The following deliverables or artifacts will be generated and reviewed during the Elaboration Iteration:
Artifact Set Deliverable Responsible Owner
Business Modeling Set Glossary (expand & update) Brian Egler
Requirements Set Vision Document (update) Use Case Specifications (update) Supplementary Specification (update) Use Case Model and Model Survey (update) User-Interface Prototype (forms only) Brian Egler Brian Egler Ed Post Ken Perch Mark Grimes
Design Set Analysis Model (Logical View) Design Model (Logical, Component & Process Views) Software Architecture Document Ken Perch Ken Perch Ken Perch
Implementation Set Integration Build Plan Architectural Prototype - Software Baseline Test Drivers, Stubs, Data, & Scripts Test Procedures Test Evaluation Report Mary Durham Ken Perch Mike Hunziker Chris Curvey Mary Durham
Management Set Iteration Plan Project Plan (update) Project Schedule (update) Project Risk List (update) Status Assessment Iteration Assessment Test Plan Mary Durham Mary Durham Mary Durham Mary Durham Mary Durham Mary Durham Mary Durham
Standards and Guidelines Design Guidelines User-Interface Guidelines Ken Perch Mark Grimes
Resources Staffing The project staffing for this iteration can be viewed as follows:
Financial Resources The budget for this iteration is $180,000. WebNewsOnLine has secured this funding. Use Cases Use cases to be developed during this iteration are:
Approve Story Edit Profile Pay Fee With Credit Card Print Advertiser Reports Provide Feedback Read Content on Web Site Send Content Send Page Subscribe
Evaluation Criteria The primary goal of this iteration is to complete the analysis and design of selected use cases and to develop a working architectural prototype. Risk associated with the architectural design or system performance will be realized by the end of the iteration. Each deliverable developed during the iteration will be peer reviewed and subject to approval from the team. The internal project team and the Subscriber, Advertiser, and Editor representatives will review the User-Interface Prototype and the Architectural Prototype.