Activity: Refine the Development Plan
This activity refines the Software Development Plan, as needed.
DescriptionWork Breakdown StructureTeam AllocationWork Product Usage
Relationships
Parent Activities
Project Management
Description
The Software Development Plan was created and reviewed early in the inception phase. Thereafter, generally at the
beginning of each iteration, the Software Development Plan (and its enclosures) may need revision, based on the
previous iteration's experience and the Iteration Plan for the next. The Project Manager also collates all other
contributions to the Software Development Plan and assemble them in Task: Compile Software Development Plan.
Properties
Event Driven
Multiple Occurrences
Ongoing
Optional
Planned
Repeatable
Staffing
This activity will obviously stress the Project Manager's estimation, planning and writing skills. Also, the Project
Manager must ensure buy-in from affected stakeholders during the construction of these plans, so presentation and
communication skills will also be important. The Management Reviewer will need to be experienced in the estimation of
projects in the relevant business or technical domain and should be able to make judgments about the validity of
assumptions made by the Project Manager. The Management Reviewer should also have enough understanding of the Rational
Unified Process to judge whether the Development Case is accurately represented in the Software
Development Plan.
Usage
Usage Guidance
This activity typically occurs at the beginning of each iteration.
Estimation should ideally be based in the organization's own experience, which is then used to calibrate an estimation
model, such as COCOMO. (See [BOE81] for a description
of the original model, or go to http://sunset.usc.edu/research/cocomosuite/index.html for the latest work.) If the Project Manager
is starting from scratch, using default values for model coefficients, it will be important to use other methods to
validate the estimates. Just as important is to obtain staff and other stakeholder agreement that the estimates are
realistic and achievable. However, the Project Manager has to take into account the experience of staff giving feedback
about estimates. More junior staff may be just guessing numbers and then adding large margins for error; conversely,
their effort estimates may be naively low. The Project Manager must be circumspect when dealing with estimates from
junior staff, and be prepared to counsel them when necessary, and offer the assistance of a more experienced peer. See
Task: Plan Phases and Iterations for more information about
estimation.
All enclosed plans and sections of the Software Development Plan should be evaluated through internal walkthroughs and
reviews before the Project Planning Review occurs.
© Copyright IBM Corp. 1987, 2006. All Rights Reserved.
contentPage.onload();
Wyszukiwarka
Podobne podstrony:
Refine the Project Plan?25A642Refine the Project Plan?25A642Refine the Project Plan?25A642refine the architecture?F2AA31plan the project3DD2BC3plan the project?2EE35plan the project3DD2BC3refine the system?finition5160221plan the project?2EE35refine the architecture?F2AA31refine the architecture?F2AA31refine the system?finition5160221refine the system?finition5160221plan the project?EB621Arefine the system?finition?7B8011refine the architecture?F2AA31refine the architecture?0FA195refine the system?finition?7B8011więcej podobnych podstron