Inspect for signs of overheating
Presence of phase barriers and shrouds
Presence of labels
Check connections for tightness
Is access to switchgear impeded
Are the duties of the circuits marked up
Verify the neutral connections are in the same order as the phase conductors
Check operation of switches
Check operation of rcd units on test button
Check for damage or holes in casing
Are necessary warning labels in position
Carry out insulation testing
Verify the number of cables enclosed does not exceed the spacing factor
Verify the segregation of cables contained in the trunking is correct.
Verify the earth continuity of the trunking
Verify the presence of phase barriers
Check for damage and holes
Check trunking is correctly supported
Check for missing lid
Check for incorrect jointing of cabled within trunking
Check for damage
Check the condition of the central battery unit
Verify the emergency lighting is connected to the correct circuits zones
Check for presence of test switches
Check for presence of testing record sheets
Check for damaged fittings
Sub Main Cables
Verify the cables are correctly supported
Check for damage to cables
Check for incorrect terminations
Extension Leads And Portable Appliances
Check for presence of testing labels
Carry out testing if applicable
Site Documentation
Check for presence of main switchgear location plan
Check for presence of schematic plan