i m s
TASK
RESOURCE
REPORT
PROJECT
VIEW
GANTT CHART TOOLS FORMAT
Al IŁ
MS Project Filtering v3.mpp - Project Standard
? - & X
Sign in
& X
1
[No Highlight] ^
Timescale.
Gantt Chart ^
Task
Usage
1153 NetWork Diagram -[0 Calendar ”■
5 Other Views -
O
Resource Sheet -
f[2 Resource Usage -Other Views -
Z
Sort
B
Outline Tables
Highlight: T Filten Si Group by:
[No Filter]
[No Group]
Days
GANTT CHART
Task Views |
Resource Views |
Data | ||||||
e |
Task Modę ▼ |
TaskName ▼ |
Total Slack |
▼ Duration |
▼ Start ▼ |
Finish ▼ |
Predecessors ▼ | |
1 |
% |
Notice to Proceed |
0 days |
0 days |
Mon 1/5/15 |
Mon 1/5/15 | ||
2 |
% |
Project Start |
0 days |
0 days |
Tue 1/6/15 |
Tue 1/6/15 |
1SS+20 hrs | |
3 |
m |
* Mobilization |
0 days |
10 days |
Wed 1/7/15 |
Thu 1/22/15 | ||
4 |
Mobilize |
0 days |
10 days |
Wed 1/7/15 |
Thu 1/22/15 |
2SS | ||
5 |
m |
' Construction |
0 days |
34 days |
Mon 1/26/15 |
Tue 3/24/15 | ||
6 |
m |
* Below Grade |
0 days |
13 days |
Mon 1/26/15 |
Mon 2/16/15 | ||
7 |
% |
Grade Site |
4 days |
8 days |
Mon 1/26/15 |
Thu 2/5/15 |
4 | |
8 |
Set Foundations |
0 days |
9 days |
Mon 1/26/15 |
Mon 2/9/15 |
4 | ||
9 |
? |
Install Conduit |
12 days |
3 days |
Mon 2/9/15 |
Wed 2/11/15 |
7 | |
10 |
? |
Dig Cable Trench |
0 days |
4 days |
Tue 2/10/15 |
Mon 2/16/15 |
8 | |
11 |
m |
* Above Grade |
2 days |
23 days |
Thu 2/12/15 |
Tue 3/24/15 | ||
12 |
? |
Erect Steel Structures |
12 days |
8 days |
Thu 2/12/15 |
Wed 2/25/15 |
9 | |
13 |
? |
Install Equipment |
0 days |
6 days |
Tue 2/17/15 |
Wed 2/25/15 |
10 | |
14 |
? |
Install Grounding |
18 days |
2 days |
Thu 2/26/15 |
Mon 3/2/15 |
12 | |
15 |
? |
Install Bus and Jumpers |
12 days |
8 days |
Thu 2/26/15 |
Wed 3/11/15 |
12 | |
16 |
? |
Lay Control Cable |
0 days |
12 days |
Wed 3/4/15 |
Tue 3/24/15 |
13FS+30 hrs | |
17 |
m |
* Fence |
4 days |
7 days |
Mon 2/9/15 |
Wed 2/18/15 | ||
18 |
m |
Install Fence |
4 days |
7 days |
Mon 2/9/15 |
Wed 2/18/15 |
7 | |
19 |
m |
* Site Restoration |
0 days |
26 days |
Tue 2/17/15 |
Wed 4/1/15 | ||
20 |
Remove Equipment |
0 days |
5 days |
Wed 3/25/15 |
Wed 4/1/15 |
16 | ||
21 |
% |
Lay Stoning |
24 days |
2 days |
Tue 2/17/15 |
Wed 2/18/15 |
10 | |
22 |
% |
Lay Roadway |
22 days |
4 days |
Tue 2/17/15 |
Mon 2/23/15 |
10 | |
23 |
m |
* Project Closeout |
0 days |
10 days |
Thu 4/2/15 |
Mon 4/20/15 | ||
24 |
Substaintial Completion |
0 days |
10 days |
Thu 4/2/15 |
Mon 4/20/15 |
14,15,18,20,21,22 | ||
25 |
m |
Project Complete |
0 days |
0 days |
Mon 4/20/15 |
Mon 4/20/15 |
24 |
F S
Zoom Entire Selected ^ Project Tasks
Timeline
Details
cP1 Switch Windows -
0 Arrange Ali
Jan 4, 15 S M T
W T F S
Split View Jan 11,15 S M T
W T F S
Window Jan 18,15
S M T W T F S
Macros
▼
Macros Jan 25,15 S M T
W T
A
Febl, 15 Feb8,15 Feb 15,15 E
SMTWT FSSMTWT FSSMTWT FS
-<► Notice to Proceed 4 Project Start
r
i
Mobilize
Grade Site