ZESTAWIENIE DZIAŁÓW KOSZTORYSU
Lp. Nazwa działu |
Od |
Do |
1 STUDNIA GŁĘBINOWA NR 3 |
1 18 | |
1.1 PRACE DEMONTAŻOWE |
1 6~ | |
1.2 PRACE MONTAŻOWE |
7 18 | |
2 STUDNIA GŁĘBINOWA NR 4 |
19 |
33 |
2.1 PRACE MONTAŻOWE |
19 |
33 |
3 STACJA UZDATNIANIA WODY |
34 |
|237 |
3.1 ROBOTY DEMONTAŻOWE |
34 |
37 |
3.2 ROBOTY MONTAŻOWE |
38_ |
[107 |
3.4 POMPOWNIE II-GO STOPNIA |
126 |
139 |
3.5 INSTALACJA DOZOWANIA PODCHLORYNU SODU |
140 |
147 |
3.61 INSTALACJA OSUSZANIA |
148 |
148 |
3.7IWEWN. INSTALACJE SANITARNE |
149 |
[236 |
3.7. INSTALACJA WODY UŻYTKOWEJ 1 |
149 |
|171 |
3.7. WEWNĘTRZNA KANALIZACJA WOD PRZYPADKOWYCH 2 |
172 |
185 |
3.7. KANALIZACJA CHEMICZNA 3 |
186 |
210 |
3.7. INSTALACJA WENTYLACJI 4 |
211 |
226 |
3.7. INSTALACJA OGRZEWANIA HALI TECHNOLOG. 5 |
227 |
227 |
3.7. INSTALACJE POMIESZCENIA AGREGATU PRĄDOTW. 6 |
228 |
236 |
3.8 ROZRUCH WRAZ Z PRACAMI TOW. STACJI TYMCZASOWEJ |
237 |
237 |
4|ODSTOJNIK WÓD POPŁUCZNYCH._ |
238 |
246 |
6 ZEWNĘTRZNA KANALIZACJA WÓD PRZYPADKOWYCH |
262 |
|275 |
7 RUROCIĄG WODY UZDATNIONEJ DO KOMORY ZASUW ZBIORNIKA MAGAZYNOWEGO 8 RUROCIĄG WODY UZDATNIONEJ Z KOMORY ZASUW ZBIORNIKA MAGAZYNOWEGO |
276 |
[292 |
293 |
309 | |
9;RUROCIĄG WODY SUROWEJ ZE STUDNI NR 3 |
310 |
[326 |
10;RUROCIĄG WODY SUROWEJ ZE STUDNI NR 4 |
327 |
342 |
11 [RUROCIĄG TRANZYTOWY "MIASTO" |
343 |
360 |
13■ budowa' i wymiana kanału wód przelewowych ze zbiornika kontaktowego |
380 |
1391 |
hIczyszczenie i umocnienie rowu melioracyjnego |
392 |
398 |
-2-