September October November December January February March April May June
ID Task Name Duration 8/19 8/26 9/2 9/9 9/16 9/23 9/30 10/7 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17 2/24 3/3 3/10 3/17 3/24 3/31 4/7 4/14 4/21 4/28 5/5 5/12 5/19 5/26 6/2 6/9
1 Project Management 214 days
2 Project Kickoff Meeting 1 day
3 Existing System Evaluation 10 days
4 Project Scope Definition 10 days
5 Detailed Design Specifica 71 days
6 Preliminary Specifica 54 days
7 General Specifica 18 days
8 Sequence of Op 11 days
9 Preliminary D 5 days
10 Design Revi 1 day
11 Design Final 5 days
12 PLC Standard S 16 days
13 Preliminary D 10 days
14 Design Revi 1 day
15 Design Final 5 days
16 Operator Interfa 16 days
17 Graphics De 10 days
18 Graphics De 1 day
19 Graphics De 5 days
20 Logic Softwa 5 days
21 Control Panels 11 days
22 Layout - Pre 5 days
23 Layout - Rev 1 day
24 Layout - Fina 5 days
25 SCADA System 21 days
26 Database 10 days
27 Control Logi 5 days
28 Screen Arch 5 days
29 Graphics De 10 days
30 Graphics De 1 day
31 Graphics De 5 days
32 Local Area Netw 16 days
33 LAN Design 10 days
34 LAN Design 1 day
35 LAN Design 5 days
36 Specification Managem 5 days
37 Specification Finalize 10 days
38 System Development 61 days
39 Programmable Contr 36 days
40 Software Config 25 days
41 Memory Map 5 days
42 Standard So 10 days
43 Control Logi 10 days
44 Software Docum 11 days
45 Documentat 5 days
46 Documentat 1 day
47 Documentat 5 days
48 Operator Interfaces 25 days
49 Software Configu 15 days
50 Documentation 10 days
51 Control Panels 30 days
52 Fabrication 20 days
Task Progress Summary Rolled Up Split Rolled Up Progress Project Summary
Project: Project
Date: Thu 10/31/02
Split Milestone Rolled Up Task Rolled Up Milestone External Tasks
Page 1
September October November December January February March April May June
ID Task Name Duration 8/19 8/26 9/2 9/9 9/16 9/23 9/30 10/7 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17 2/24 3/3 3/10 3/17 3/24 3/31 4/7 4/14 4/21 4/28 5/5 5/12 5/19 5/26 6/2 6/9
53 Delivery 10 days
54 SCADA System 20 days
55 Database Configu 10 days
56 Control Logic Con 5 days
57 Graphics Configu 20 days
58 Local Area Networks 5 days
59 Speed Test 5 days
60 PC's 5 days
61 Archive Data/Alar 5 days
62 Disaster Recover 5 days
63 Configuration File 5 days
64 Documentation 187 days
65 Drawings - Pre-Cons 75 days
66 P&ID Drawings 20 days
67 Input/Output Layo 10 days
68 Panel Drawings 10 days
69 LAN Architecture 5 days
70 DC Power Distrib 2 days
71 AC Power Distrib 2 days
72 Drawings - As Built 10 days
73 Manuals 25 days
74 Hardware Manua 5 days
75 Operations Manu 15 days
76 Maintenance Man 5 days
77 PLC Manual 5 days
78 OI Manual 5 days
79 Programming Ma 5 days
80 SCADA Manual 5 days
81 Manuals - As Built 2 days
82 Hard/Soft Copy Delivery 5 days
83 In house Preliminary Syste 20 days
84 Factory Acceptance Test 5 days
85 Commissioning 20 days
86 SAT 5 days
87 Documentation Review - A 1 day
88 Training 10 days
Task Progress Summary Rolled Up Split Rolled Up Progress Project Summary
Project: Project
Date: Thu 10/31/02
Split Milestone Rolled Up Task Rolled Up Milestone External Tasks
Page 2
Wyszukiwarka
Podobne podstrony:
Sample Project Mgmt CourseTOEIC Listening and Reading Sample Testshortcuts sampleproject prasy do wyciskaniaAdvanced Project Management?ycja polska?promconceive new project?5322C0Fundamentowanie Project 1Sampletailor process for projectlFD05E2Log sampleprepare environment for project 602A4Dragonfly (sample)prepare environment for project?133D66The Babylon Project Eye of the Shadowbaby sampler3 misiabeProject manager CV example 1Projects SelFolderForm dfmwięcej podobnych podstron