Activity: Evaluate Project Scope and Risk
var defaultQueryStr = '?proc={EA0C1D32-E39A-4D96-B956-E178DB776A96}&path={EA0C1D32-E39A-4D96-B956-E178DB776A96},{BADBA2C5-144D-482B-9B63-C95DA4DBD3E5}';
var backPath = './../../';
var imgPath = './../../images/';
var nodeInfo=null;
contentPage.preload(imgPath, backPath, nodeInfo, defaultQueryStr, false, true, false);
Activity: Evaluate Project Scope and Risk
This activity reappraises the project's scope and risk and updates the business case.
DescriptionWork Breakdown StructureTeam AllocationWork Product Usage
Relationships
Parent Activities
Project Management
Description
This activity appraises the project's intended capabilities and characteristics, and the risks associated with
achieving them. As the capabilities and risks are better understood, the business case should be updated, to ensure
that the project continues to be worth investing in, in its current form, or if a change in direction is needed.
Properties
Event Driven
Multiple Occurrences
Ongoing
Optional
Planned
Repeatable
Staffing
The skills required in the person acting as Project Manager in this activity are in technical project management
- risk analysis, planning and decision analysis - and in the domain of the application.
Usage
Usage Guidance
This evaluation is done once after the preferred approach is chosen and the project is initiated, to give a solid basis
for detailed planning.
This activity is recommended, to ensure that project scope and risks are managed effectively.
This activity updates and refines the Risk List
and Business Case. Techniques such as those described in Activity: Conceive New Project: Guidelines may be used for risk and
decision analysis. The Risk List and Business Case should be subjected to internal walkthroughs and reviews to ensure
there is a general consensus, before the next round of detailed planning is begun.
© Copyright IBM Corp. 1987, 2006. All Rights Reserved.
contentPage.onload();
Wyszukiwarka
Podobne podstrony:
evaluate project scope and risk?77352evaluate project scope and risk?77352evaluate project scope and risk?77352Reevaluate Project Scope and Riskf6F17C8Reevaluate Project Scope and Riskf6F17C8Reevaluate Project Scope and Riskf6F17C8Reevaluate Project Scope and Riskf6F17C8test and evaluate within scope<6279C7test and evaluate within scope<6279C7test and evaluate within scope<6279C7test and evaluate within scope<6279C7test and evaluate within scope<6279C7define project organization and staffingCD8015define project organization and staffingI0679CBdefine project organization and staffing?AB432Btesting and evaluating components(3725B2więcej podobnych podstron