Guideline: Classifying Work Products
var backPath = './../../../';
var imgPath = './../../../images/';
var nodeInfo=[{view: "view:_FCx1oN7CEdmsEI4YDGX2ag", path: ["_FCx1oN7CEdmsEI4YDGX2ag", "_jD8dUAIbEdqEutyfYo0quQ", "_2ClPcDIcEdqDs_9ORT1Rig", "7.27749388241665E-306"]}];
contentPage.preload(imgPath, backPath, nodeInfo, '', false, false, false);
Guideline: Classifying Work Products
This guideline offers a classification scheme for documenting the importance of individual work products and whether or not they will be used.
Relationships
Related Elements
Tailor the Development Process for the Project
Main Description
Introduction
These classifications can be used to describe how to use work products (and reports) when tailoring the Development Process. These values can be complemented with a
separate classifier to define the review procedures for the work product. For more information on review levels for
work products, see Guideline: Review Levels.
Classification
Explanation
Must have
You must use this work product. It is a key work product and may cause problems later in development if
it's not produced.
Should have
You should have this work product, if at all possible, but it is negotiable. If you do not produce this
work product, you should be able to justify why not.
Could have
Could have means that this work product doesn't have to be produced. It's only produced if it adds
value and if there's enough time.
Won't have
This means you won't use this work product. This may occur where a Rational Unified Process work
product is replaced by a local work product.
This classification scheme can be extended or customized to reflect your organization's individual culture.
An example of when this classification scheme may be adjusted depends on the level of tailoring that is being
performed. For example, when tailoring a process for a specific project, the decision of whether or not a
specific work product is to be used is made as part of the tailoring effort. In such cases, the above classification
scheme may be reduced to "Required" and "Not Required". In other cases, say when you are tailoring a process
for an organization and further tailoring for individual projects is expected, a more extensive classification scheme
as described in the above table becomes important. For more information on the different levels of tailoring, see
Concept: Tailoring RUP.
Impact of Classification
All work products classified as Must have or Should have must have their review procedures, tools,
templates and configuration management practices defined.
The specification of these procedures is optional for work products classified as Could have-these decisions
could be left to the developers or projects that decide to produce these work products.
All work products classified as Won't have must have their omission justified.
The major benefit of adopting this classification scheme is that it clearly denotes how the process has been
customized, and where there are options for negotiation and local decision making.
Examples of Usage
One way to think about the work product classification scheme is that it sets constraints on how the work products are
used.
For example, if you decide that the project could have an Analysis Model, then further customization could adjust these
values by deciding that the project will meet one of the following criteria:
It will have an Analysis Model
It won't have an Analysis Model
It will stay in its current state (an Analysis Model is optional)
The classification scheme can even be used dynamically-allowing the status of the work product to change depending upon
which phase the project is in.
The following table shows different ways of treating the Analysis Model. The How to use column defines how the
work product is used in each of the phases.
Work Product
How to use
Comment
Incep
Elab
Const
Trans
Analysis Model
Won't
Won't
Won't
Won't
No Analysis Model is developed
Analysis Model
Could
Could
Could
Could
Normal
Analysis Model
Could
Should
Won't
Won't
An evolutionary approach where the Analysis Model is replaced by the Design Model
Analysis Model
Must
Won't
Won't
Won't
An evolutionary approach where the Analysis Model is mandatory during the Inception phase to help
scope the project but is replaced by the Design Model during Elaboration
Analysis Model
Should
Must
Must
Must
A formal process where the Analysis Model is a mandatory, preserved work product that is optional
in the inception phase
© Copyright IBM Corp. 1987, 2006. All Rights Reserved.
contentPage.onload();
Wyszukiwarka
Podobne podstrony:
work product kind?8B98E5test work products?43E07developer work products?914DE7general work productsb318B77manager work products?EE5B60work product kinds@26BBAEwork products?9E13D0work product?6E4C22work product`FEF5A4work productCEEF8DManaging Producing Fieldclassidproductinstall product pagewięcej podobnych podstron