Zostaje kolejno od 16.05- 1 maszyna, 3, 9.
Zostaje kolejno od 06.06-2 maszyny, 4, 9.
Zostaje kolejno od 13.07 – 5 maszyn
14.07 - 6
15.07 - 6
18.07 -6
19.07 -6
20.07 -6
21.07 -8
22.07 -9
Lp. | Opis robót | J. miary | Ilość jednostek | Przyjęta wydajność zmianowa | Robocizna | L. maszyn | L. dni pracy | Śr. wydajność dzienna | ||
---|---|---|---|---|---|---|---|---|---|---|
1m | 2m | 1m | 2m | |||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 7 | 8 | 9 | |
1 | I-IV | [m3] | 4,31 | 462 | 714 | 1 | 1 | 5 | 1 | 4,31 |
2 | I-VII | [m3] | 14896,02 | 372 | 597 | 41 | 25 | 7 | 5 | 2979,204 |
3 | I-X | [m3] | 14907,67 | 298 | 493 | 51 | 31 | 10 | 4 | 3726,918 |
4 | II-VIII | [m3] | 12729,94 | 374 | 599 | 35 | 22 | 7 | 4 | 3182,485 |
5 | II-X | [m3] | 3637,66 | 289 | 480 | 13 | 8 | 11 | 2 | 1818,83 |
6 | II-XI | [m3] | 11681,95 | 303 | 500 | 39 | 24 | 10 | 4 | 2920,488 |
7 | III-IX | [m3] | 11513,54 | 374 | 599 | 31 | 20 | 7 | 4 | 2878,385 |
8 | III-XI | [m3] | 3771,7 | 293 | 485 | 13 | 8 | 11 | 3 | 1257,233 |
9 | III-XII | [m3] | 14360,76 | 301 | 497 | 48 | 29 | 10 | 4 | 3590,19 |
10 | IV-X | [m3] | 15142,69 | 374 | 599 | 41 | 26 | 7 | 5 | 3028,538 |
11 | V-XI | [m3] | 17820 | 380 | 607 | 47 | 30 | 7 | 7 | 2545,714 |
12 | VI-XII | [m3] | 19400 | 390 | 620 | 50 | 32 | 7 | 5 | 3880 |
13 | VII-X | [m3] | 7,98 | 459 | 710 | 1 | 1 | 5 | 1 | 7,98 |
14 | VIII-XI | [m3] | 98,35 | 473 | 728 | 1 | 1 | 5 | 1 | 98,35 |
15 | IX-XII | [m3] | 259,24 | 470 | 725 | 1 | 1 | 5 | 1 | 259,24 |
Lp. | Opis robót | J. miary | Ilość jednostek | Przyjęta wydajność zmianowa | Robocizna | L. maszyn | L. dni pracy | Śr. wydajność dzienna | ||
---|---|---|---|---|---|---|---|---|---|---|
1m | 2m | 1m | 2m | |||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 7 | 8 | 9 | |
1 | I-I | [m3] | 1137,73 | 649 | 934 | 2 | 2 | 2 | 2 | 568,865 |
2 | IV-I | [m3] | 1297,93 | 492 | 751 | 3 | 2 | 4 | 1 | 1297,93 |
3 | V-I | [m3] | 6677,54 | 453 | 703 | 15 | 10 | 5 | 2 | 3338,77 |
4 | II-II | [m3] | 259,2 | 649 | 934 | 1 | 1 | 2 | 1 | 259,2 |
5 | V-II | [m3] | 11061,46 | 495 | 755 | 23 | 15 | 4 | 4 | 2765,365 |
6 | VI-II | [m3] | 405 | 459 | 710 | 1 | 1 | 2 | 1 | 405 |
7 | III-III | [m3] | 8,55 | 627 | 910 | 1 | 1 | 2 | 1 | 8,55 |
8 | VI-III | [m3] | 16119 | 495 | 755 | 33 | 22 | 4 | 6 | 2686,5 |
9 | VI-VI | [m3] | 23,02 | 622 | 904 | 1 | 1 | 3 | 1 | 23,02 |
10 | IV-VII | [m3] | 413,13 | 498 | 759 | 1 | 1 | 4 | 1 | 413,13 |
11 | VIII-VIII | [m3] | 98,78 | 643 | 928 | 1 | 1 | 2 | 1 | 98,78 |
12 | IX-IX | [m3] | 1,16 | 627 | 910 | 1 | 1 | 2 | 1 | 1,16 |
13 | IV-X | [m3] | 17242,94 | 394 | 626 | 44 | 28 | 7 | 6 | 2873,823 |
14 | VII-X | [m3] | 5113,06 | 495 | 755 | 11 | 7 | 4 | 2 | 2556,53 |
15 | VII-XI | [m3] | 7214,33 | 453 | 703 | 16 | 11 | 5 | 3 | 2404,777 |
16 | VIII-XI | [m3] | 13359,67 | 495 | 755 | 27 | 18 | 4 | 5 | 2671,934 |
17 | VIII-XII | [m3] | 1058,67 | 467 | 721 | 3 | 2 | 5 | 1 | 1058,67 |
18 | IX-XII | [m3] | 17085,33 | 498 | 759 | 35 | 23 | 4 | 7 | 2440,761 |
19 | XII-XII | [m3] | 27,12 | 627 | 910 | 1 | 1 | 2 | 1 | 27,12 |
Lp. | Opis robót | J. miary | Ilość jednostek | Przyjęta wydajność zmianowa | Robocizna | L. maszyn | L.dni pracy | Śr. wydajność dzienna | ||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
1m | 2m | 1m | 2m | |||||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | ||
1 | VII-I | [m3] | 12905,69 | 378,57 | 604,85 | 35 | 22 | 7 | 7 | 1843,67 | ||
2 | X-I | [m3] | 14229,31 | 301,37 | 497,09 | 48 | 29 | 10 | 7 | 2032,7586 | ||
3 | X-IV | [m3] | 18792 | 372,95 | 597,24 | 51 | 32 | 7 | 6 | 3132 | ||
4 | X-VII | [m3] | 161,73 | 464,98 | 717,74 | 1 | 1 | 5 | 1 | 161,73 | ||
5 | X-II | [m3] | 5129,96 | 289,78 | 480,31 | 18 | 11 | 11 | 2 | 2564,98 | ||
6 | VIII-II | [m3] | 11365,45 | 374,8 | 599,75 | 31 | 19 | 7 | 4 | 2841,3625 | ||
7 | XI-II | [m3] | 11935,59 | 302,58 | 498,83 | 40 | 24 | 10 | 6 | 1989,265 | ||
8 | XI-V | [m3] | 21222 | 372,95 | 597,24 | 57 | 36 | 7 | 6 | 3537 | ||
9 | XI-VIII | [m3] | 351,44 | 467,87 | 721,38 | 1 | 1 | 5 | 1 | 351,44 | ||
10 | XI-III | [m3] | 4884,97 | 290,9 | 481,93 | 17 | 11 | 11 |
|
976,994 | ||
11 | IX-III | [m3] | 9663,19 | 374,8 | 599,75 | 26 | 17 | 7 | 3 | 3221,0633 | ||
12 | XII-III | [m3] | 14692,84 | 302,58 | 498,83 | 49 | 30 | 10 | 4 | 3673,21 | ||
13 | XII-VI | [m3] | 23166 | 371,11 | 594,74 | 63 | 39 | 7 | 6 | 3861 | ||
14 | XII-IX | [m3] | 518,98 | 467,87 | 721,38 | 1 | 1 | 5 | 1 | 518,98 |