var nodeInfo=[{view: "view:_LVCagP5WEdmAzesbYywanQ", path: ["_LVCagP5WEdmAzesbYywanQ", "_4U33kAILEdq-_NKqZM1EhA", "_qIh6UABuEdqrKcHWz1HoWw", "{435E36E7-98E5-4A4C-B61A-3B29459DB7B8}", "{4C2F0277-EA66-4C98-8351-17E32D3C9BAA}"]}, {view: "view:_LVCagP5WEdmAzesbYywanQ", path: ["_LVCagP5WEdmAzesbYywanQ", "_4U33kAILEdq-_NKqZM1EhA", "_nB0hwAITEdqu-LkyOdB8SQ", "_yeA1y9nmEdmO6L4XMImrsA", "{4C2F0277-EA66-4C98-8351-17E32D3C9BAA}"]}, {view: "view:_FCx1oN7CEdmsEI4YDGX2ag", path: ["_FCx1oN7CEdmsEI4YDGX2ag", "_f6_YwN7DEdmsEI4YDGX2ag", "_qIh6UABuEdqrKcHWz1HoWw", "{435E36E7-98E5-4A4C-B61A-3B29459DB7B8}", "{4C2F0277-EA66-4C98-8351-17E32D3C9BAA}"]}, {view: "view:_FCx1oN7CEdmsEI4YDGX2ag", path: ["_FCx1oN7CEdmsEI4YDGX2ag", "_kC0pcN7GEdm8G6yT7-Wdqw", "_yeA1y9nmEdmO6L4XMImrsA", "{4C2F0277-EA66-4C98-8351-17E32D3C9BAA}"]}];
contentPage.preload(imgPath, backPath, nodeInfo, '', true, false, false);
Task: Iteration Evaluation Criteria Review
This task describes how to approve the criteria that will be used to determine if the work completed during an iteration meets the iteration's objectives.
Disciplines: Project Management
Relationships
RolesPrimary Performer:
Management Reviewer
Additional Performers:
InputsMandatory:
Iteration Plan
Software Development Plan
Optional:
None
Outputs
Review Record
Process Usage
Project Management
>
Manage Iteration
>
Iteration Evaluation Criteria Review
Main Description
The Iteration Evaluation Criteria Review is a formal review of the tests and reviews that will be used to demonstrate
to the customer that the objectives for an iteration have been met. This is an important review because it ensures that
the project team and customer have consistent expectations for how success in the work of the iteration will be
measured.
Steps
Schedule Iteration Evaluation Criteria Review Meeting
The Iteration Evaluation Review meeting is a meeting between a customer representative and the project's management
team (the project manager, plus the team leads for the various functional areas of the project team). Representative(s)
of the Project Review Authority may also be involved.
Once the attendees of the meeting have been identified, set a date/time for the meeting to take place. It is important
that you provide sufficient lead time to allow the participants to review the materials that will be used as the basis
for the approval decision.
Distribute Meeting Materials
Prior to the meeting, distribute the review materials to the reviewers. Make sure these materials are sent out
sufficiently in advance of the meeting to allow the reviewers adequate time to review them. A minimum set of work
products that should be presented for review is:
Iteration Plan
Test Plan
Conduct Iteration Evaluation Criteria Review Meeting
During the meeting, the reviewers assess the proposed program of tests and reviews defined in the Test Plan that will
be used to determine if the iteration's objectives have been met. During the meeting, make sure that:
Both the customer representative and the project team have a clear understanding of which project work products
will be delivered at the end of the iteration
Both the customer representative and the project team have a clear understanding of which reviews, tests and
demonstrations will be carried out, and how the results will be interpreted
That reviews and tests are planned covering each of the objectives defined for the iteration in the Iteration Plan
At the end of the meeting, the reviewers should make their approval decision. The result can be one of the following:
Criteria Approved
The customer representative and the project team agree that the evaluation criteria are satisfactory
Criteria Rejected
The evaluation criteria are not acceptable. This could be due to incomplete coverage of iteration objectives,
or tests/reviews that do not properly assess whether particular objectives are met.
If the criteria are rejected, the project team should address the identified deficiencies and re-submit revised
iteration evaluation criteria for a follow-up review.
Record Decision
At the end of the meeting, a Review Record is completed capturing any important discussions or action items, and
recording the result of the Iteration Evaluation Criteria Review. If the result was "criteria rejected" a follow-up
Iteration Evaluation Criteria Review Meeting should be scheduled for a later date.
© Copyright IBM Corp. 1987, 2006. All Rights Reserved.
contentPage.onload();
Wyszukiwarka
Podobne podstrony:
iteration evaluation criteria reviewdD7BD8Citeration plan review?2D5CC2iteration plan review5A6F0A8iteration plan reviewm20D94review requirements tmS4695E9REVIEWANSWERSplan for next iteration?CDF5ABtesting and evaluating components(3725B2deRegnier Neurophysiologic evaluation on early cognitive development in high risk anfants and toddJRC NRD 525 technical reviewDoD Joint Services Weapon Safety Review Processplan for next iteration?855DCDplan for next iteration?CDF5ABproduct reviewswięcej podobnych podstron