background image

 
 

 

 

                                

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

    

 

     Standard costing and    
         variance analysis 

 
 
 

Chapter 

5

 

 

background image

 
 

 

 

                                

 

5.1 

Standard costing 

 

 

A standard cost is a planned (budgeted) or forecast unit cost for a product or service, which 

is assumed to hold good given ‘expected’ efficiency and cost levels within an organisation.  

A standard cost normally represents the planned (budgeted) or forecast unit cost for material, 

labour and overhead expected for a product or service. 

 

 

Types of standard cost  

 

  Ideal  standard  e.g.  a  standard  attained  under  the  ‘most  favourable’  operating 

conditions, no allowance for any waste, scrap, idle time or production stoppage.  This 
type  of  standard  is  normally  unrealistic  or  unattainable  in  reality;  staff  could  be 
demotivated because such targets set would rarely be achieved. 

  Attainable  (or  expected)  standard  e.g.  a  standard  that  could  be  achieved  by  staff, 

given a reasonable (not perfect) level of effort from them.  Some allowances would be 
made  for  delays  or  inefficiencies  that  are  expected  to  occur  during  production  or 
delivery of a service. 

  Current standard e.g. a standard based on current and existing operating conditions.  

Management  must  continually  attempt  to  improve  cost  and  efficiency  levels  by  the 
continual introduction of attainable (or expected) standards (as explained above). 

  Loose standard e.g. a standard ‘loosely’ set and therefore easy to achieve by staff. 

  Basic standard e.g. the first standard ever used  by the organisation, often used as a 

yardstick to monitor trends for improvement made over time. 

  Historical standards e.g. any standard used historically in previous periods. 

 

Practical advice for setting standards 

 

1.  Use  challenging  but  realistic  targets.    Link  higher  financial  reward  to  the  higher 

achievement  of  more  challenging  targets  and  perhaps  moderate  incentives  for  easier 
targets to achieve. 

2.  Consult with and allow staff to participate when setting targets, this can help improve 

their motivation, reduce frustration and increase job satisfaction.   

3.  Clear  trust  and  communication  must  be  developed  between  management  and  staff, 

management  must  avoid  be  over  critical  if  very  challenging  targets  have  not  been 
achieved.  

4.  Good planning is essential to ensure whatever standards or targets that are used, they 

are  realistic  and  achievable.    Frequent  periodic  reviews  of  standards  or  targets  are 
required to ensure they are attainable. 

 

Example 5.1   
 
Wood Plc makes wooden tables and chairs from natural timber.  To make one unit of product 
consisting  of  one  table  and  four  chairs,  it  consumes  60kg  of  timber;  after  an  expected  20% 
wastage  due  to  wood  shavings  and  scrap  in  the  cutting  process.    100kg  of  timber  currently 
costs Wood Plc £50. 

 

What is the standard cost of material to make one unit of product? 
 

background image

 
 

 

 

                                

 

Information for a standard (budgeted) cost e.g. for a product or service. 

 

 

Standard material price 

 

  Supplier  contracts,  quotations  and 

estimates. 

  Previous  supplier  invoices  and  cost 

trends. 

  Websites 

of 

material/component 

suppliers. 

  Discounts 

available 

for 

bulk 

purchases. 

  Seasonality/volatility 

of 

material 

prices. 

  Differences 

in 

quality 

of 

material/components  and  therefore 
differences in price. 

  Inflation 

rates 

expected 

for 

material/component prices. 

 

 

Standard material usage 

 

 

  The quality of material e.g. levels of 

wastage  and  scrap  maybe  higher  for 
more  inferior  material/components 
and vice versa. 

  Specification  and  design  of  the 

product  or  service  e.g.  determines 
directly the material usage. 

  Normal  wastage  levels  expected 

during  delivery  of  a  service  or 
manufacturing of a product. 

  Estimations  based  upon  previous 

consumption of material/components 
e.g.  quality  of  litres,  kilos  etc  issued 
from  stores  to  production  ÷  volume 
of products made = average material 
consumption. 

 

 

Standard labour rate 

 

  Market  rates  for  different  skills  and 

grades of staff. 

  Wage inflation rates expected. 

  Existing  internal  rates  from  payroll 

records e.g. bonus schemes, overtime 
or piece work rates currently in use. 

 

The  standard  (budgeted)  wage  rate  per  hour 
normally  incorporates  any  level  of  bonus  or 
overtime  expected  for  a  period,  based  upon 
forecast output. 
 

 

Standard labour efficiency 

 

  Idle 

time 

expected 

e.g. 

non-

productive time during processes. 

  Time and motion studies. 

  Time  sheets  e.g.  total  hours  worked 

÷  volume  of  products  made  =  the 
average time per unit. 

  Skill  and  expertise  of  staff  e.g. 

skilled  staff  work  quicker  or  more 
efficiently. 

  The  learning  curve  or  learning  rate 

expected when untrained staff or new 
processes are introduced. 

  Motivation and morale of staff often 

creates quicker performance. 

 

 

Standard overhead rate 

 

  A  variable  or  fixed  overhead  rate  per  unit  can  be  obtained  by  dividing  the  total 

forecast  (budgeted) overhead for a period, by a  forecast  (budgeted) level  of activity 
e.g. labour hours worked, machine hours run or products and services made (output). 

  Review  and  monitor  variable  overhead  rates  used  in  past  periods  and  consider 

expected inflation rates. 

  Cost relationships can be found by using techniques such as the high-low method or a 

scatter graph as a way of separating variable and fixed cost. 

 

background image

 
 

 

 

                                

 

Standard costing can be used for 

 

  Preparation of budgets e.g. more accurate planning and forecasting. 

  Controlling performance of an organisation by ‘exception reporting’ e.g. standard or 

budgeted  costs  and  revenues,  compared  with  actual  results  and  any  differences 
highlighted for investigation. 

  Inventory  valuation  e.g.  raw  material,  work-in-progress  and  finished  goods 

inventory valued at standard cost for simplicity. 

  Simplifying  cost  bookkeeping  e.g.  the  flow  of  entries  from  expense  accounts  to 

work-in-progress  or  cost  of  sales  can  take  place  at  standard  rather  than  actual  cost, 
this integrates both financial and management accounting systems together. 

  Motivating  and  rewarding  staff  e.g.  standards  can  be  used  as  goals  or  targets  for 

staff  achieve,  financial  reward  can  be  linked  measurably  to  achieving  standards  set.  
Staff bonuses can be linked to efficiency, productivity or cost savings made by staff. 

 

 

Criticisms of standard costing 

 

  Sometimes it can be hard to define a ‘current’ or ‘attainable standard’ especially with 

the complexity and diversity of modern manufacturing.  Traditionally manufacturers 
produced  a  small  range  of  products  using  mass  production  techniques.    Nowadays 
products have shorter lifecycles and different batches of many different products can 
be produced. 

  With  more  automation  of  manufacturing  operations  today  and  less  human 

intervention,  labour  standards  are  becoming  less  valuable  as  management 
information.  Automation  produces  greater  uniformity  and  consistency  of  products 
made, with less likelihood of material and labour variances actually occurring.   

  Standard costing is an internal not external control measure e.g. too internally focused 

on maximising efficiency and minimising cost.  Organisations need to consider other 
external  factors  such  as  competition,  customers  and  other  global  environmental 
factors, not just internal cost and efficiency levels.  Quality, innovation and customer 
satisfaction have become far more important to survive as an organisation today. 

  Even when variances are identified there could be uncontrollability of any exceptions 

highlighted e.g. discounts lost due to a reduction in the quantity of material ordered or 
seasonal  price  fluctuations  within  the  financial  period.    In  these  cases  very  little 
control  action  (if  any)  can  be  taken  by  management  and  care  must  also  be  taken  to 
avoid blame. Often the reason or causes of variances even when found are sometimes 
overlooked or not investigated at all. 

  The  revision  to  standards  may  be  too  infrequent  to  guide  or  improve  performance 

over time e.g. the life cycle of products are much shorter in a modern manufacturing 
environment  and  the  environment  more  dynamic.  Standards  quickly  become  out  of 
date due to frequent and continuous change.  

  Modern  manufacturing  techniques  such  as  TQM  and  quality  circles  mean  as 

manufacturers  aim  for  near  perfection,  the  frequency  and  materiality  of  variances 
should not occur so often.  Today focus is more on quality and customer satisfaction 
not the minimisation of cost. 

 
 
 
 
 
 

background image

 
 

 

 

                                

 

5.2 

Variance analysis 

 

 

Variance analysis is a budgetary control technique, which compares planned (budgeted) or 

forecast costs and revenues to actual financial results, it measures the differences between 

standard (budgeted) and actual performance.  Variance analysis is used to improve 

operational performance through control action by management e.g. investigation of any 

variance causes and correction of them to prevent in future any further deviations from plan.   

 

 

Reasons why variances occur 

 

  Inaccurate  data  used  to  compile  standards,  inaccurate  compilation  of  the  budget  or 

inaccurate compilation of actual financial results. 

  Standard used either not realistic or out of date. 

  Efficiency  of  how  operations  were  undertaken  and  performed  by  staff  during  the 

period  e.g.  mistakes  made,  poor  decisions  made,  lack  of  effort  etc  can  all  lead  to 
actual results be worse than expected. 

  Random  or  chance  events  occurring  e.g.  sudden  economic  down  turn  such  as  the 

credit crunch, volatility of exchange rates, weather and commodity prices. 

 

The  budgetary  planning  process  involves  the  production  of  budgets  or  forecasts  using  the 
most  realistic  standards  for  cost  and  efficiency  levels.    The  budgetary  control  process 
identifies  areas  of  responsibility  for  management  and  staff  and  then  frequently  compares 
actual results against the budget or standards used.  The original budget would have normally 
forecast a different number of units produced and sold, compared with the actual number of 
units  produced  and  sold,  a  ‘flexed  budget’  is  therefore  prepared  e.g.  the  original  budget 
‘flexed’,  (redrafted  based  on  actual  units  produced  and  sold),  to  compare  with  actual  costs 
and revenues.  When a flexed budget is compared with actual results this is on a like for like 
basis  and  therefore  a  meaningful  yardstick  to  calculate  variances.  Variances  can  be 
subdivided  and  analysed  further  to  help  management  determine  where  control  action  is 
needed. 

 

 

A variance is the difference between planned, budgeted or standard cost and the actual cost 

incurred.  The same comparisons may be made for revenues. 

(CIMA) 

 

 

There are many variance proforma calculations that need to be learned and applied as part of 
your studies.  These proforma are essential to learn and practice in order to truly understand 
and interpret what variances mean.  Once variances have been calculated either ‘F’ or ‘A’ is 
used  as  terminology  to  indicate  favourable  or  adverse  differences  between  actual  and 
standard  performance.    Favourable  means  that  actual  results  were  better  than  standard.  
Adverse  means  that  actual  results  were  worse  than  standard.    Remember  variances  are  just 
reconcilable  differences  between  a  budget  (standard)  and  actual  results  so  in  the  case  of  an 
adverse  variance  this  would  mean  that  actual  cost  will  be  higher  or  profit  lower  when 
compared to the budget, and vice versa if a variance was favourable. 
 
 

background image

 
 

 

 

                                

 

Sales variance proforma  

 
 
 

 

Sales price 

variance 

 
 
 
 
 
 
 
 

Sales volume 

(contribution) 

variance 

 

 
 
 
 
 
 
 
 

 

 

Sales volume 

profit 

variance 

 

 
 
 
 
 
 

 
 
 

 
 

Sales volume 

(revenue) 

variance 

 

 

                                                                                                    £ 
Did sell (actual quantity sold x actual selling price)                  X 
Should sell (actual quantity sold x standard selling price)        (X) 
Sales price variance   

 

 

 

                X 

 
This measures the impact on profit when actual units sold were at a lower 
or higher price than the standard (budgeted) price. 

 

 
                                                                                    Units 
Did sell (actual quantity sold)  

 

                X 

Should sell (original budgeted quantity sold)              (X) 

 

 

 

                X 

 

 

 

 

           x    Standard Contribution per unit 

Sales volume (contribution) variance 

                X 


The sales volume (contribution) variance measures the difference between 
the  original  and  flexed  budgeted  contribution.  It  measures  the  impact  on 
contribution,  when  actual  sale  of  units  is  more  or  less  than  the  original 
budgeted sale of units.  This method of calculation would be applied when 
marginal costing is used by the organisation. 
 

 

                                                                                   Units 
Did sell (actual quantity sold)  

 

              X 

Should sell (original budget quantity sold)                 (X) 

 

 

 

              X 

 

 

 

 

                   x   Standard Profit per unit 

Sales volume (profit) variance 

                          X 

 
The  sales  volume  (profit)  variance  measures  the  difference  between  the 
original and flexed budgeted profit.  It measures the impact on profit, when 
actual sale of units is more or less than the original budgeted sale of units.  
This  method  of  calculation  would  be  applied  when  absorption  costing  is 
used by the organisation. 

 

 
                                                                                Units 
Did sell (actual quantity sold)  

 

            X 

Should sell (original budget quantity sold)              (X) 

 

 

 

            X 

 

 

 

 

                         x Standard Price 

Sales volume (revenue) variance 

                        X 

 
The above proforma would be the same regardless of whether marginal or 
absorption costing principles are applied. 

 

background image

 
 

 

 

                                

 

Cost variance proforma 

 

 
 

 

 

 

Material 

price 

variance 

  
                                                                                                      £ 
Did spend (actual quantity purchased x actual price)  

      X 

Should spend (actual quantity purchased x standard price)       (X) 
Material price variance 

 

 

 

 

      X 

 
The material price variance measures the impact on contribution or profit 
when  the  actual  quantity  of  material  purchased  was  at  a  lower  or  higher 
price  than  the  standard  price.  This  variance  calculation  always  uses  the 
quantity of material purchased never material used if there is a difference 
between material purchased and used in a question. 

 
 

 
 
 
 
 
 
 

Material 

usage 

variance 

       
                                                                                    
                                                                                      kg/litres/units 
Actual production did use 

 

              

 

   X 

Actual production should use  
(actual production x standard usage)                                        (X) 

 

 

 

                           X 

 

 

 

 

                                    x Standard Price  

Material usage variance 

 

 

     

               X 

 
The material usage variance measures the impact on contribution or profit 
when the actual  quantity of material  used was  a  lower or higher amount 
than standard usage. This variance calculation always uses the quantity of 
material  used  never  material  purchased  if  there  is  a  difference  between 
material purchased and used in a question. 

 
 

 

 

 

 

Total material variance 

equals material price variance  

+/- material usage variance  

 

background image

 
 

 

 

                                

 

 
 
 

Labour rate 

variance 

 

                                                                                                 £ 
Did spend (actual hours paid x actual rate)   

            X 

Should spend (actual hours paid x standard rate)                 (X) 
Labour rate variance 

 

 

 

 

X 

 

 
The  labour  rate  variance  measures  the  impact  on  contribution  or  profit 
when  the  actual  hourly  rate  paid,  was  at  a  lower  or  higher  rate  than  the 
standard  rate.  This  variance  calculation  always  uses  actual  hours  paid 
never  hours  worked  if  there  is  a  difference  between  hours  paid  and 
worked in a question. 

 

 
 
 
 
 
 

Labour 

efficiency 

variance 

                                                                                
                                                                                            Hours                                                                                                                                           
Actual production did take 

 

              

 

Actual production should take  
(actual production x standard hours)                                     (X) 

 

 

 

             

 

 X 

 

 

 

 

                    x Standard Rate per hour 

Labour efficiency variance   

 

     

 

 X 

 
 
The  labour  efficiency  variance  measures  the  impact  on  contribution  or 
profit when the actual quantity of labour hours worked was at a lower or 
higher amount than standard efficiency. This variance calculation always 
uses actual hours worked never hours paid if there is a difference between 
hours paid and worked in a question. 
.

 

 

 

 
 
 
 

Labour idle 

time 

variance 

 

                                                                                  
                                                                                         Hours                                                                                                            
Actual hours paid  

              

 

 

         X 

Actual hours worked                                                          (X) 
Idle time                          

 

 

                     X 

 

 

 

 

                x Standard Rate per hour 

Labour idle time variance   

 

                     X 

 
 
The idle time variance measures the impact on contribution or profit when 
labour hours paid is different to labour hours worked. Tip: The idle time 
variance in your exam will always be adverse. 

 
 

 
 

 

 

Total labour variance 

equals labour rate variance  

+/- labour efficiency variance  

+/- labour idle time variance 

 

background image

 
 

 

 

                                

 

 

 
 

 

Variable 

overhead 

expenditure 

variance 

 
                                                                                                                   £ 
Did spend (actual hours worked x actual variable overhead rate)            X                                                                                    
Should spend (actual hours worked x standard variable overhead rate) (X)                      
Variable overhead expenditure variance   

 

                  X 

 
The variable overhead rate variance measures the impact on contribution 
or profit when the actual rate paid, was at a lower or higher rate than the 
standard rate. This variance calculation always uses actual hours worked 
never hours paid if there is a difference between hours paid and worked in 
a  question.    It  is  assumed  that  no  variable  overhead  would  be  incurred 
during any periods of idle time. 
 

 
 
 
 
 

 

Variable 

overhead 

efficiency 

variance 

                                                                                                                                                                                                     
                                                                                             Hours                                                                                                                                           
Actual production did take 

 

              

             X 

Actual production should take  
(actual production x standard hours)                                      (X) 

 

 

 

             

 

  X 

 

 

 

 

                             x Standard Rate per hour 

Variable overhead efficiency variance 

     

 

  X 

 

 

The  variable  overhead  efficiency  variance  measures  the  impact  on 
contribution  or  profit  when  the  actual  quantity  of  labour  hours  worked 
was  at  a  lower  or  higher  amount  than  standard  efficiency.  This  variance 
calculation always uses actual hours worked never hours paid if there is a 
difference  between  hours  paid  and  worked  in  a  question.  Tip:  Similar 
proforma  to  the  labour  efficiency  variance  e.g.  if  staff  work  more 
efficiently when compared to standard, labour cost and variable overhead 
can be saved due to the saving in staff time. 
 

 

Total variable overhead variance 

equals variable overhead expenditure variance  

+/- variable overhead efficiency variance 

 

 
 
 
 
 
 
 
 

background image

10 

 
 

 

 

                                

 

 

Fixed 

overhead 

expenditure 

variance 

 

 
Actual fixed overhead expenditure   

 

 

 

 X 

Budgeted fixed overhead expenditure 

 

 

            (X) 

Fixed overhead expenditure variance 

 

 

 

 X 

 

 
 
 
 
 

Fixed 

overhead 

volume 

variance 

 
                                                                                                        Units 
Did produce (actual quantity produced) 

 

 

            X 

Should produce (budget quantity produced)                                     (X) 

 

 

 

                                    X 

 

 

 

 

        x Overhead Absorption Rate (O.A.R) 

Fixed overhead volume variance   

 

                        X 

 
This  variance  calculation  is  only  applicable  if  the  organisation  uses 
absorption costing.  When marginal costing an organisation does not use 
the  process  of  absorbing  fixed  overhead  and  therefore  doers  not  use  an 
overhead absorption rate for fixed overhead.    
 

 

Total fixed overhead variance 

equals fixed overhead expenditure variance  

+/- fixed overhead volume variance 

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

11 

 
 

 

 

                                

 

 
 
Example 5.2 
 
Ramsey Oliver Restaurants is a local restaurant renowned for good quality food. One dish on 
the menu which is sold throughout the week has been of major concern for management, the 
‘all  week  chicken  roast’.    The  standard  cost  and  price  of  the  ‘all  week  chicken  roast’  is  as 
follows: 
 
Standard cost information for 1 meal 
                                                                                         £ Per meal  

 

 

Chicken 0.3kg @ £2.50 per kg 

 

 

 

0.75 

Vegetables 0.5kg @ £0.50 per kg 

 

 

 

0.25 

Labour 15 mins @ £9.00/hr   

 

 

 

2.25 

Variable overhead 15 mins @ £2.00/hr 

 

 

0.50 

Fixed overhead 15 mins @ £20.00/hr  

 

 

5.00 

 

 

 

 

 

 

 

 

 

8.75 

Standard profit 

 

 

 

 

 

3.20 

Selling price    

                                                          11.95 

 

 

 
The budget each week aims to produce and sell 500 meals. Fixed budgeted overhead for each 
week is £2,500.  For week 43 the following actual information was obtained. 

 

  The number of meals actually produced was 476. 

  The number of meals actually sold were 460, earning revenue of only £4,600 due to a 

promotional offer on the menu reducing each meal sold to £10.00 rather than £11.95 
as offered on the menu. 

 

Ingredients purchased 
 

 

 

 

 

Chicken                     Vegetables 

Purchased 

 

 

 

180kg  (£405)  

250kg (£140) 

Used   

 

 

 

165kg   

 

220kg 

 
Chef wages for week 43 
Hours paid 

 

 

120 hours (wages paid £1,200) 

Hours worked  

 

114 hours 

 
6 hours were idle due to ovens failing on Tuesday afternoon 
 
Variable overhead 

 

  £150 

 
Fixed overhead 

 

£2,750  

 
Standard costing is used to value any material inventory at the end of a period. 
 
Prepare  an  operating  statement  for  week  43  applying  both  absorption  and  marginal 
costing  principles,  which  reconciles  any  differences  between  actual  and  budgeted 
results?   
 

background image

12 

 
 

 

 

                                

 

5.3 

Working backwards with variances 

 
Some  exam  questions  rather  than  the  requirement  being  to  calculate  variances,  it  could 
instead require you to work out actual information or even standard or budgeted information, 
the question will provide variances and normally further information to help.  The following 
example provides an operating statement prepared using absorption costing principles.  You 
have  to  use  the  budgeted  information  and  variances  provided  to  work  out  actual  results.  
Whether the question asks for actual or standard (budgeted) information the approach is the 
same each time, use your variance proforma, include all the numbers you do know, then work 
backwards to derive the answer you need. 

 
Example 5.3 – Working backwards 
 
Ramsey Oliver Restaurants had a problem with their accountant during period 46; he left in a 
fume and took all the actual accounts information with him as revenge.  You have been called 
in from a temping agency to sort out the mess.  The following information has been provided 
to you. 
 
Operating statement for week 43 
 
Budget profit   

 

 

 

 

 

                        1,600 

Sales volume variance  

 

 

 

 

 

 

   128 (A) 

Flexed budget profit   

 

 

 

 

 

 

1,472 

Sales price variance    

 

 

 

 

 

 

   897 (A) 

 

 

 

 

 

 

 

 

 

 

   575 

Cost variances 

 

 

 

                         F 

   A 

 
Chicken price variance  

 

 

 

             45 

 

Chicken usage variance  

 

 

 

 

              55 

 
Vegetable price variance  

 

 

 

 

 

   15 

Vegetable usage variance  

 

 

 

 

   9 

 
Labour rate variance   

 

 

 

                        120 

Labour efficiency variance    

 

 

 

 45 

Idle time variance  

 

 

 

 

 

               54 

 
Variable overhead expenditure variance 

 

 

 78 

Variable overhead efficiency variance 

 

 

 10 

 
Fixed overhead expenditure variance  

 

 

             250 

Fixed overhead volume variance 

 

 

 

             120 

 

 

 

 

 

 

 

            187 

 614    =  427 (A) 

Actual profit   

 

 

 

 

 

 

               148 

 
 

 

 

 
 

background image

13 

 
 

 

 

                                

 

 
Standard cost information for 1 meal
 
                                                                                       £ Per meal   

 

 

Chicken 0.3kg @ £2.50 per kg 

 

 

 

0.75 

Vegetables 0.5kg @ £0.50 per kg 

 

 

 

0.25 

Labour 15 mins @ £9.00/hr   

 

 

 

2.25 

Variable overhead 15 mins @ £2.00/hr 

 

 

0.50 

Fixed overhead 15 mins @ £20.00/hr  

 

 

5.00 

 

 

 

 

 

 

 

 

 

8.75 

Standard profit 

 

 

 

 

 

3.20 

Standard selling price   

                                              11.95 

 
Additional information
 

 

  Budgeted fixed overhead was £2,500 

  Actual hours paid were 6 more than worked due to an electrical fault with the ovens 

  Closing  inventory  for  Chicken  and  vegetables  rose  during  this  period  by  15kg  and 

30kg respectively. 

  Closing inventory for meals prepared rose during this period by 16 meals.  There was 

no opening inventory of meals for the period. 

 

You are required to 
 

1.  Calculate the actual sale of meals during the period 
2.  Calculate the actual production of meals during the period 
3.  Calculate actual hours worked by the chefs during the period 
4.  Calculate the actual quantity of chicken purchased during the period 
5.  Calculate the actual price paid for chicken during the period 
6.  Calculate the actual variable overhead expenditure during the period 
7.  Calculate the actual fixed overhead expenditure during the period 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Tip:
  The  standard  cost  information  above  includes  fixed  overhead  in  the  unit  cost  of  each 
meal therefore absorption costing not marginal costing principles need to be applied. 
 

background image

14 

 
 

 

 

                                

 

5.4 

Material mix and yield (productivity) variances 

 
When  different  types  of  materials  can  be  used  as  substitutes  for  each  other,  a  standard  mix 
can usually be determined to ensure a quality product at the lowest possible cost. If the actual 
material mix varies from the standard mix, both quality and cost may be affected.  A material 
usage  variance  can  be  subdivided  into  a  mix  and  yield  (productivity)  variance  when  there 
exists two or more ingredients that can be substituted for one another e.g. to provide a service 
or manufacture a product. The sum of the material mix and yield variances will be equal the 
material usage variance.   
 
The material mix variance can be calculated by using two different methods, the ‘individual 
valuation  bases’  which  is  the  easiest  to  apply  and  the  ‘average  valuation  bases’.  If  the 
examiner does not specify which method to use, the individual valuation bases is the easiest 
method  to  apply,  both  methods  give  the  same  answer  as  a  total  mix  variance,  but  the 
individual  values  for  each  material  which  make  up  the  mix  variance  will  be  different 
depending on each method used. 
 
The merit of using the mix variance calculations is that we can see exactly how much money 
has  been  saved  or  wasted  by  understanding  the  overall  composite  (mix)  of  how  materials 
were used together.  For example if making steak and kidney pies, the budget may aim to mix 
steak  and  kidney  in  the  ratio  of  80%  steak  and  20%  kidney  per  pie  and  the  budget  would 
reflect this.  If more kidney which is the assumed cheaper ingredient is substituted to replace 
steak  which  is  the  assumed  more  expensive  ingredient,  then  the  mix  would  change  and  an 
adverse  total  mix  variance  would  be  the  result  of  spending  too  much  money  overall  for  all 
ingredients together. 
 
Yield  (or  productivity)  variances  measure  the  amount  of  output  (unit  of  product  or  service) 
from a given amount of input (total materials mixed). Producing more output than expected 
from  a  given  amount  of  material  input,  indicates  greater  efficiency  of  production,  the 
variance would be favourable, indicating that money has been saved by using material more 
efficiently.  Producing  less  output  than  expected  from  a  given  amount  of  material  input, 
indicates  lower  efficiency  of  production,  the  variance  would  be  adverse,  indicating  that 
money has been wasted by using material less efficiently. 

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

15 

 
 

 

 

                                

 

 
Relationship for material variance calculations 

 
Significance of mix and yield variances 
 
If  mix  or  yield  variances  occur  this  not  only  has  an  impact  on  cost,  but  also  can  have  an 
impact on the quality of the final product.  For the example if making steak and kidney pies, 
substituting  more  kidney  for  less  steak  would  normally  produce  a  favorable  mix  variance, 
because  kidney  is  cheaper,  but  now  consider  the  quality  of  the  pies  made?    Will  customers 
complain?    A  favorable  yield  variance  indicates  greater  efficiency  of  how  all  material  was 
used altogether e.g. more output (pies) from the input of steak and kidney, however this could 
mean that the pies are going out to less than the weight specified, which again may save cost 
but may compromise on quality. 

 

Proforma for material mix and yield variances 

 

 
Yield (productivity) variance 

     Output 
      (units) 

Actual material used (never purchased if there is a difference) did produce           X 
Actual material used should produce   

 

(total material input ÷ standard usage per unit of output for all material)                X 
Over/(under) yield (production) 

 

 

 

 

                       X 

x standard cost of material for one unit of output*       

 

                    x £x 

 

 

 

 

 

 

 

 

 

                      £X (A)/(F) 

Over yielded (produced) = (F) Under yielded (produced) = (A) 
 
*Weighted average standard price of material for one unit of output.  This is found by taking 
the total standard material cost ÷ the total number of units (output) that would be budgeted 
to be made. 

Total 

Material 

Variance 

Material 

Price 

Variance  

 

Material 

Usage 

Variance 

Material 

Mix 

Variance 

Material 

Yield 

Variance 

background image

16 

 
 

 

 

                                

 

 

 
Individual valuation bases  

 

Actual output         Did Mix      Should Mix           Standard Price       Variance  

    

 

 

 

(1)  

 

(2)  

 

 

(3) 

Material A 

 

 X  

 

 X 

 

 

x £x =               £x (A) 

Material B 

 

 X  

 

 X 

 

 

x £x =               £x (F) 

Material C 

 

 X 

 

 X 

 

 

x £x =              £x (A) 

 X  

 

 X 

 

 

             

 £x (A)  

         

Approach 

 

1.  (1) Record the actual quantity of material used (never purchased if this is different to 

the quantity used).  Add this up e.g. total litres, units, kg etc for all material together. 

2.  (2)  Take  the  actual  quantity  of  material  as  a  total  from  column  (1)  recalculate  for 

each material how much you should have used according to the standard (budgeted) 
mix. Column (1) total should be equal to column (2) total. 

3.  Deduct (1) – (2) then multiply by the standard price (3) for each material to get the 

variance  for  each  material.    The  sum  of  the  variances  individually  is  the  total  mix 
variance. 

 

Interpretation 

 

  If you use a quantity of material which is more than the standard mix there would be 

an adverse variance. 

  If you use a quantity of material which is less than the standard mix there would be a 

favourable variance. 

 

background image

17 

 
 

 

 

                                

 

 
Average valuation bases  

 

Actual output         Did Mix   Should Mix     Standard Price  WA Standard   Variance 
                                                                                                      Price                                            
                                    (1)  

 

(2)  

 

(3)                      (4) 

 
Material A 

 

X  

 

 

x (£x               - £x)  =             £x (A) 

Material B 

 

X  

 

 

x (£x              - £x)  =             £x (F) 

Material C 

 

 

 

x (£x    

- £x) =             £x (A) 

X  

 

 

 

             

 

£x (A) 

 

           

Approach 

 

1.  (1) Record the actual quantity of material used (never purchased if this is different to 

the quantity used).  Add this up e.g. total litres, units, kg etc for all material together. 

2.  (2)  Take  the  actual  quantity  of  material  as  a  total  from  column  (1)  recalculate  for 

each material how much you should have used according to the standard (budgeted) 
mix.  Column (1) total should be equal to column (2) total. 

 

Note: Up to this point this is an identical approach to the individual valuation bases. 

 

3.  (4)  Calculate  the  weighted  average  standard  price  of  one  kg,  litre,  unit  etc  for  all 

material  ‘together’  by  using  the  standard  cost  information  provided  e.g.  standard 
total material cost ÷ standard units of material consumed for this cost = the weighted 
average standard price of material. 

4.  Deduct  (1)  –  (2) then multiply by the standard price  (3)  for  each material  less  the 

weighted  average  standard  price  (4)  for  all  material  together,  this  will  find  the 
variance individually for each material.  The sum of these variances individually is 
the total mix variance 

 
Interpretation 

 

  If you use more of a more expensive ingredient when compared to the standard mix 

the variance will be adverse

  If you use more of a less expensive ingredient when compared to the standard mix 

the variance will be favourable

  If you use less of a more expensive ingredient when compared to the standard mix 

the variance will be  favourable. This  is  because less expensive ingredients  will be 
used in substitute therefore saving cost. 

  If you use less of a less expensive ingredient when compared to the standard mix the 

variance will be adverse. This is because more expensive ingredients will be used in 
substitute therefore increasing cost. 

 

 
 
 
 
 

background image

18 

 
 

 

 

                                

 

 
Example 5.4 – Material mix and yield 

 

Ramsey Oliver Restaurants also does a ‘deep pan cheese and tomato pizza’ on its menu, the 
standard or budgeted cost and usage of  topping ingredients for one pizza are as follows 
 
Standard cost information for one pizza 
 

 

 

 

 

 

  £ 

0.5kg Tomatoes @ £1.40 a kg 

 

0.70 

0.6kg  Cheese @ £7.50 a kg   

 

4.50 

 

 

 

 

 

 

5.20 

 
1.1kg of cheese and tomato ingredients should produce a 1kg pizza (0.1kg of weight is lost 
due to evaporation in the cooking process).  In the previous week 60 pizzas were cooked (to 
the weight specified of 1.0kg) and the following ingredients were used during this process. 
 
Tomatoes          

 

 28 kg     

  £45.00 

Cheese                

             40 kg   

£270.00 

 
Calculate the material usage, mix and yield variances for Ramsey Oliver Restaurants 
for this day?

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Note: two methods exist for the calculation of mix variances, the individual valuation and 
average valuation bases.  Make sure you are familiar with both types of calculation. 
 

background image

19 

 
 

 

 

                                

 

 
Example 5.5 – (CIMA past exam question) 
 
A company has a process in which the standard mix for producing 9 litres of output is as 
follows: 

   $ 

4·0 litres of D at $9 per litre    

 

36·00 

3·5 litres of E at $5 per litre    

 

17·50 

2·5 litres of F at $2 per litre    

 

  5·00 
58·50 

 
A standard loss of 10% of inputs is expected to occur. The actual inputs for the latest period 
were: 

      $ 

4,300 litres of D at $9·00 per litre 

 

 38,700 

3,600 litres of E at $5·50 per litre  

 

 19,800 

2,100 litres of F at $2·20 per litre  

 

   4,620 

             63,120 

 
Actual output for this period was 9,100 litres. 

 

You are required to calculate 

 

(a) the total materials mix variance 
(b) 
the total materials yield variance 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

20 

 
 

 

 

                                

 

 
Example 5.6  – (CIMA past exam question) 
 
X Ltd uses an automated manufacturing process to produce an industrial chemical, Product P. 
X Ltd operates a standard marginal costing system. The standard cost data for Product P is as 
follows: 
 
Standard cost per unit of Product P 

 

     Materials 

A       10 kgs    

@ £15 per kilo  

£150 

B  

8 kgs    

@ £8 per kilo   

  £64 

C  

5 kgs    

@ £4 per kilo   

  £20 

                                  23 kgs 

 

Total standard marginal cost    

 

 

 

£234 

 

Budgeted fixed production overheads £350,000 
 
In order to arrive at the budgeted selling price for Product P the company adds 80% mark-up 
to  the  standard  marginal  cost.  The  company  budgeted  to  produce  and  sell  5,000  units  of 
Product P in the period. There were no budgeted inventories of Product P. 

 

The actual results for the period were as follows: 

 

Actual production and sales    

 

 

 

5,450 units 

Actual sales price  

 

 

 

 

 

£445 per unit 

Material usage and cost 

A  

 

 

 

43,000 kgs 

 

£688,000 

B  

 

 

 

37,000 kgs  

 

£277,500 

 

 

 

23,500 kgs  

 

  £99,875 

          103,500 kgs 

Fixed production overheads    

 

 

 

£385,000 

 
Required: 

 

(a) Prepare an operating statement which reconciles the budgeted profit to the actual profit for 
the period. (The statement should include the material mix and material yield variances)? 

 

(b)  The  Production  Manager  of  X  Ltd  is  new  to  the  job  and  has  very  little  experience  of 
management information. Write a brief report to the Production Manager of X Ltd that 

 

(i) 

 interprets the material price, mix and yield variances? 

(ii)  

discusses  the  merits,  or  otherwise,  of  calculating  the  materials  mix  and  yield 
variances for X Ltd? 

 
 
 
 
 
 

background image

21 

 
 

 

 

                                

 

Labour mix and yield (productivity) variances 
 
When  different  types  of  labour  e.g.  different  grades  or  skills,  can  be  used  as  substitutes  for 
each  other,  the  labour  efficiency  variance  can  be  subdivided  into  a  mix  and  yield 
(productivity) variance when there exists two or more types of labour that can be substituted 
for one another e.g. to provide a service or manufacture a product. The sum of the labour mix 
and yield variances will be equal the labour efficiency variance.   
 
The labour mix variance can be calculated by using the same two different methods that can 
be applied to material mix and yield variances, the ‘individual valuation bases’ which is the 
easiest  to  apply  and  the  ‘average  valuation  bases’.  If  the  examiner  does  not  specify  which 
method  to  use,  the  individual  valuation  bases  is  the  easiest  method  to  apply,  both  methods 
give the same answer as a total mix variance, but the individual values for each type of labour 
which makes up the mix variance will be different depending on each method used.   
 
The  yield  variance  for  labour  is  also  an  identical  calculation  when  compared  to  material 
yield.  For labour mix and  yield  follow the same guidance as  for material  mix and  yield but 
use labour hours and labour rates rather than material usage and material prices. 
 
Relationship for labour variance calculations 

 
There  can  be  an  interdependent  relationship  (both  connected  to  each  other),  between  a  mix 
and yield variance, for example a higher skill of labour used in substitute for a lower skill of 
labour would normally give an adverse mix variance, (higher skills normally demand a higher 
labour  rate),  but  at  the  same  time  perhaps  a  favourable  yield  variance,  due  to  the  greater 
experience and efficiency of the higher skill of labour substituted.   

 

 
 
 
 

Total 

Labour 

Variance 

Labour 

Rate 

Variance  

Labour 

Idle Time 

Variance 

Labour 

Efficiency 

Variance 

Labour 

Mix 

Variance 

Labour 

Yield 

Variance 

background image

22 

 
 

 

 

                                

 

A word of caution, favourable variances, especially when dealing with mix and yield do not 
necessarily  mean  you  have  improved  an  organisations  cost  effectiveness  or  quality  of  the 
product.  Mixing more water and less concentrated flavor to make a drink can certainly create 
a favorable mix variance (water is cheaper) but it can have an effect on the quality of the end 
product as well, in this case the taste of the drink may change.  In the case of favorable yield 
variance more output from a certain amount of input could mean you are short changing the 
customer  e.g.  producing  soft  drinks  in  500ml  bottles  but  increasing  efficiency  by  only 
bottling  an  average  of  480ml  in  each  bottle.    Mix  or  yield  variances  can  have  a  damaging 
impact on the organisations brand image and reputation, in turn leading to a loss of customers 
and  sales.    Mix  and  yield  variances  must  therefore  be  interpreted  and  used  very  carefully, 
ideally if the standard information is correct then expect no planning errors or variances at all.   
 
 
 
 
 
 
 
 
 
 
 
 
      
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

23 

 
 

 

 

                                

 

 
Example 5.7 
 
Mr  Chumney-Warner,  the  accountant  that  left  Ramsey  Oliver  Restaurants  due  to  personal 
grievances against the organisation and has now set up an audit practice, providing work to 
local  business  within  the  area.    Even  though  being  a  service  organisation,  Mr  Chumney-
Warner  recognises  that  labour  mix  and  yield  variances  can  also  be  applied  to  service 
organisations.  He has created a standard cost for one audit, which normally takes a partner, 
semi-senior and junior together a total of 20 hours to perform. 
 
Standard cost details for one audit 
 
 

 

 

 

 

 

 

 

  £ 

Partner  

 

3 hours   @ £100 per hour 

 

300 

Semi-senior 

 

5 hours   @ £70 per hour 

 

350 

Junior   

 

12 hours @ £30 per hour 

 

360 

 

 

 

 

 

 

 

        1,010 

 
During the month of February, time sheets recorded the below information.  In total 90 hours 
were recorded and logged as  audit work, this time was for completion of five audits  during 
the period.  The new junior that had been recruited was under allot  of pressure  and did  not 
cope well.  This  meant  the semi-senior had to  be involved more in  the compliance work to 
improve  the  quality  of  the  audit  files.    Mr  Chumney-Warner  was  pleased  however  that  his 
time  as  a  partner  was  used  less  because  of  the  final  quality  of  the  audit  files,  due  to  more 
involvement from the semi-senior.   
 
Actual time worked and paid for five audits: 
 

 

 

 

 

 

 

 

 

Partner  

 

12 hours  

Semi-senior 

 

40 hours  

Junior   

 

38 hours 

 

 

 

 

 

 

 

 

 

90 hours 

 
The standard rates per hour paid to staff were the same as budget. 
 
Produce the labour mix and yield variances for the above period? 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

24 

 
 

 

 

                                

 

 
5.5 

Sales mix and quantity variances 

 
The sales volume variance can be further subdivided into a mix and a quantity variance.  
 
The sales mix variance shows the change in the different product lines being sold and the 
impact it has on profit or contribution.  
 
The sales quantity variance shows the change in the different total amount of units being 
sold
 and the impact it has on profit or contribution.    
 
The  sales  mix  variances  can  be  calculated  by  using  two  different  methods,  the  ‘individual 
valuation  bases’  which  is  the  easiest  to  apply  and  the  ‘average  valuation  bases’.  If  the 
examiner does not specify which method to use, the individual valuation bases is the easiest 
method  to  apply,  both  methods  give  the  same  answer  as  a  total  mix  variance,  but  the 
individual  values  for  each  sales  line  which  make  up  the  mix  variance  will  be  different 
depending on each method used. 
 

 
 
 
 
 

 
Sales mix variance (individual valuation bases)  

 

Actual output         Did Mix      Should Mix           Standard Profit       Variance 

    

 

 

 

(1)  

 

(2)  

 

 

(3) 

Product A 

 

 X  

 

 X 

 

 

x £x =               £x (A) 

Product B 

 

 X  

  

 X 

 

 

x £x =               £x (F) 

Product C 

 

 X 

 

 X 

 

 

x £x =               £x (A) 

 X  

 

 X 

 

 

             

 £x (A)  

           

Approach 

 

1.  (1) Record the actual quantity of units sold and add this up. 
2.  (2) Take the actual quantity of  units sold as a total from column (1) recalculate for 

each product how much you should have sold according to the standard (budgeted) 
mix. Column (1) total should be equal to column (2) total. 

3.  Deduct (1) – (2) then multiply by the standard profit (3) for each product to get the 

variance  for  each  product.    The  sum  of  the  variances  individually  is  the  total  mix 
variance. 

 

Interpretation 

 

  If you sell a quantity of product which is more than the standard mix there would be 

a favourable variance. 

  If you sell a quantity of product which is less than the standard mix there would be 

an adverse variance. 

 

background image

25 

 
 

 

 

                                

 

 

 
 
 
 
 

 
Sales mix variance (average valuation bases)  

 

Actual output         Did Mix   Should Mix     Standard Price  WA Standard   Variance 
                                                                                                      Profit                                            
                                    (1)  

 

(2)  

 

(3)                      (4) 

 
Product A 

 

X  

 

 

x (£x               - £x)  =              £x (A) 

Product B 

 

X  

 

 

x (£x              - £x)  =              £x (F) 

Product C 

 

 

 

x (£x    

- £x) =              £x (A) 

X  

 

 

 

             

 

 £x (A) 

 

           

Approach 

 

1.  (1) Record the actual quantity of units sold and add this up. 
2.  (2) Take the actual quantity of  units sold as a total from column (1) recalculate for 

each product how much you should have sold according to the standard (budgeted) 
mix. Column (1) total should be equal to column (2) total. 

 

Note: Up to this point this is an identical approach to the individual valuation bases. 

 

1.  (4)  Calculate  the  weighted  average  standard  profit  of  one  unit  for  all  products 

‘together’ by using the standard cost information provided e.g. standard total product 
profit ÷ standard units of products sold = the weighted average standard profit of a 
unit. 

2.  Deduct (2) from (1) then multiply by the standard profit (3) for each product less the 

weighted  average  standard  profit  (4)  for  all  products  together,  this  will  find  the 
variance  individually  for  each  product.    The  sum  of  these  variances  individually  is 
the total mix variance 

 
Interpretation 

 

  If you sell more of a more profitable product when compared to the standard mix 

the variance will be favourable. 

  If you sell more of a less profitable product when compared to the standard mix the 

variance will be adverse

  If you sell less of a more profitable product when compared to the standard mix the 

variance  will  be  adverse.  This  is  because  less  profitable  products  will  be  sold  in 
substitute therefore decreasing profits.  

  If you sell less of a less profitable product when compared to the standard mix the 

variance will be favourable. This is because more profitable products will be sold in 
substitute therefore increasing profits. 

 

background image

26 

 
 

 

 

                                

 

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
Sales quantity variance 

 

Actual output       Should Mix      Budget Mix         Standard Profit       Variance 

    

 

 

           (1)  

               (2)    

 

    (3) 

Product A 

 

X  

 

    X 

 

 

x £x =                    £x (A) 

Product B 

 

X  

 

    X 

 

 

x £x =                    £x (F) 

Product C 

 

 

    X 

 

 

x £x =                    £x (A) 

X  

 

    X 

 

 

             

      £x (A) 

 

           

Approach 

 

1.  (1) Take the actual quantity of units sold as a total recalculate for each product how 

much you should have sold according to the standard (budgeted) mix.  

2.  (2) Record the budgeted quantity of units sold and add this up. 
3.  Deduct (2) from (1) then multiply by the standard profit (3) for each product to get 

the variance for each product.  The sum of the variances individually is the total mix 
variance. 

 

background image

27 

 
 

 

 

                                

 

 
 
 
 
 

 
Example 5.8 - Worked example on sales mix and quantity variances 
 
Tasty Meals Ltd makes and sells 2 meals, camel dansak and pigeon vindaloo. The budgeted 
sales and profit are as follows: 
 

 

Sales (units) 

Profit (£) 

Profit per unit (£) 

Camel dansak 

400 

4,000 

10 

Pigeon vindaloo 

300 

1,800 

 

 

5,800 

 

 
Actual sales were 140 units of camel dansak and 315 units of pigeon vindaloo.  
 
Calculate the sales mix and quantity variances. 
 
Sales mix variance 
 

 

Actual 

sales 

quantity 

Actual 

sales at 

budget mix 

(W1) 

Difference 

Contribution 

Variance 

Camel dansak 

140 

260 

120 (A) 

£10 

£1,200 (A) 

Pigeon vindaloo 

315 

195 

120 (F) 

£6 

  £720 (F) 

 

455 

455 

 

 

   £480 (A) 

 
Sales quantity variance 
 

 

Actual 

sales at 

budget mix 

(W1) 

Budget 

sales 

quantity 

Difference  Contribution 

Variance 

Camel dansak 

260 

400 

140 (A) 

£10 

£1,400 (A) 

Pigeon vindaloo 

195 

300 

105 (A) 

£6 

   £630 (A) 

 

455 

700 

245 (A) 

 

£2,030 (A) 

 
Workings 
 
W1 – Actual sales at budget mix 
 
Camel dansak = 400 / 700 x 455 = 260 
Pigeon vindaloo = 300 / 700 x 455 = 195 
 

background image

28 

 
 

 

 

                                

 

 
Example 5.9 – (CIMA past exam question) 
 
A  company  produces  trays  of  pre-prepared  meals  that  are  sold  to  restaurants  and  food 
retailers. Three varieties of meals are sold: economy, premium and deluxe. 
 
Extracts from the budget for last year are given below: 
 

 

Economy 

Premium 

Deluxe 

Sales quantity (units) 

180,000 

360,000 

260,000 

Selling price per tray 

$2.80 

$3.20 

$4.49 

Total sales revenue 

$504,000 

$1,152,000 

$1,167,400 

Direct material cost per tray 

$1.00 

$1.60 

$2.20 

Total direct material cost 

$180,000 

$576,000 

$572,000 

Direct labour cost per tray 

$0.50 

$0.50 

$0.50 

Total direct labour cost 

$90,000 

$180,000 

$130,000 

Variable overheads per tray 

$0.65 

$0.65 

$0.65 

 
Actual results for the last year were as follows: 
 

 

Economy 

Premium 

Deluxe 

Sales quantity (units) 

186,000 

396,000 

278,000 

Selling price per tray 

$2.82 

$3.21 

$4.50 

Total sales revenue 

$524,520 

$1,271,160 

$1,251,000 

Direct material cost per tray 

$1.10 

$1.50 

$2.10 

Total direct material cost 

$204,600 

$594,000 

$583,800 

Direct labour cost per tray 

$0.52 

$0.54 

$0.48 

Total direct labour cost 

$96,720 

$213,840 

$133,440 

Variable overheads per tray 

$0.64 

$0.66 

$0.63 

 
Actual fixed overheads were $546,000. 
 
Calculate  the  sales  quantity  contribution  variance  and  the  sales  mix  contribution 
variance. 
  
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

29 

 
 

 

 

                                

 

5.6 

Interpretation of variance calculations 

 
In  your exam  you could  be asked to interpret the variances  you have calculated or interpret 
from  variances  already  provided  to  you  in  a  question.    The  examiner  may  require  you  to 
explain  some  possible  reasons  why  a  favourable  or  adverse  variance  has  occurred.    It  is 
important to give an answer that is practical and relates to the scenario or organisation, also to 
apply consistent explanations with your answer e.g. if an adverse variance then give possible 
reasons  for  the  cause  of  an  adverse  not  favourable  variance.  Possible  causes  or  reasons  for 
variances have been included in the table below. 
 

Sales price 

variance 

  Unplanned price increases for the product or service sold. 

 

  Unplanned  price  reductions  e.g.  attracting  additional  business  by 

offering discounts or price promotions. 

 

 

Interdependence (sales price and volume (demand) are both connected to each other) e.g. a 

lower price for the product or service sold would normally cause an adverse sales price 

variance, however the effect of lowering price is normally to sell more, so the sales volume 

variance would be expected to be favourable, and vice versa. 

 

Sales volume 

variance 

  Seasonal changes in demand for the final product or service sold. 

 

  Economic (business) recession or boom. 

 

 

Material price 

variance 

  Different sources of supply may cost more or less. 

 

  Unexpected general price increases or decreases. 

 

  Alteration in quantity discounts. 

 

  Alteration in exchange rates for imported materials or components. 

 

  Substitution  of  a  different  grade  of  material  which  is  cheaper  or 

more expensive. 

 

  Standard set at mid-year price, due to seasonal fluctuations and price 

volatility,  so  one  would  expect  a  favourable  price  variance  for  part 
of the year and an adverse variance for the rest of the year. 

 

 

Interdependence (material price and usage both connected to each other) e.g. a lower price 

for material obtained would give a favourable material price variance, but if an inferior 

quality it could cause more wastage and therefore an adverse material usage variance, and 

vice versa. 

 

Material usage 

variance 

  Higher or lower incidence of scrap, wastage, evaporation etc. 

 

  Alterations  to  product  design  e.g.  product  now  consumes  more  or 

less material. 

 

  Substitution  of  a  different  grade  of  material  e.g.  cheaper  and  more 

inferior material can create more wastage. 

 

 
 
 

background image

30 

 
 

 

 

                                

 

 

Labour rate 

variance 

  Unexpected national wage increases. 

 

 

Overtime and bonus payments different from the standard ‘average’ 
plan. 

 

  Substitution of a different grade of labour which is cheaper or more 

expensive. 

 

 
 

Interdependence (labour rate and efficiency both connected to each other) e.g. a lower rate 

for labour skills obtained would give a favourable labour rate variance, but if these staff are 

inexperienced and face a steep learning curve, this could cause less efficiency  and therefore 

an adverse labour efficiency variance, and vice versa. 

 
 

Labour 

efficiency 

variance 

  Improvement in the efficiency of working methods or conditions e.g. 

through training or new technology. 

 

  Introduction  of  new  incentive  schemes  e.g.  higher  productivity  or 

efficiency bonuses could make staff work more quickly. 

 

  Substitution  of  a  different  grade  of  labour  e.g.  less  skilled  staff 

normally means they are less efficient. 

 

 

Variable 

overhead rate 

variance 

  Unexpected price changes for variable overhead items. 

  Seasonal effects e.g. heat and light in winter.  (This arises where the 

annual  budget  is  divided  into  four  equal  quarters  of  thirteen  equal 
four-weekly periods without allowances for seasonal factors.  Over a 
whole year the seasonal effects would cancel out.). 

 

Variable 

overhead 

efficacy 

variance 

  This  variance  is  interdependent  on  the  labour  efficiency  variance 

therefore see reasons for labour efficiency variances.   

Fixed overhead 

expenditure 

variance 

  Changes in prices relating to fixed overhead items e.g. rent increase. 

Fixed overhead 

volume 

variance 

  Change  in  production  volume  due  to  changes  in  sales  demand  or 

alterations  to  inventory  holding  policy.  Production  lost  through 
strike, idle time etc. 

 
 
 
 

background image

31 

 
 

 

 

                                

 

 
Example 5.10   – (CIMA past exam question) 

 

Marshall  Limited operates a business that sells advanced photocopying machines and offers 
on-site  servicing.  There  is  a  separate  department  that  provides  servicing.  The  standard  cost 
for  one  service  is  shown  below  along  with  the  operating  statements  for  the  Service 
Department  for  the  six  months  to  30  September  2003.  Each  service  is  very  similar  and 
involves the replacement of two sets of materials and parts. 

 

Marshall Limited’s budgets for 5,000 services per month. 
 
Standard cost for one service 

£ 

Materials – 2 sets @ £20 per set  

 

 

 

40 

Labour – 3 hours @ £11 per hour 

 

 

 

33 

Variable overheads – 3 hours @ £5 per hour  

 

15 

Fixed overheads – 3 hours @ £8 per hour  

 

 

24 

Total standard cost    

 

 

 

          112 

 
Operating statements for six months ending 30 September 2003 
 
Months  

 

 

      1            2          3           4            5           6            Total 

Number of  
services per  
month   

 

 

   5,000     5,200    5,400    4,800     4,700    4,500 

 29,600                           

 
                                                       £            £           £           £            £           £              £ 
Flexible budget 
Costs   

 

 

560,000 582,400 604,800 537,600 526,400 504,000 3,315,200 

Less: variances: 

 

Materials 
Price    

 

 

 5,150F  3,090F  1,100F   -2,040A  -5,700A -2,700A  -1,100A 

Usage   

 

 

-6,000A 2,000F -4,000A -12,000A -2,000A       0      -22,000A 

 

Labour 
Rate    

 

 

26,100F 25,725F 27,331F 18,600F 17,400F 15,515F 130,671F 

Efficiency  

 

 

 5,500F   9,900F 12,100F -12,100A -4,400A -11,000A      0 

 

Variable overheads: 
Spending  

 

 

-3,500A  -3,500A  -2,500A  -4,500A   500F    2,500F -11,000A 

Efficiency 

 

 

 2,500F     4,500F    5,500F  -5,500A -2,000A -5,000A       0 

 

Fixed overheads: 
Expenditure   

            -3,000A -5,000A -5,000A -15,000A  5,000F  5,000F  -18,000A 

Volume  

 

 

      0        4,800F   9,600F  - 4,800A -7,200A -12,000A  9,600A 

Actual costs    

 

533,250 540,885 560,669  574,940  524,800 511,685 3,246,229 

 
Note: “A” = adverse variance; “F” = favourable variance 
 

background image

32 

 
 

 

 

                                

 

 
Required: 
 
(a)  Prepare  a  summary  financial  statement  showing  the  overall  performance  of  the  Service 
Department for the six months to 30 September 2003.  

 

(b)  Write  a  report  to  the  Operations  Director  of  Marshall  Limited  commenting  on  the 
performance  of  the  Service  Department  for  the  six  months  to  30  September  2003.  Suggest 
possible  causes  for  the  features  you  have  included  in  your  report  and  state  the  further 
information that would be helpful in assessing the performance of the department.  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
5.7 

Investigating the cause of variances  

 

Factors to consider before investigation or control action is taken  

 

1.  Consider  the  size  or  ‘materiality’  of  the  variance  e.g.  the  variance  relatively  or 

absolutely could be adverse but small in value, therefore not considered a problem. 

2.  The general trend of the variance e.g. control charts could indicate the variance trend 

is persistent (not random) and therefore should be investigated. 

3.  Consider  the  type  of  standard  used  e.g.  ideal  standard  unrealistic  or  planning  errors 

exist in the budget, knowing this could save wasting time investigating variances with 
no operational faults. 

4.  Interdependence with  other variances  e.g. poor quality of material  already  explained 

by the favourable price variance, variable overhead efficiency variance explained by 
the labour efficiency variance etc. 

5.  The  likelihood  of  identifying  the  cause  of  the  variance  if  it  were  investigated  e.g.  if 

unlikely a cause can be found then there maybe no value obtained from investigating. 

6.  The  likelihood  that  if  the  cause  of  a  variance  is  found,  the  cause  or  reason  is 

controllable and therefore can be rectified. 

7.  The  cost  of  investigation  and  correction  must  be  compared  to  the  benefits  e.g.  cost 

savings or improvements in quality, if correction is applied.  The cost of investigating 
and correcting or rectifying variances can be very expensive.   

 

background image

33 

 
 

 

 

                                

 

Statistical methods for interpretation 

 

Variances  can  be  expressed  relatively  rather  than  absolutely,  the  variance  always  expressed 
as a percentage of standard (never actual) cost.  These percentages can be plotted on a graph 
over time to provide trend analysis for variances. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
        
 
  
 
 
 
 
 
Advantages of relative statistical analysis 

 

  Graphical  presentation  of  percentages  over  time  will  allow  easier  interpretation  and 

clearer understanding for any persistent deviations or exceptions. 

  By  working  in  percentages  (variance  ÷  standard  cost)  it  removes  any  distortion  for 

changes  in  the  monetary  size  of  variances  caused  by  the  activity  (output)  level 
changing for each period. 

 
 
 

 

 
 
 
 
 
 
 
 
 
 

Example of a percentage variance chart 
 
 
          % 
 
 
 
 
 
 

Favourable 
 
 
 

 

                  0 
                         JAN                         FEB                             MAR                         APR 
 
 
    Adverse 
 
 
 

Note: Each line represents two different variances monitored over the four months. 

 

background image

34 

 
 

 

 

                                

 

5.8 

Planning and operational variances 

 

 

Operational variances are the normal variance calculations as learned and applied earlier 

within this chapter. 

 

Planning variances are caused by the budget (standard) at the planning stage being wrong 

e.g. budgeting errors or poor planning when the budget was prepared.  The budget 

(standard) used would need revising if operational variance calculations are to be more 

realistic.  Planning variances help ensure that all planning errors within the budget 

(standard) are adjusted for or removed; the standard used for operational variances would 

therefore be more realistic. 

 

 

Process of calculating planning variances  

 

1.  Calculate  the  planning  variance.  This  adjusts  the  flexed  budget  (a  budget  based  on 

actual sales or production volume) by comparing the ex ante standard (beforehand) to 
an  ex  post  (revised  or  realised)  standard.  All  planning  variances  follow  a  similar 
proforma because they all adjust the flexed budget up or down due to the revision of a 
standard.    Just  like  operational  variances  planning  variances  can  be  favourable  or 
adverse. 

2.  Now  that  the  budget  (standard)  has  been  adjusted  calculate  operational  variances  in 

the normal way but now using the new (revised) standard. 

 

The effect is to sub-divide variances into two components 

 

1.  The  planning  variance  which  is  beyond  the  operational  control  of  management  and 

staff e.g. errors due to poor planning. 

2.  The operational variance which is normally within the control of staff and now more 

realistic as a yardstick because calculations would include any revisions to standard.   

 

Advantages of calculating planning variances 

 

  Helps highlight variances between those which are controllable and those which are 

uncontrollable. 

  Helps motivate managers and staff e.g. avoids staff being blamed for faulty planning 

and  gives  a  fairer  reflection  of  any  operational  variances  calculated  when  assessing 
any  operational  efficiencies  or  inefficiencies.  Management  and  staff  would  be 
appraised  more  fairly  for  any  favourable  or  adverse  deviations  that  are  within  their 
control. 

  Use of realistic standards in order to measure performance gives better management 

information for control purposes. 

 

Limitations of calculating planning variances 

 

 

Determining a ‘realistic standard’ in the first place, often management or staff could 
politically  place  more  emphasis  on  ‘bad  planning’  rather  than  ‘bad  management’ 
when it comes to exception reporting. 

  Further  analysis  of  variances  can  be  more  time  consuming  and  costly  than  the 

conventional approach. 

background image

35 

 
 

 

 

                                

 

 
Example 5.11 

 

Using  the  information  contained  within  Example  4.2,  demonstrate  how  Ramsey  Oliver 
Restaurants would deal with the variance calculations if you were told the following?  

 

Note:  Treat each example below as a separate consideration. 

 

a)  A  pay  rise  was  given  to  kitchen  staff  as  from  the  beginning  of  last  month. 

The  new  labour  rate  payable  to  chefs  being  £11.25  rather  than  as  budgeted 
£9.00 a hour, this had been overlooked and was not reflected in the budget. 

b)  Expected  labour  efficiency  of  15  minutes  (0.25  hours)  per  meal  served  has 

always  been  considered  by  management  as  too  generous,  the  budget  was 
supposed to be updated last week using only 12 minutes (0.2 hours) per meal 
but was overlooked during the planning process. 

c)  Due to a salmonella scare across the country the price of chicken had fallen 

to  £2  per  kg  at  the  beginning  of  the  week.  According  to  management  this 
should be reflected in the budget. 

d)  Due  to  more  skin  and  bone  on  the  poultry  purchased  for  the  month,  it  was 

considered more realistic by management that 0.35kg of chicken should have 
been served for each meal rather than currently 0.3kg of chicken. 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

36 

 
 

 

 

                                

 

5.9 

Machine expenditure and efficiency variances  

 

Machine  variances  would  use  the  same  method  of  calculation  as  labour  rate  and  efficiency 
variances  e.g.  machines  have  a  rate  of  overhead  per  hour,  they  can  also  make  more  or  less 
product than standard efficiency targets which have been set. 
 
 
Example 5.12 
 
In the bar at Ramsey Oliver Restaurants they produce a ‘banana extravaganza’ by using a 
machine blender (it has proved to be very popular). 
 
Standard processing time for every 50 half-pint glasses is 0.6 hours at £40 variable overhead 
per hour. 
 
During one hot summer week there was 42 hours of processing time at a total cost that week 
of £1,880, 1,900 pints were produced. 
 
Calculate the machine expenditure and efficiency variances for this machine? 
 
 
 
 
 
 
 
 
 
 
 
 
What  if  you  were  told  that  the  machine  had  been  replaced  at  the  beginning  of  the 
period  with  a  machine  that  is  20%  faster  than  the  previous  model,  but  this  had  not 
been reflected in the budget? 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

37 

 
 

 

 

                                

 

5.10 

Benchmarking 

 

 

“A continuous, systematic process for evaluating the products, services and work processes 

of an organisation that are recognised as representing best practice, for the purpose of 

organisational improvement.”  

(Michael Spendolini) 

 

 
Four types of benchmarking  
 
A hospital is used to illustrate the following types of benchmarking 
 

1.  Internal.    Compare  an  internal  function  to  ‘the  best  internally’  within  the  same 

organisation  e.g.  different  methods  of  cleaning  used  by  hospital  wards  within  the 
same hospital. 

 
2.  Best  practice  or  functional.    Compare  an  internal  function  to  ‘the  best’  but  not 

necessarily an organisation in the same industry e.g. compare administration activities 
or cleaning methods to other hospitals or other organisations other than a hospital not 
involved in healthcare. 

 
3.  Competitive.    Hospital  or  healthcare  services  are  compared  to  that  of  rival 

‘competition’ in the same industry e.g. methods of patient care and levels of service 
compared and contrasted with other hospitals. 

 
4.  Strategic.    Comparison  in  terms  of  an  organisations  ‘strategic  choices’  made  to  the 

most  successful  market  leader  e.g.  review  organisational  structure,  culture,  mission 
statement  and  goals  of  other  hospitals  higher  in  ‘quality  league  tables’.    Strategic 
choices could include outsourcing or decisions about the closure of expensive wards 
even though unpopular. 

 
Companies to be the very best must  
 

  Establish where customers perceive differences 

  Set the very best standards to exceed 

  Establish what the competition is doing 

  Encourage staff, manage knowledge, ideas and innovate to exceed  

 
 
 
 
 
 
 
 

background image

38 

 
 

 

 

                                

 

A process for benchmarking 
 

1.  Gain senior management commitment to establish benchmarking as a process within 

the organisation and educate staff and stakeholders about the benefits.  Participate and 
consult with staff and stakeholders. 

2.  Consider the benefits  against the cost  for each  activity to  be benchmarked to  ensure 

economic or financial justification. 

3.  Assign  responsibilities  to  a  team  of  staff  e.g.  set  goals;  establish  BM  processes  and 

systems, checklists and documentation.  

4.  Identify potential partners and known leaders. 
5.  Undertake  the  process  of  benchmarking  e.g.  test,  measure,  observe,  experiment  or 

investigate. 

6.  Gather, analyse and summarise information collected and documented. 
7.  Gap analysis undertaken for deficiencies identified e.g. standard v actual. 
8.  Implement improvement e.g. new programmes, processes and procedures. Education 

and  participation  encouraged  by  those  affected,  avoid  being  over  critical  for 
weaknesses identified.  Set objectives and manage change. 

9.  Monitor  and  repeat  regularly  to  discourage  complacency,  follow  up  improvements 

implemented to ensure the expected benefits are realised. 

 
Benefits of benchmarking 

 
  Better understanding of the business, competition and customers. 
  Improves business performance and discourages complacency.  
  Good way of comparing competitive strategies to reposition products. 
  You can learn from other organisations mistakes. 
  You don’t need to ‘re-invent the wheel’ for innovation and creativity e.g. learn from 

other organisations and a source of new ideas. 

  Advance warning for deteriorating competitive performance e.g. faster awareness of 

industry innovation and other competitor decisions. 

  Fewer complaints, product returns, and warranty claims e.g. quality improves. 
  Leaner and more cost efficient organisation. 
  Customer satisfaction and brand loyalty increases. 
  Sales and profitability will improve in the long-term. 

 
Drawbacks of benchmarking 

 

  Benchmarking systems and programmes can be costly and time consuming 
  The diversity and complexity of information can ’overload’ management e.g. so much 

information; management cannot see the wood through the trees. 

  Obtaining  information  to  actually  undertake  a  BM  exercise  can  be  a  problem  e.g. 

absent, historical or out of date. 

  Confidential information could be leaked or compromised when shared 
  Deciding who the ‘best in a class’ is? 

  Keeping staff motivated e.g. staff can be criticised and once they exceed standards the 

standard is normally raised 

 
 
 

background image

39 

 
 

 

 

                                

 

5.11 

McDonaldization 

 

Modern  manufacturing,  questions  the  thought  to  whether  standard  costing  still  plays  a 
valuable part when considering information for control purposes. 

 

Characteristics of modern manufacturing 

  Dynamic environments, customisation and differentiation of products. 

  Shorter product life-cycles and high levels of automation. 

  Higher concern for quality and customer satisfaction. 

 

George  Ritver  in  his  book  ‘The  McDonaldization  of  Society’  listed  the  advantages  of 
producing  standard  (homogenous  or  identical)  products,  the  pinnacle  comparison  being 
McDonalds,  with  its  fast  food strategy of uniformity of operations  and delivery on a  global 
basis.  A concept you will find within thousands of companies, especially large corporations 
e.g.  Audi  or  V/W  Group  incorporating  hundreds  of  the  same  standard  components  within 
their different ranges of cars they manufacture.  Although surely you would understand such 
an  idea  better  through  the  use  of  a  ‘Big  Mac’  right?    Food  already  pre-prepared  before 
cooking e.g. cheese sliced, salads prepared, sauces all pre-packed and easy to open and serve.  
Standardisation  of  machinery,  uniforms  and  packaging  e.g.  standard  product,  sachets, 
drinking cups and paper bags.  Automation of dispensers, cooking processes and staff… even 
a standardised departure e.g. have a nice day!   

 

Some facts about McDonalds 

  Started as a hot dog stand in 1939 by 2 brothers (Richard and Maurice McDonald). 

  30,000 outlets in 119 countries. One of the first to end waiter service. 

  Cut their menus down to a few standard and homogenous dishes for simplicity. 

  Plates were replaced with cardboard containers to save on washing up. 

 

Advantages of McDonaldization 
Standardisation reduces cost and improves efficiency. 

 

  Control e.g. easier to create a pre-defined standard because of uniformity of product 

specification and processes, easier to manage, organise, train and control workers. 

  Efficiency e.g. combined with specialisation it is the most efficient way of working 

within large organisations. 

  Predictability e.g. customer always knows what they are buying to give reassurance 

and support brand recognition. 

  Calculability e.g. quantitative so easier to interpret expected results. 
  Proficiency of staff performance can be assessed more effectively due to consistent 

standards applied. 

 

 
Example 5.13  – (CIMA past exam question) 
 
UV  Limited  is  a  catering  company  that  provides  meals  for  large  events.  It  has  a  range  of 
standard  meals  at  fixed  prices.  It  also  provides  meals  to  meet  the  exact  requirements  of  a 
customer and prices for this service are negotiated individually with each customer. 

 

Discuss how a ‘McDonaldisation’ approach to service delivery would impact on budget 
preparation and control within UV Limited? 

 

background image

40 

 
 

 

 

                                

 

5.12 

Diagnostic related or reference groups (DRG) ‘can applied to a Big Mac’ 

 

Standard  costing  can  be  applied  to  service  organisations  such  as  the  health  services, 
accountancy  practices,  fast  food  outlets  etc.  The  diagnostic  reference  group  or  healthcare 
resource group is a system of classifying hundreds of different medical treatments within the 
healthcare  sector.    It  applies  standardisation  by  recognising  that  similar  medical  illnesses 
require  essentially  similar  treatments  and  care.    There  are  around  800  DRG  classifications 
that exist within the healthcare industry sector.  

 

DRG applied to health care services 

 

  Standardise resources e.g. beds/wards/consultancy time/medication etc. 

  Standardise patient treatment e.g. specifications of how treatments are applied. 

  Standardised codes for insurance companies or payments to the NHS (or other private 

health care providers) based on standard prices used. 

  Government can benchmark performance and provide league tables for hospitals. 

 

Such  a  system  is  not  without  its  critics,  arguing  that  surely  it  is  the  qualitative  factors  in 
patient  treatment  that  is  more  important  than  the  quantitative  measures  when  it  comes  to 
patient care, and not every operation or treatment can be dealt with in a single best way.  If 
payments  are  made  to  hospitals  based  on  a  standard  price  for  each  DRG,  this  could  mean 
overzealous treatment of a patients in order to save cost, but at the same time compromising 
the quality of patient care. 

 

The characteristics of services 

 

  Intangibility e.g. no material substance or physical existence of the service contrasted 

to a tangible good, difficult to tell in advance what you will be getting. 

  Legal  ownership  e.g.  little  physical  evidence  exists  for  its  performance,  so  you  can 

never return it if it is faulty. 

  Instant  perishability  e.g.  unlike  physical  goods,  services  cannot  be  stored,  unused 

capacity cannot be stored for future use. 

  Heterogeneity  (not  perfectly  identical  or  variable)  e.g.  each  time  the  service  is 

performed even to the same customer it is different each time, physical goods tend to 
be homogenous (perfectly identical) when produced.  

  Inseparability  e.g.  the  service  cannot  be  separated  from  the  person  who  provides  it 

and it is normally produced at the same time the customer requires it. 

 

background image

41 

 
 

 

 

                                

 

 
Example 5.14  – (CIMA past exam question) 
 
The standard cost schedule for hospital care for a minor surgical procedure is shown below. 
 
Standard Cost of hospital care for a minor surgical procedure 

 

Staff: patient ratio is 0·75:1 

  £ 

Nursing costs: 2 days x 0·75 x £320 per day   

 

 

 480 

Space and food costs: 2 days x £175 per day  

 

 

 350 

Drugs and specific materials    

 

 

 

 

 115 

Hospital overheads: 2 days x £110 per day   

 

 

 220 

Total standard cost    

 

 

 

 

          1,165 

 
The  actual  data  for  the  hospital  care  for  one  patient  having  the  minor  surgical  procedure 
showed that the patient  stayed in  hospital for three days.  The cost  of the drugs  and specific 
materials for this patient was £320. There were 0·9 nurses per patient on duty during the time 
that the patient was in hospital. The daily rates for nursing pay, space and food, and hospital 
overheads were as expected. 
 
Prepare  a  statement  that  reconciles  the  standard  cost  with  the  actual  costs  of  hospital 
care  for  this  patient.  The  statement  should  contain  five  variances  that  will  give  useful 
information to the manager who is reviewing the cost of hospital care for minor surgical 
procedures? 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

42 

 
 

 

 

                                

 

5.13 

Further question practice 

 

 
Example 4.15 

 

MCQ 1.1 
 
X Plc uses a standard absorption costing system. Details for the month were as follows 
 

Budget 

 Actual 

 
Sales units 

 

 

 

 

  7,300  

  6,780 

 
Selling price per unit   

 

 

£13.00  

£13.80 

Profit per unit   

 

 

 

  £5.00  

  £5.20 

 
The sales price and volume variance for the month was? 

 

Volume 

Price 

a) 

£2,600 (A) 

£5,424 (F) 

b) 

£2,600 (A) 

£5,424 (A) 

c) 

£2,600 (F) 

£4,480 (A) 

d) 

£2,600 (F) 

£4,480 (F) 

 
The following data is to be used for MCQ 1.2 and 1.3 

 

Z Plc sells garden gnomes that it purchases from a local distributor.  Its budget shows for the 
four-week period that it plans to sell 800 gnomes at a unit price of £30, which would give a 
contribution to sales ration of 40%. Actual sales were 770 gnomes at an average selling price 
of £27.50, the actual contribution to sales ratio averaged 27% 

 

MCQ 1.2 

 

The sales price variance was? 
 

a)  £2,000 (A) 
b)  £1,925 (F) 
c)  £1,925 (A) 
d)  £2,000 (F) 

 

MCQ 1.3 

 

The sales volume variance was? 
 

a)  £360 (A) 
b)  £360 (F) 
c)  £223 (A) 
d)  £223 (F) 

 
 

background image

43 

 
 

 

 

                                

 

 
The following data is to be used for MCQ 1.4 and 1.5 

 

Meat and Veg Ltd manufactures steak and kidney pies, the standard cost of a 1kg pie being as 
follows: 
 

 

 

 

              £ 

0.6kg Steak 

£5.60 per kg  3.36 

0.6kg Kidney  @ 

£1.40 per kg  0.84 

 

 

 

 

 

4.20 

 

Actual data for the month was as follows: 
 
1kg pies produced 

 

 

1,350 

 

Raw material used: 
 

 

 

 

 

Steak  Kidney 

Quantity (Kg)   

 

 

   852       990 

Cost (£) 

 

 

 

5,106    1,287 

 
MCQ 1.4 

 

The total material mix variance (to the nearest £) using the weighted average approach 
for both ingredients would be? 
 

a)  £145 (A) 
b)  £145 (F) 
c)  £290 (A) 
d)  £290 (F) 

 

MCQ 1.5 

 

The total material yield variance would be? 
 

a)  £1,134 (A) 
b)  £1,134 (F) 
c)  £777 (A) 
d)  £648 (F) 

 
 
 
 
 
 
 
 
 
 
 
 
 

background image

44 

 
 

 

 

                                

 

 
MCQ 1.6 
 
The following data has been extracted from the budget of XL Plc: 
 

Activity 

Overhead cost 

                             (Machine hours)           £ 
 

 

 

10,000  

      £25,000 

 

 

 

12,000  

      £29,000 

 

 

 

18,000  

      £41,000 

 
In  May  2002,  the  actual  activity  was  12,750  machine  hours  and  the  actual  overhead  cost 
incurred was £32,560. 
 
The overhead expenditure variance was? 
 

a)  £2,060 (A) 
b)  £2,060 (F) 
c)  £1,748 (A) 
d)  £1,748 (F) 

 
MCQ 1.7 
 
BB Plc standard cost of labour time per unit was as follows: 
 
4 Hrs @ £5.60  

£22.40 

 
The budgeted and actual number of units produced for this period was 4,000 and 4,260 units 
respectively, giving an adverse labour efficiency variance of £2,386 (A). 
 
The actual labour hours worked for the period was? 
 

a)  17,466 
b)  16,614 
c)  16,426 
d)  15,574 

 
 
 
 
 
 
 
 
 
 
 
 

background image

45 

 
 

 

 

                                

 

 
MCQ 1.8 
 
ABC  Ltd  standard  cost  of  material  X  which  is  used  to  assemble  their  final  product  is  as 
follows 
 
2kg @ £6.50 = £13.00 
 
3,000  units  were  produced  for  the  period.    This  gave  a  material  usage  variance  of  £4,875 
adverse, with material stock for the period rising by 800kg. 
 
The quantity of material purchased for this period was? 
 

a)  6,750kg 
b)  6,000kg 
c)  5,250kg 
d)  7,550kg 

 
MCQ 1.9 
 
A budget has been prepared which includes the standard cost of material per unit of £50 (4kg 
of material P at £12.50 per kg).  Budgeted production was 1,000 units.  There was a shortage 
of material P during this month and the price per kg fluctuated to £13.00 per kg.  During this 
period 950 units were manufactured at a material cost of £50,160 for 3,800kg of material P. 
 
What was the material price operational and planning variance for this period? 
 
        Operational 

Planning 

a) 

£760(A) 

£1,900(A) 

b)  £760(A) 

£1,900(F) 

c) 

£760(F)  

£2,000(F) 

d)  £760(A)  

£2,000(A) 

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

46 

 
 

 

 

                                

 

 

The following information is to be used for MCQ 1.10, MCQ 1.11 and MCQ 1.12 

 

A unit takes two types of labour to complete, unskilled and skilled.   
 
 

 

 

 

 

 

  £ 

0.5hrs @ £1.40 an hour (unskilled)   

0.70 

0.6hrs @ £7.50 an hour (skilled) 

 

4.50 

 

 

 

 

 

 

5.20 

 
On  a  Wednesday  afternoon  60  units  were  manufactured,  incurring  the  following  actual 
expenses: 

 

Unskilled  28  hours  £45.00 
Skilled      40 hours   £270.00 
 
MCQ 1.10 

 

The labour yield variance for the above period (to the nearest £1) was? 
 

a)  £9(A) 
b)  £9(F) 
c)  £6(A) 
d)  £9(F) 

 
MCQ 1.11 

 

It  was  found  during  the  period  that  the  labour  rate  per  hour  for  skilled  labour  was 
estimated as too high; it should have been £5.50 an hour rather than the £7.50 an hour 
used within the standard cost.  What was the operational and planning variance for the 
labour rate variance for skilled labour? 
 

Operational  Planning 

a)  £50(A)  

£80(A) 

b)  £50(F)  

£72(A) 

c)  £50(A)  

£80(F) 

d)  £50(F)   

£72(F) 

 
MCQ 1.12 

 

Using the new revised standard of £5.50 an hour for skilled labour, what would be the 
planning and operational efficiency variance for skilled labour if the budget was wrong 
and it should have been 0.5 hours per unit rather than the 0.6 hours as planned above? 
 

Operational  Planning 

a)  £55(A)  

  £33(F) 

b)  £55(F)   

  £33(A) 

c)  £55(A)  

  £45(A) 

d)  £55(F)   

  £45(A) 

 

background image

47 

 
 

 

 

                                

 

 
MCQ 1.13 

 

Moogle Plc uses 3kg of raw material Alpha into the production process to produce one unit of 
output,  but  have  calculated  that  this  would  be  after  25%  wastage  of  the  raw  material.    The 
cost of 1kg of Alpha is £25. 

 

What would be the standard usage of material Alpha, per unit of output, if Moogle Plc 
wanted to include the level of wastage within this standard? 
 

a) 3 kg 
b) 4 kg 
c) 5 kg 
d) 6 kg 

 

MCQ 1.14 

 

F  Ltd  uses  an  absorption  costing  system  in  which  labour  hours  are  used  as  the  basis  of 
recovering  overhead  costs.    Its  accounting  year  is  divided  into  13  four-week  periods,  with 
fixed  production  overhead  costs  budgeted  to  be  incurred  at  a  constant  rate  of  £300,000  per 
four-week  period.    Budgeted  labour  hours  per  four-week  period  were  40,000  hours.    In  the 
accounting period of quarter 2, actual hours worked were 37,576 and the output was 39,000 
standard hours. 

 

Given that actual fixed overhead expenditure was £315,000, what would have been the 
fixed overhead expenditure and volume variance for the above period? 
 
     Fixed overhead expenditure  

       Fixed overhead volume 

a)  £15,000 Adverse  

 

 

£7,500 Adverse 

b)  £15,000 Favourable   

 

£9,500 Favourable 

 

c)  £15,000 Adverse 

 

 

£10,680 Adverse 

d)  £15,000 Favourable   

 

£18,180 Adverse 

 
MCQ 1.15 

 

The following data is for XYZ plc. 
 

Budget         Actual 

Material 
Average price   

 

 

£5.00    

£5.60 

Average usage per unit  

 

3.5kg    

3.3kg 

Units produced  

 

 

2,000    

2,300 

 
The material usage variance is? 
 

a) £2,240 favourable 
b) £2,000 adverse 
c) £2,000 favourable 
d) £2,300 favourable 

 

background image

48 

 
 

 

 

                                

 

 
 
MCQ 1.16
 
 
The following data is for ABC plc. 
 

Budget          Actual 

Material 
Average price   

 

 

£7.00    

£7.60 

Units produced  

 

 

2,000    

2,300 

Material purchased 

 

 

6,500kg 

6,700kg 

 
The material price variance is? 
 

a) £3,900 adverse 
b) £4,020 adverse 
c) £7,590 adverse 
d) £9,300 adverse 

 
MCQ 1.17 
 
BB Plc standard cost of labour time per unit was as follows: 
 
8 Hrs @ £7.60  

£60.80 

 
The budgeted and actual number of units produced for this period was 4,000 and 4,260 units 
respectively, to meet production for the period 32,450 hours were worked. 
 
The labour efficiency variance for the period was? 
 

a) £12,388 favourable 
b) £3,420 adverse 
c) £12,388 adverse 
d) £3,420 favourable 

 
 
 

background image

49 

 
 

 

 

                                

 

5.14 

ABC and variance analysis. 

 
These  variances  are  appropriate  for  controlling  the  costs  of  unit-level  activities  and  can 
provide meaningful information for controlling those costs that are fixed in the short-term but 
variable in the longer-term (provided suitable cost drivers can be established). 
 
Illustration: 

 

T  Ltd  uses  activity-based  costing  to  allocate  its  overheads.  One  of  its  main  overheads  is 
machine set-up costs. The following information was available in relation to set-up costs for 
the last accounting period: 
 
Budget  

 

 

 

 

 

Actual 

Total number of units produced 264,000                   Total number of units produced 320,000 
 
Total number of set ups 330    

 

 

Total number of set ups 360 

 
Total set-up costs $52,800 

 

 

 

Total set-up costs $60,000 

 
The  following  activity-based  variances  in  relation  to  the  set-up  overhead  costs  can  be 
established:  
 
(i) The expenditure variance
 
(ii) The efficiency variance. 
 
(i) The expenditure variance 
 
Cost driver rate = $52,800 / 330 = $160 
 
Expected cost therefore = 360 x $160  

 

$57,600 

Actual cost  

 

 

 

 

            $60,000 

                                                                             –––––––– 

Variance  

 

 

 

 

              $2,400 A 

                      –––––––– 

(ii) The efficiency variance 
 
Expected no. of units per set up = 264,000 / 330 = 800 
 
Therefore expected no. of set ups for 320,000 = 320,000 / 800 

 = 

400 

 
Actual number of set ups 

 

 

 

 

             = 

360 

                                                                                                            ––––––– 

                               Difference  

 

 

  40 F 

                            ––––––– 

x standard rate per set up $160                    Variance  

 

      $6,400 F 

                             ––––––– 

 
 

background image

50 

 
 

 

 

                                

 

Key summary of chapter 

 

 

 

A standard cost is a planned (budgeted) or forecast unit cost for a product or service, which 

is assumed to hold good given ‘expected’ efficiency and cost levels within an organisation.  

A standard cost normally represents the planned (budgeted) or forecast unit cost for material, 

labour and overhead expected for a product or service. 

 

 

Types of standard cost  

 

  Ideal standard  

  Attainable (or expected) standard 

  Current standard  

  Loose Standard  

  Basic Standard  

  Historical Standards  

 

 

Practical advice for setting standards 

 

1.  Use challenging but realistic targets.   
2.  Consult with and allow staff to participate when setting targets.  
3.  Clear trust and communication between management and staff. 
4.  Standards or targets used must be realistic and achievable.   

 

 

Standard costing can be used for 

 

  Preparation of budgets  

  Controlling performance  

  Inventory valuation  

  Simplifying cost bookkeeping  

  Motivating and rewarding staff  

 

 

Criticisms of standard costing 

 

  Sometimes it can be hard to define a ‘current’ or ‘attainable standard’. 

  Less human intervention means labour standards are becoming less valuable. 
  Automation  produces  greater  uniformity  and  consistency  of  product  therefore  less 

likelihood of material and labour variances actually occurring.   

  Standard costing is an internal not external control measure. 
  Uncontrollability of any exceptions highlighted. 

  Revision to standards too infrequent to guide or improve performance over time.  

  Modern  manufacturing  techniques  such  as  TQM  and  quality  circles  means  the 

frequency and materiality of variances should not occur so often.   

 

 
 

 

background image

51 

 
 

 

 

                                

 

 

 

Variance analysis 

 

Variance analysis is a budgetary control technique, which compares planned (budgeted) or 

forecast costs and revenues to actual financial results, it measures the differences between 

standard (budgeted) and actual performance.  Variance analysis is used to improve 

operational performance through control action by management e.g. investigation of any 

variance causes and correction of them to prevent in future any further deviations from plan.   

 

 

A variance is the difference between planned, budgeted or standard cost and the actual 

cost incurred.  The same comparisons may be made for revenues. 

(CIMA) 

 

 

Reasons why variances occur 

 

  Inaccurate data used to compile standards. 

  Standard used either not realistic or out of date. 

  Efficiency of how operations were undertaken and performed by staff. 

  Random or chance events occurring. 

 

There are many variance proforma calculations that need to be learned and applied as part of 
your studies.  These proforma are essential to learn and practice in order to truly understand 
and interpret what variances mean.  Once variances have been calculated either ‘F’ or ‘A’ is 
used  as  terminology  to  indicate  favourable  or  adverse  differences  between  actual  and 
standard  performance.    Favourable  means  that  actual  results  were  better  than  standard.  
Adverse means that actual  results  were worse than standard.   Remember variances are just 
reconcilable differences  between a budget (standard) and actual results so in the case of an 
adverse  variance  this  would  mean  that  actual  cost  will  be  higher  or  profit  lower  when 
compared to the budget, and vice versa if a variance was favourable. 

 

Interpretation of variance calculations 

In your exam you could be asked to interpret the variances you have calculated or interpret 
from  variances  already  provided  to  you  in  a  question.    The  examiner  may  require  you  to 
explain  some  possible  reasons  why  a  favourable  or  adverse  variance  has  occurred.    It  is 
important to give an answer that is practical and relates to the scenario or organisation, also 
to  apply  consistent  explanations  with  your  answer  e.g.  if  an  adverse  variance  then  give 
possible  reasons  for  the  cause  of  an  adverse  not  favourable  variance.  Possible  causes  or 
reasons for variances have been included in the table below. 

 

 
 

.  
 
 
 

background image

52 

 
 

 

 

                                

 

 
Material mix and yield (productivity) variances
 
 
When different  types  of  materials  can be used as substitutes for each other, a standard mix 
can usually be determined to ensure a quality product at the lowest possible cost. If the actual 
material mix varies from the standard mix, both quality and cost may be affected.  The sum 
of the material mix and yield variances will be equal the material usage variance.   

 

The material mix variance can be calculated by using two different methods, the ‘individual 
valuation  bases’  which  is  the  easiest  to  apply  and  the  ‘average  valuation  bases’.  If  the 
examiner does not specify which method to use, the individual valuation bases is the easiest 
method  to  apply,  both  methods  give  the  same  answer  as  a  total  mix  variance,  but  the 
individual  values  for  each  material  which  make  up  the  mix  variance  will  be  different 
depending on each method used. 

 

Yield (or productivity) variances measure the amount of output (unit of product or service) 
from a given amount of input (total materials mixed). Producing more output than expected 
from  a  given  amount  of  material  input,  indicates  greater  efficiency  of  production,  the 
variance would be favourable, indicating that money has been saved by using material more 
efficiently.  Producing  less  output  than  expected  from  a  given  amount  of  material  input, 
indicates  lower  efficiency  of  production,  the  variance  would  be  adverse,  indicating  that 
money has been wasted by using material less efficiently. 

.   

 

Relationship for material variance calculations 
 

 
 

 

 

Total 

Material 

Variance 

Material 

Price 

Variance 

 

Material 

Usage 

Variance 

Material 

Mix 

Variance 

Material 

Yield 

Variance 

background image

53 

 
 

 

 

                                

 

 

Labour mix and yield (productivity) variances 

 

When different types of labour e.g. different  grades or skills, can be used as  substitutes for 
each  other,  the  labour  efficiency  variance  can  be  subdivided  into  a  mix  and  yield 
(productivity) variance when there exists two or more types of labour that can be substituted 
for one another e.g. to provide a service or manufacture a product. The sum of the labour mix 
and yield variances will be equal the labour efficiency variance.   
 
The labour mix variance can be calculated by using the same two different methods that can 
be applied to material mix and yield variances, the ‘individual valuation bases’ which is the 
easiest  to  apply  and the  ‘average valuation  bases’.  If the  examiner does  not  specify  which 
method  to  use,  the  individual  valuation  bases  is  the  easiest  method  to  apply,  both  methods 
give  the  same  answer  as  a  total  mix  variance,  but  the  individual  values  for  each  type  of 
labour which makes up the mix variance will be different depending on each method used.   
 
The  yield  variance  for  labour  is  also  an  identical  calculation  when  compared  to  material 
yield. For labour mix and yield follow the same guidance as for material mix and yield but 
use labour hours and labour rates rather than material usage and material prices. 

.   

 

Relationship for labour variance calculations 
 

 

 

 
There can be an interdependent  relationship  (both  connected to  each other), between a mix 
and yield variance, for example a higher skill of labour used in substitute for a lower skill of 
labour  would  normally  give  an  adverse  mix  variance,  (higher  skills  normally  demand  a 
higher  labour  rate),  but  at  the  same  time  perhaps  a  favourable  yield  variance,  due  to  the 
greater experience and efficiency of the higher skill of labour substituted.  

 

Total 

Labour 

Variance 

Labour 

Rate 

Variance  

Labour 

Idle Time 

Variance 

Labour 

Efficiency 

Variance 

Labour 

Mix 

Variance 

Labour 

Yield 

Variance 

background image

54 

 
 

 

 

                                

 

 

Sales mix and quantity variances 

 

The sales volume variance can be further subdivided into a mix and a quantity variance. 

 

The sales mix variance shows the change in the different product lines being sold and the 
impact it has on profit or contribution. 

 

The sales quantity variance shows the change in a different total amount of units being 
sold
 and the impact it has on profit or contribution. 

 

Planning and operational variances 

 

Planning variances are caused by the budget (standard) at the planning stage being wrong 

e.g. budgeting errors or poor planning when the budget was prepared.  The budget (standard) 

used would need revising if operational variance calculations are to be more realistic.  

Planning variances help ensure that all planning errors within the budget (standard) are 

adjusted for or removed; the standard used for operational variances would therefore be more 

realistic.  

 

Operational variances are the normal variance calculations as learned and applied earlier 

within this chapter. 

 

 

Process of calculating planning variances  

 

1.  All  planning  variances  follow  a  similar  proforma  because  they  all  adjust  the  flexed 

budget up or down due to the revision of a standard.  Just like operational variances 
planning variances can be favourable or adverse. 

2.  When  the  planning  variance  is  calculated  and  the  budget  (standard)  adjusted, 

operational variances would then be calculated using any new (revised) standards. 

 

 

The effect is to sub-divide variances into two components 

 

1.  The  planning  variance  which  is  beyond  the  operational  control  of  management  and 

staff e.g. errors due to poor planning. 

2.  The operational variance which is normally within the control of staff and now more 

realistic as a yardstick because calculations would include any revisions to standard.   

 

 

Advantages of calculating planning variances 

 

  Highlights variances between controllable and uncontrollable. 
  Helps motivate managers and staff. 
  Better management information for control purposes. 

 

Limitations of calculating planning variances 

 

 

Determining ‘bad planning’ or ‘bad management’ can sometimes be a thin line. 

  Time consuming and costly than the conventional approach. 

 

background image

55 

 
 

 

 

                                

 

 

Factors to consider before investigation or control action is taken  

 

1.  Size or ‘materiality’ of the variance. 
2.  The general trend of the variance. 
3.  Consideration of the type of standard used. 
4.  Interdependence with other variances. 
5.  The likelihood of identifying the cause of the variance if it were investigated. 
6.  The likelihood that if the cause is controllable and can be rectified. 
7.  The cost of investigation and correction compared to the benefits e.g. cost savings.  

 

 

Statistical methods for interpretation 

 

Variances can be expressed relatively rather than absolutely, the variance always expressed 
as a percentage of standard (never actual) cost.  These percentages can be plotted on a graph 
over time to provide trend analysis for variances. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
        
 
  
 
 
 
 
 
 
 
 
 

 
 
 
 

Example of a percentage variance chart 
 
 
          % 
 
 
 
 
 
 

Favourable 
 
 
 

 

                  0 
                         JAN                         FEB                             MAR                         APR 
 
 
    Adverse 
 
 
 

Note: Each line represents two different variances monitored over the four months. 

 

background image

56 

 
 

 

 

                                

 

 

Benchmarking 

 

“A continuous, systematic process for evaluating the products, services and work processes 

of an organisation that are recognised as representing best practice, for the purpose of 

organisational improvement.”  

(Michael Spendolini) 

Types of benchmarking  
 

  Internal 

  Best practice or functional 

  Competitive 

  Strategic 

 

The process  

  Selecting what you want to benchmark 

  Consider benefits against the cost of doing it 

  Assign responsibilities to a team 

  Identify potential partners/known leaders 

  Breakdown processes to complete 

  Test and measure e.g. observation, experimentation or investigation/interview 

  Gather information 

  Gap analysis 

  Implement changes/programmes/communicate 

  Monitor and control 

  Repeat regularly 

 

 
 

 

 
 
 
 
 
 
 
 
 
 
 
 

 

 

background image

57 

 
 

 

 

                                

 

 

The characteristics of services 

 

  Intangibility e.g. no material substance or physical existence  

  Legal ownership e.g. difficult to return if faulty 

  Instant perishability e.g. cannot be stored for future use 

  Heterogeneity e.g. performed different each time 

  Inseparability e.g. cannot be separated from the person who provides it  

 

 
McDonaldization 

 
 

George  Ritver  in  his  book  ‘The  McDonaldization  of  Society’  listed  the  advantages  of 
producing  standard  (homogenous  or  identical)  products,  the  pinnacle  comparison  being 
McDonalds, with its fast food strategy of uniformity of operations and delivery on a global 
basis.   

 

Advantages of McDonaldization 

 

Standardisation reduces cost and improves efficiency. 

 

  Control  
  Efficiency  
  Predictability  
  Calculability  
  Proficiency  

 

 
Diagnostic related or reference groups (DRG) ‘can applied to a Big Mac’ 

 

Standard  costing  can  be  applied  to  service  organisations  such  as  the  health  services, 
accountancy  practices,  fast  food  outlets  etc.  The  diagnostic  reference  group  or  healthcare 
resource group is a system of classifying hundreds of different medical treatments within the 
healthcare  sector.    It  applies  standardisation  by  recognising  that  similar  medical  illnesses 
require  essentially  similar  treatments  and  care.    There  are  around  800  DRG  classifications 
that exist within the healthcare industry sector.  

 

DRG applied to health care services 

 

  Standardise resources e.g. beds/wards/consultancy time/medication etc. 

  Standardise patient treatment e.g. specifications of how treatments are applied. 

  Standardised  codes  for  insurance  companies  or  payments  to  the  NHS  (or  other 

private health care providers) based on standard prices used. 

  Government can benchmark performance and provide league tables for hospitals. 

 

 

 
 
 

background image

58 

 
 

 

 

                                

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Solutions to lecture examples 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

59 

 
 

 

 

                                

 

Chapter 5 
 
 
Example 5.1   
 
Wood Plc makes wooden tables and chairs from natural timber.  To make one unit of product 
consisting  of  one  table  and  four  chairs,  it  consumes  60kg  of  timber;  after  an  expected  20% 
wastage  due  to  wood  shavings  and  scrap  in  the  cutting  process.    100kg  of  timber  currently 
costs Wood Plc £50. 
 
What is the standard cost of material to make one unit of product? 
 
Solution  
 
The standard usage of material is 60kg of timber to make one unit of product, but this is only 
80% of material  usage,  given that 20% of timber is  expected to  be scrapped in  the process.  
Therefore  the  total  material  used  to  make  one  unit  of  product  would  be  60kg  (80%  before 
wastage) x (100% ÷ 80%) = 75kg. 
 
Standard cost of material to make one unit of product: 
 
(75kg ÷ 100kg) x £50 (per 100kg) = £37.50 per unit of product. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

60 

 
 

 

 

                                

 

 

Example 5.2 - Absorption costing principles 

 

 

Operating statement for week 43 
 
Budget profit (500 x £3.20)   

 

 

 

 

 

1,600 

Sales volume variance (460 - 500) x £3.20 (W1) 

 

 

 

   128 (A) 

Flexed budget profit for 460 meals   

 

 

 

 

1,472 

Sales price variance 460 x (£10.00 - £11.95) (W2)    

 

 

   897 (A) 

 

 

 

 

 

 

 

 

 

 

   575 

Cost variances 

 

 

 

                           F 

  A 

 
Chicken price variance 180kg x (£2.25 - £2.50) (W3)             45 

 

Chicken usage variance (143kg - 165kg) x £2.50(W4) 

               55 

 

Vegetable price variance 250kg x (£0.50 - £0.56) (W5)                      15 
Vegetable usage variance (238kg - 220kg) x £0.50 (W6)          

 

Labour rate variance 120hrs x (£9-£10) (W7)   

                        120 

Labour efficiency variance (119hrs-114hrs) x £9 (W8)           45 
Idle time variance (6hrs x £9) (W9)    

 

 

              54 

 

Variable overhead expenditure variance 
114hrs x (£2 - £1.32) (W10)    

 

 

               78 

Variable overhead efficiency variance 
(119hrs – 114hrs) x £2 (W11)   

 

 

               10 

 

Fixed overhead expenditure variance 
(£2,500 - £2,750) (W12)   

 

 

 

                         250 

Fixed overhead volume variance 
(476 units - 500 units) x £5 (W13)     

 

 

             120 

 

 

 

 

 

 

 

             187 

 614    =  427 (A) 

Actual profit   

 

 

 

 

 

 

               148 

 

Calculation of actual profit 
 
Sales   

 

 

 

                     4,600 

Chicken 

 

 

             405 

Closing stock (15kg x £2.50)               (38) 
Vegetables  

 

 

             140 

Closing stock (30kg x 50p)                 (15) 
Labour  

 

                      1,200 

V/OH Exp 

 

 

             150 

F/OH Exp 

 

                      2,750 

Closing stock of meals 
(476 produced – 460 sold) =  
16 meals valued at £8.75 Std Cost    (140) 

 

                                                                                (4,452)        
Profit for the period   

 

 

            148 

 
Note: The above assumes that any material and finished good inventory can be stored. 

 

background image

61 

 
 

 

 

                                

 

 
Example 5.2
 - Absorption costing principles - continued 
 
WORKINGS 
 
W1 Sales volume variance 
                                                                                              meals 
Did sell 

 

 

 

 

 

 

 460 

Should sell (as per original budget)   

 

 

 500 

 

 

 

 

 

 

 

 

   40 

x Standard profit per meal sold                                                   x £3.20 
 

 

 

 

 

 

 

 

 128 (A) 

W2 Sales price variance 

   £ 

460 did sell for 

 

 

 

 

 

4,600   

 

 

460 meals should sell for (x £11.95)   

 

 

5,497 
   897 (A) 

W3 Chicken price variance 

  £ 

180kg did cost  

 

 

 

 

 

405 

180kg should cost (180kg x £2.50)   

 

 

450 

 

 

 

 

 

 

 

 

  45 (F) 

W4 Chicken usage variance  
 

 

 

 

 

 

 

 

 kg 

476 meals did use  

 

 

 

 

 

165 

476 meals should use (x 0.3kg)  

 

 

 

143 

 

 

 

 

 

 

 

 

  22 

x Standard Price                                                                         x  £2.50 
 

 

 

 

 

 

 

 

 55 (A) 

W5 Vegetable price variance 

  £ 

250kg did cost  

 

 

 

 

 

140 

250kg should cost (250kg x £0.50)   

 

 

125 

 

 

 

 

 

 

 

 

  15 (A) 

W6 Vegetable usage variance  
 

 

 

 

 

 

 

 

 kg 

476 meals did use  

 

 

 

 

 

220 

476 meals should use (x 0.5kg)  

 

 

 

238 

 

 

 

 

 

 

 

 

  18 

x Standard Price                                                                         x  £0.50 
 

 

 

 

 

 

 

 

   9 (F) 

W7 Labour rate variance 
 
120 hours paid did cost 

 

 

 

 

1,200 

120 hours paid should cost (120 hours x £9)   

 

1,080 

 

 

 

 

 

 

 

 

   120 (A) 

 
 

background image

62 

 
 

 

 

                                

 

 
Example 5.2
 - Absorption costing principles - continued 
 
W8 Labour efficiency variance 
                                                                                              hours 
476 meals did take (hours worked)   

 

 

114 

476 meals should take (x 0.25 hours)  

 

 

119 

 

 

 

 

 

 

 

 

    5 

x Standard Rate                                                                          x  £9.00 
 

 

 

 

 

 

 

 

  45 (F) 

W9 Labour idle time variance 
                                                                                              hours 
Hours paid 

 

 

 

 

 

 

120 

Hours worked  

 

 

 

 

 

114 

 

 

 

 

 

 

 

 

    6 

x Standard Rate                                                                          x  £9.00 
 

 

 

 

 

 

 

 

  54 (A) 

 
W10Variable overhead expenditure variance 

    £ 

114 hours worked did cost 

 

 

 

 

  150 

114 hours worked should cost (114 hours x £2) 

 

  228 

 

 

 

 

 

 

 

 

    78 (F) 

 
W11Variable overhead efficiency variance 
 
                                                                                              hours 
476 meals did take (hours worked)   

 

 

114 

476 meals should take (x 0.25 hours)  

 

 

119 

 

 

 

 

 

 

 

 

    5 

x Standard Rate                                                                          x  £2.00 
 

 

 

 

 

 

 

 

  10  (F) 

 
W12 Fixed overhead expenditure variance 

               £ 

Actual fixed overhead expenditure   

 

 

2,750 

Original budgeted fixed overhead expenditure 

 

2,500 

 

 

 

 

 

 

 

 

   250 (A) 

W13 Fixed overhead volume variance 

          meals 

Did produce    

 

 

 

 

 

476 

Should have produced  

 

 

 

 

500 
  24 

x Fixed overhead absorption rate per meal (O.A.R)                   x £5.00 O.A.R 

120 (A) 

 
 

background image

63 

 
 

 

 

                                

 

 
Example 5.2
 - Absorption costing principles - continued 
 
Traditional  absorption  costing  takes  the  total  budgeted  fixed  overhead  for  a  period  and 
divides  by  a  budgeted  (or  normal)  activity  level  e.g.  units,  in  order  to  find  the  overhead 
absorption  rate.  This  is  a  simple  method  of  charging  fixed  overhead  and  allows  fixed 
overhead to be allocated to products, jobs or work-in-progress 
 
Overhead absorption rate (OAR) =  

Budgeted production overhead   

             Normal/budget level of activity 

 
In this case the overhead absorption rate has already been calculated e.g. £2,500 budgeted 
fixed overhead ÷ 500 meals expected to be produced = £5.00 per meal. 
 

At the end of the period, the overhead ‘absorbed’ or charged to production is compared to the 
actual production overhead incurred for the period.  Any shortfall in overhead charged would 
be an ‘under absorption’ of production overhead (DR profit and loss account CR Production 
overhead control account).  Any ‘over charge’ to the profit and loss account during a period 
would  be  an  ‘over  absorption’  of  production  overhead  (CR  profit  and  loss  account  DR 
Production overhead control account). 
 
The sum of the fixed overhead expenditure and volume variance would be equal to the under 
or  over  absorption,  when  sub-divided,  explaining  the  two  different  causes  as  to  how  this 
occurred  during  a  period  e.g.  under  or  over  spent  and/or  under  or  over  produced  when 
compared to the original budget.  In this case the under absorption is £370 (A) which consists 
of  the  expenditure  and  volume  variance  added  together,  £250  (A)  expenditure  variance  + 
£120 (A) volume variance = £370 (A) under absorption. 
 
The  difference  between  absorption  and  marginal  costing  organisations  is  that  the  marginal 
costing  organisation  makes  no  attempt  to  absorb  or  charge  production  overhead  into  a  cost 
unit  or  the  profit  and  loss  account.    It  treats  production  overhead  as  a  period  cost  only  and 
does not absorb overhead, but rather charges it entirely to the profit and loss account for each 
period.  With marginal costing organisations only the fixed overhead expenditure  never the 
fixed overhead volume variance would be applicable within a question. 
 
 

 

Actual production (units of meals)  
x O.A.R = charge or absorption of 
 fixed overhead to income statement    
(£5 x 476 meals) = absorbed                  2,380 

 

Under absorption for the period 
(£2,750 - £2,380) =                                  370 
 

 

 

 

 

  2,750 

Production fixed overhead control account 

     Actual production overhead           2,750 
 
 
 
 
                                                                    

f 

 

 

 

 

           2,750 

 

background image

64 

 
 

 

 

                                

 

 

 
Example 5.2
 - Marginal costing principles 

 

Operating statement for week 43                                                              £ 

 

Budget contribution  (500 x £8.20)   

 

 

 

 

 4,100 

Sales volume variance (460-500) x £8.20 W14 

 

 

 

    328 (A) 

Flexed budget contribution for 460 meals 

 

 

 

 

 3,772 

Sales price variance 460 x (£10.00-£11.95)      

 

 

 

    897 (A) 

 

 

 

 

 

 

 

 

                        2,875 

 

Cost variances 

 

 

 

 

 

    F 

   A 

                                                                                                     £        £ 
Chicken price variance 180kg x (£2.25-£2.50) 

 

   45 

 

Chicken usage variance (165kg -143kg) x £2.50 

 

 

  55 

 

Vegetable price variance 250kg x (£0.50-£0.56) 

 

 

  15 

Vegetable usage variance (220kg-238kg) x £0.50 

    

     9 

 

Labour efficiency variance (114hrs-119hrs) x £9 

               45 

Labour rate variance 120hrs x (£10-£9) 

 

 

           120 

Idle time variance (6hrs x £9)  

 

 

 

             54 

 

V/OH efficiency variance (114-119hrs) x £2  

 

   10 

V/OH overhead expenditure var 114hrs x (£1.32-£2)               78           

7

                

 

 

 

 

 

 

 

 

 187 

244  =      57 (A) 

Actual contribution                                                                                        2,818 
Less budgeted fixed overhead                                                                       2,500 
Fixed overhead expenditure variance (£2500-£2750) 

 

 

   250 (A) 

Actual profit      

 

 

 

 

 

 

 

     68 

 
Calculation of actual profit 
                                                                                                  £              £ 
Sales   

 

 

 

                

 

 

  4,600 

Chicken 

 

 

           

 

 

  405 

Closing stock (15kg x £2.50)         

 

 

             (38) 

Vegetables  

 

 

       

 

 

 

  140 

Closing stock (30kg x 50p)            

 

 

 

  (15) 

Labour  

 

                    

 

 

           1,200 

V/OH Exp 

 

 

    

 

 

 

  150 

Closing stock of meals (476 produced – 460 sold) =  
16 meals valued at £3.75 Variable Std Cost    

             (60)   

Variable cost of sales                                                                   

 (1,782)        

Contribution for the period 

 

 

 

 

 

   2,818 

Less Fixed overhead    

 

 

 

 

 

  (2,750) 

Profit for the period   

 

 

 

 

                    68 

 
Note: The above assumes that any material and finished good inventory can be stored.  
 

background image

65 

 
 

 

 

                                

 

 
 
Example 5.2
 - Marginal costing principles - continued 
 
WORKINGS 
 
The variances calculated would be identical under both costing methods with the exception of 
the sales volume and fixed overhead volume variance. 
 
W14 Sales volume variance 
                                                                                             meals 
Did sell 

 

 

 

 

 

 

 460 

Should sell (as per original budget)   

 

 

 500 

 

 

 

 

 

 

 

 

   40 

x Standard contribution per meal sold                                       x £8.20 
 

 

 

 

 

 

 

 

 328 (A) 

 
The fundamental differences between marginal and absorption costing 
 

  Marginal costing uses a different format for its profit calculation, it deducts variable 

cost first from sales in order to arrive at contribution, then deducts fixed overhead to 
arrive a profit.  

  The  sales  volume  variance  when  marginal  costing  would  be  calculated  slightly 

different to when using absorption costing. Because the marginal costing format uses 
contribution,  then  the  standard  contribution  must  be  used  for  the  calculation  of  the 
sales  volume  effect,  rather  than  standard  profit,  which  would  be  used  if  absorption 
costing. 

  The  fixed  overhead  volume  variance  would  not  exist  when  marginal  costing,  this  is 

because  when  marginal  costing  there  is  no  calculation  of  fixed  overhead  absorption 
rates and  absorption  of fixed overhead.  Any fixed overhead is  treated as period not 
product cost and would be charged as incurred rather than absorbed. 

 
Note: 
A profit difference exists under both statements prepared, the only reason why profits 
would be different is because of the way each method values finished goods inventory.  An 
absorption costing approach would value finished goods inventory at full standard production 
cost (£8.75 a meal), the marginal costing approach would value finished  goods inventory at 
variable standard production cost only (£3.75 a meal). 
 
Reconciliation of profit  

 

Profit under absorption costing 

 

 

 

 

 

 

148 

Increase in closing inventory carries forward £5 of fixed overhead each meal  
To the next accounting period under absorption costing  

 

 

 

 

(16 meals x £5 Fixed overhead per unit)  

 

 

 

 

 

(80) 

Profit under marginal costing  

 

 

 

 

 

 

 68 

 
 
 

background image

66 

 
 

 

 

                                

 

 
Example 5.3 – Using absorption costing principles 
 
1. Calculate the actual sale of meals 
 
                                                      meals 
Did sell                       

 

460 (balance figure

Should sell        

 

 

500 (£1,600 original budget profit ÷ £3.20 Std Profit) 

 

 

 

 

 

  40 

Standard profit per meal  

 

    x £3.20 Std Profit per unit 

 

 

 

 

            128 (A) Given 

 
2. Calculate the actual production of meals 
 

              meals 

Did produce    

 

 

 

 

 

      476 (balance figure

Should have produced  (£2,500 budgeted F/OH ÷ £5 O.A.R)     500 

       24 

x Fixed overhead absorption rate per meal (O.A.R)                        x  £5.00 O.A.R 

     120 (A) Given 

 
Alternatively the additional information included that closing inventory of meals rose by 16 
meals for the period.  Therefore if you derive actual sales which was 460 meals + 16 meals 
rise in closing inventory would equal 476 actual meals produced. 
 
3. Calculate actual hours worked for the chefs 
 
476 meals did take 

 

 

 

114 (balance figure

476 meals should take (476 x 0.25 hrs) 

119 

 

 

 

 

 

 

    5 

Standard rate per hour  

 

 

    x £9.00 Std Rate per hour 

 

 

 

 

 

 

 45 (F) Given 

 
Hours paid would have been 114 hours worked (as above) plus 6 hours idle time = 120 hours 
 
4. Calculate the actual quantity of chicken purchased 
 
476 meals did use 

 

 

 

165 kg (balance figure

476 meals should have used  (x 0.3kg) 

143 kg 

 

 

 

 

 

 

  22 kg 

Standard price per kg   

 

 

    x  £2.50 Std price per Kg 

 

 

 

 

 

              55 (A) Given 

 
 
 
 
 

background image

67 

 
 

 

 

                                

 

 
Example 5.3 – Using absorption costing principles – continued 
 
5. Calculate the actual price paid for chicken  
 
165kg used (as above) + 15kg rise in closing inventory levels = 180kg purchased. 
 
180kg did cost  

 

 

 

405 (balance figure

180kg should cost (x £2.50 kg) 

 

450 

 

 

 

 

 

 

  45 (F) 

 
6. Calculate the actual variable overhead expenditure 
 
114 hrs worked did cost 

 

 

150 (balance figure

114 hrs should have cost (x £2 per hour) 

228 

 

 

 

 

 

 

  78(F) Given 

 
7. Calculate the actual fixed overhead expenditure 
 
Actual fixed overhead  

 

 

2,750 (balance figure

Budget fixed overhead 

 

 

2,500 

 

 

 

 

 

 

   250(A) Given 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

68 

 
 

 

 

                                

 

 
Example 5.4 

 

Material usage variance 
 
60kg pizza 

        Did use        Should use     Standard price 

Variance 

 
Tomato 

 

28kg   

30kg x  

£1.40 = 

     £2.80 (F) 

Cheese  

 

40kg   

36kg x  

£7.50 =              £30.00 (A) 

 

 

 

68kg   

66kg   

 

              £27.20 (A) 

 

Mix variances can be calculated using two methods 
 
First method (individual valuation basis) 
 
60kg pizza 

        Did use       Should use    Standard price 

Variance 

 

 

 

 

           (W1) 

Tomato 

 

28kg   

31kg  x 

£1.40 = 

      £4.20 (F) 

Cheese  

 

40kg   

37kg  x 

£7.50 =                £22.50 (A) 

68kg   

68kg   

 

                £18.30 (A)   

           

 

 
(W1) 
The total of 68kg of ingredients actually mixed 
 

  (68kg x (0.5kg/1.1kg)) = 31kg of standard mix for tomatoes.  

  (68kg x (0.6kg/1.1kg)) = 37kg of standard mix for cheese.   

  The total of 68kg in both columns should be equal because you are taking the actual 

total  of  all  material  actually  used  and  recalculating  how  much  material  you  should 
have used if the standard mix had been applied. 

 

Interpretation of individual valuation basis 

 

  For  tomato  a  lower  quantity  of  material  was  used  compared  to  the  standard  mix 

therefore a favourable variance. 

  For  cheese  a  greater  quantity  of  material  was  used  compared  to  the  standard  mix 

therefore an adverse variance. 

  Overall  the  budget  is  worse  when  compared  with  actual  cost;  this  is  because  more 

expensive cheese has been substituted for less expensive tomato. 

 
 
 
 
 
 
 
 
 
 
 
 

background image

69 

 
 

 

 

                                

 

 
Example 5.4 - continued 
 
Second method (average valuation basis) 
 
60kg pizza 

        Did use        Should use             Average price (W2)        Variance 

                                                                                less standard price 
Tomato 

 

28kg   

31kg      =  3kg  x  (£4.73-£1.40)  =         £10.00 (A) 

Cheese  

 

40kg   

37kg      =  3kg   x (£4.73-£7.50)  =           £8.30 (A) 

68kg   

68kg   

 

                              £18.30(A)   

 

(W2)  £5.20  is  the  standard  (budgeted)  cost  of  one  pizza  which  uses  1.1kg  of  ingredients, 
therefore £5.20 ÷ 1.1kg = £4.73 average price of one kg of input (cheese and tomato). Or an 
alternative working (0.5kg/1.1kg) x £1.40 + (0.6kg/1.1kg) x £7.50 = £4.73 average price for 
one kg of input.  The fractions used are the same as what was used to rearrange the actual mix 
in order to find the standard mix. 

 

Interpretation of average valuation basis 

  For tomato a lower quantity of material was  used compared to the standard mix but 

the material is less expensive relative to the average cost for all material (its standard 
price  of  £1.40  is  less  than  the  average  price  of  all  ingredients  £4.73).    This  is  an 
adverse  variance,  no  cost  saving  is  obtained  by  using  less  of  a  less  expensive 
ingredient when compared to the weighted average standard price of £4.73.  

  For cheese a greater quantity of material was used compared to the standard mix and 

the material is more expensive relative to the average cost of all material (its standard 
price  of  £7.50  is  more  than  the  average  price  of  all  ingredients  £4.73).  This  is  an 
adverse  variance,  no  cost  saving  is  obtained  by  using  more  of  a  more  expensive 
ingredient when compared to the weighted average standard price of £4.73.  

 
 
 
 

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

70 

 
 

 

 

                                

 

 
Example 5.4 - continued 
 
Yield (productivity) variance 

               Units of  
                 pizza 
               (output) 

68kg of cheese and tomato did yield   

                                                      60.0 

68kg of cheese and tomato input should yield (68kg/1.1kg input per pizza)       61.8 
Under produced (yielded)  

 

 

  

 

 

 

        1.8 

 
x Standard cost for one unit of pizza (output cost of material)                          x £5.20 (given)                                       
 

 

 

 

 

 

 

 

 

 

      £9.37 (A) 

 
The  amount  of  cheese  and  tomatoes  actually  used  should  have  yielded  1.8  pizza  more  than 
what  was  expected,  which  suggests  more  wastage  of  ingredients  than  what  was  necessary.  
Perhaps staff are putting too much topping on the pizza? 
 
Operating statement (to reconcile budget to actual cost) 
 

Flexed budgeted cost  (60 pizzas x £5.20) 

 

312.00   

 

 

 

 

 

 

 

 

Material price - tomatoes 

 

 

 

28kg did cost 

45.00   

 

28kg should cost (28kg x £1.40 per kg) 

39.20   

 

 

 

6.00  (A) 

Material price - cheese 

 

 

 

40kg did cost 

270.00   

 

40kg should cost (40kg x £7.50 per kg) 

300.00   

 

 

 

30.00  (F) 

 

 

 

 

Material mix  

 

18.00  (A) 

 

 

 

 

Material yield 

 

9.00  (A) 

 

 

 

 

Actual cost (£45 + £270) 

 

315.00   

 
Note: 
The material usage variance can be subdivided into a material mix and yield variance.  
The  mix  and  yield  variances  calculated  above  were  £18.30  (A)  +  £9.37  (A)  =  £27.67  (A)        
(give or take pennies this is the material usage variance). 
 
 
 
 
 
 

background image

71 

 
 

 

 

                                

 

 
Example 5.5 
 
Individual valuation basis 

 

Based on actual production of 9,100 litres  

 

                                 Did use         Should use      Standard price  Variance 
 

 

           (litres)            (litres)   

 

 

        $ 

 

  

4,300   

4,000  W1         x $9 = 

   2,700  (A) 

 

 

3,600   

3,500  W2 

   x $5 = 

      500  (A) 

 

 

2,100              2,500   W3         x $2 =                 800 (F) 

          10,000            10,000   

 

               2,400 (A) 

 

           

 

W1 10,000 litres x 4 ÷ (4 + 3.5 + 2.5) =    

4,000 litres 

W2 10,000 litres x 3.5 ÷ (4 + 3.5 + 2.5) =     3,500 litres 
W3 10,000 litres x 2.5 ÷ (4 + 3.5 + 2.5) =     2,500 litres 

 

 

 

Tip: Yield or productivity variance (proforma) 

 

Actual material used did produce  

 

 

 

  

 

 X 

Actual material used should produce   

 

 

 

 

 X 

Over/(under) produced 

 

 

 

 

 

 

 X 

x standard cost of one unit of output             

 

 

          x £x 

 

 

 

 

 

 

 

 

 

            £X (F)/(A) 

 
Over produced = (F) Under produced = (A) 

 

 

Yield variance 

Litres of output 

10,000 litres input did yield    

 

 

 

 

 

9,100 

10,000 litres input should yield (10,000 x  0.9) 

 

 

 

9,000 

Over produced  

 

 

 

 

 

 

               100 

 
x standard cost of one litre (W1) 

 

 

 

 

                  x $6.50 

 

 

 

 

 

 

 

 

 

            $650 (F) 

 
W1 
The standard cost of 9 litres of output is $58.50 therefore the standard cost of one litre of 
output is $58.50 ÷ 9 litres = $6.50. 
 
 
 
 
 
 
 
 
 

background image

72 

 
 

 

 

                                

 

 
Example 5.6 – part (a) 
 

Operating statement 

£ 

£ 

£ 

Budgeted profit (W1)  

 

 

586,000 

Sales volume variance (W2) 

 

 

84,240 (F) 

Flexed budget 

 

 

670,240 

Sales price variance (W3) 

 

 

129,710 (F) 

 

 

 

799,950 

Cost variances 

Fav 

Adv 

 

Material price variance (W4) 

 

 

 

Material A  

 

43,000 

 

Material B  

18,500 

 

 

Material C  

 

5,875 

 

Material mix variance (W5) 

18,000 

 

 

Material yield variance (W6) 

222,300 

 

 

Fixed overhead variance  

 

 

 

Expenditure variance (£385,000 - £350,000) 

 

35,000 

 

Total 

258,800 

83,875 

174,925 (F) 

Actual profit 

 

 

974,875 

 
Working 1 

Budgeted profit 

 
Standard marginal cost  

 

 

= £234 per unit 

Budgeted mark – up at 80%   

 

= £187.20 per unit 

Budgeted units  

 

 

 

= 5,000 units 

Budgeted total mark –up (5,000 x £187.20)  = £936,000 
Budgeted fixed costs   

 

 

= £350,000 

Budgeted profit (£936,000 – 350,000) 

= £586,000 

 
Working 2 

Sales volume variance 

 

 

 

Did sell (actual quantity sold)  

5,450 

Should sell (budget quantity sold)   

5,000 

Variance in units 

         450 (F) 

x standard contribution per unit 

              £187.20 

Sales volume contribution variance 

£84,240 (F) 

 
 
 
 
 
 
 
 
 
 

background image

73 

 
 

 

 

                                

 

 
Example 5.6 – part (a) continued  
 
Working 3 

Sales price variance 

 

 

  £ 

Did sell (actual quantity sold x actual price) 5,450 x £445 

2,425,250 

Should sell (actual quantity sold x standard price) 5,450 x £421.20 

2,295,540 

Sales price variance   

        129,710(F) 

 
Working 4 

Material price variance 

 

 

 

      A 

      B 

    C 

Did spend (actual quantity purchased x actual price) 

688,000 

277,500 

99,875 

Should spend  

645,000 

296,000 

94,000 

Material price variance 

43,000(A) 

18,500(F) 

5,875(A) 

 
Should spend (actual quantity purchased x standard price) 
 

 

                                                      £ 

Material A – 43,000 x £15 

645,000 

Material B – 37,000 x £8 

296,000 

Material C – 23,500 x £4 

94,000 

 
Alternative working can be based on price per unit 
For example  
Material A  

Budget price per unit    

 

 

    £15 per kilo 

 

 

Actual price per unit (£688,000 / 43,000kg)      £16 per kilo 

 

 

Price variance per kilo 

 

 

      £ 1 (A) per kilo 

 

 

X actual quantity purchased    

 

43,000 kgs 

 

 

 

Material price variance in £   

 

£43,000 (A) 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

74 

 
 

 

 

                                

 

 
Example 5.6 – part (a) continued  
 
Working 5 

Material mix variance 

 
Standard mix 
 

 

Material A 

10 / 23 

Material B 

8 / 23 

Material C 

5 / 23 

 

 

 
Standard mix of actual usage = fraction x 103,500 kg 
 

 

Did use 

Should use 

Variance 

in kilo 

Standard 

price 

Variance £ 

Material A 

43,000 

45,000 

2,000 (F) 

£15 

£30,000(F) 

Material B 

37,000 

36,000 

1,000 (A) 

£8 

  £8,000(A) 

Material C 

23,500 

22,500 

1,000(A) 

£4 

  £4,000 (A) 

 

103,500 

103,500 

 

 

£18,000 (F) 

 
Working 6 

Material yield variance 

 

 

Tip: Yield or productivity variance (proforma) 

 

Actual material used did produce  

 

 

 

  

 

 X 

Actual material used should produce   

 

 

 

 

 X 

Over/(under) produced 

 

 

 

 

 

 

 X 

x standard cost of one unit of output             

 

 

          x £x 

 

 

 

 

 

 

 

 

 

            £X (A)/(F) 

 

 

 

Units 

Actual material used did produce  

5,450  

Actual material used should produce (103,500kg / 23kg) 

4,500  

Over produced 

   950  

x standard cost of one unit of output           

     x £234 

Yield variance 

£222,300 (F) 

 
 
 
 
 
 
 
 
 
 

background image

75 

 
 

 

 

                                

 

 
Example 5.6 part (b) 
 

REPORT 

 
To: 

 

Production Manager 

From:   

Accountant 

Date:   

November 2006  

Subject: 

Variances 

 
This report will firstly interpret the material price, mix and yield variances that have occurred 
during  the  period.    This  report  will  also  discuss  the  merits  and  drawbacks  of  calculating 
material mix and yield variances. 
 
1.1 

Interpretation of material price, mix and yield variance 

 
Material price variance 
 
This variance looks at the difference between the budgeted cost of the material purchased and 
the actual cost.  For materials A and C the price variance is adverse.  Material A is adverse by 
£43,000  and  material  C is  adverse  by  £5,875.    This  could  be  due  to  increase  in  the  general 
prices of material A and C or it could be due to a change of supplier.  The price variance for 
material B is favourable by £18,500.  The total material price variance is adverse by £30,375.  
This  is  bad  news  for  X  Ltd  suggesting  problems  with  the  purchasing  department  and 
therefore requires thorough investigation. 
 
Material mix and yield variance 
 
The  material  mix  variance  is  £18,000  favourable  because  overall  less  expensive  materials 
(material B and C) have been used in place of a more expensive material (material A).  The 
material input or usage to produce product P has also resulted in a favourable yield variance 
of £222,300 e.g. greater productivity from the material consumed.  The total of the mix and 
yield  variance  gives  the  material  usage  variance  which  is  £191,925  favourable.    This  is  a 
huge variance and could indicate that the original budget is incorrect e.g. it could due to poor 
planning.  I would recommend prior periods should be investigated to see the overall trend of 
these material variances. 
 
 
 
 
 
 
 
 
 
 
 
 

background image

76 

 
 

 

 

                                

 

 
Example 5.6 – part (b) continued  
 
1.2 

Merits and drawbacks of calculating material mix and yield variances 

 
As  mentioned  before  the  material  usage  variance  can  be  subdivided  into  a  mix  and  yield 
variance  where  there  exist  two  or  more  ingredients  that  can  be  substituted  for  one  another.  
The  sum  of  the  material  mix  and  yield  variances  will  total  the  sum  of  the  material  usage 
variance.    X  Ltd  manufactures  a  product  which  uses  three  materials  which  are  inter-
changeable.  For this period X Ltd has been able to use cheaper materials (B & C) relative to 
a  more  expensive  material  (A)  to  improve  their  situation  e.g.  lowering  cost  and  therefore 
increasing profit.  The merit of using the mix calculation is that we can see exactly how much 
money  has  been  saved  for  each  material  as  well  as  understanding  the  overall  composite  of 
how materials were mixed together, something a material usage variance in isolation would 
not have told us. 
 
However the quality of the product does require careful inspection and it would be interesting 
to  see  if  there  are  any  complaints  from  customers  about  the  quality  of  the  product.    For 
example mixing more water and less concentrated flavour to make a drink can certainly give 
a  favourable  mix  variance  (water  is  cheaper)  but  it  can  have  an  effect  on  the  quality  of  the 
end product, in this case the taste of it.  The chemical produced in the case of X Ltd could be 
poorer quality or ineffective because of a deviation in mix.  The same problem can be applied 
to the yield, a favourable yield variance indicates you are short changing the customer e.g. X 
plc  may  not  be  delivering  exactly  23  kg  of  chemical  for  every  unit  of  product  P  (ignoring 
evaporation in the process) customers are getting less product for their money. 
 
These  problems  in  turn  could  have  a  damaging  impact  on  the  X  Ltd  brand  image  and 
reputation, in turn leading to loss of customers and lower sales.  Therefore the mix and yield 
variances  must be interpreted and used very  carefully, ideally if the standard information  is 
correct you should have no variances at all.  A short term favourable variance could result in 
a poorer quality product and long term decline in sales. 
 
I hope you find this information useful. 
 
Signed: Accountant 
 
 
  
 
 
 
 
 
 
 
 
 
 

background image

77 

 
 

 

 

                                

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Example 5.7 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Labour Mix calculation - individual valuation bases 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Actual Mix  

 

Standard Mix 

  Standard hours 

 

Standard rate 

 

 

Partner 

 

12 

 

3 / 20 x 90 

13.5 

1.5 

£100 

150.00  (F) 

 

Semi-senior 

40 

 

5 / 20 x 90 

22.5 

-17.5 

£70 

-1,225.00  (A) 

 

Junior 

 

38 

 

12 / 20 x 90  = 

54.0 

16 

£30 

480.00  (F) 

 

 

 

90 

 

 

 

90.0 

0.0 

 

-595.00  (A) 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Labour Mix calculation - average valuation bases 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Actual Mix 

 

Standard Mix 

   

Standard rate - Average rate                     

 

 

Partner 

 

12 

 

13.5 

 

1.5 

£100 

£50.50 

-49.50 

74.25  (F) 

Semi-senior 

40 

 

22.5 

 

-17.5 

£70 

£50.50 

-19.50 

-341.25  (A) 

Junior 

 

38 

 

54.0 

 

16 

£30 

£50.50 

20.50 

-328.00  (A) 

 

 

90 

 

90.0 

 

0.0 

 

(W1) 

 

-595.00  (A) 

 

 

 

 

 

 

 

 

 

 

 

 

W1 Weighted average standard rate 

 

 

 

 

 

 

 

 

(3/20 x £100) + (5/20 x £70) + (12/20 x £30) =  £50.50 

 

 

 

 

 

 

 

or £1,010 Std cost  ÷ 20 Std hours = £50.50 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Labour yield (productivity) variance 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

90 hours did yield 

 

 

 

 

5.0 audits 

 

 

 

 

90 audits should yield (90 hours/20 hours an audit) 

 

4.5 audits 

 

 

 

 

 

 

 

 

 

 

0.5 audits 

 

 

 

 

 

 

 

 

 

 

x standard cost of an audit (£1,010) 

 

 

 

 

 

 

 

 

£505(F) 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Operating statement 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5 audits should cost (based on standard mix of labour) 

5 x £1,010 =  

 

£5,050  

 

 

 

 

 

 

 

 

 

 

 

 

 

Labour mix variance   

 

 

 

 

 

 

£595 (A) 

 

 

 

 

 

 

 

 

 

 

 

 

 

Labour yield variance 

 

 

 

 

 

 

£505 (F) 

 

5 audits did cost  (12 hours x £100) + (40 hours x £70) + (38 hours x £30) =                                                           £5 ,140  

 

 

 

 

 

 

Note: the actual rates paid to all staff were the same as the standard rate  

 

  

 

 
 
 
 

background image

78 

 
 

 

 

                                

 

Example 5.9 – (CIMA past exam question) 
 
Sales quantity contribution variance 
 

 

Economy 

Premium 

Deluxe 

Selling price 

$2.80 

$3.20 

$4.49 

Direct labour 

($0.50) 

($0.50) 

($0.50) 

Direct material 

($1.00) 

($1.60) 

($2.20) 

Variable overheads 

($0.65) 

($0.65) 

($0.65) 

Contribution 

$0.65 

$0.45 

$1.14 

 
 
 

Actual 

sales at 

budget mix 

(W1) 

Budget 

sales 

quantity 

Difference  Contribution 

Variance 

Economy 

193,500 

180,000 

13,500 (F) 

$0.65 

$8,775 (F) 

Premium 

387,000 

360,000 

27,000 (F) 

$0.45 

$12,150 (F) 

Deluxe 

279,500 

260,000 

19,500 (F) 

$1.14 

$22,230 (F) 

 

860,000 

800,000 

60,000 (F) 

 

$43,155 (F) 

 
Sales mix contribution variance 
 
 

Actual 

sales 

quantity 

Actual sales 

at budget 
mix (W1) 

Difference  Contribution 

Variance 

Economy 

186,000 

193,500 

7,500 (A) 

$0.65 

$4,875 (A) 

Premium 

396,000 

387,000 

9,000 (F) 

$0.45 

$4,050 (F) 

Deluxe 

278,000 

279,500 

1,500 (A) 

$1.14 

$1,710 (A) 

 

860,000 

860,000 

 

 

$2,535 (A) 

 
Workings 
 
W1 – Actual sales at budget mix 
 
Economy = 180 / 800 x 860,000 = 193,500 
Premium = 360 / 800 x 860,000 = 387,000 
Deluxe = 260 / 800 x 860,000 = 279,500 
 
 
 
 
 
 
 
 
 
 

background image

79 

 
 

 

 

                                

 

 
Example 5.10 Part (a) 

 

 

Tip:  It  is  important  that  all  workings  are  clearly  shown  to  support  your  financial 
statement.  Make sure also your layout is clear and easy to follow.  Other formats of 
presenting the information below would have been acceptable. 

 

For actual costs you can derive these using the flexed budgeted cost (based on 29,600 
services)  and  the  total  of  the  favourable  or  adverse  variances  given.    Note  that  the 
30,000  original  budget  for  services  would  be  irrelevant.    It  is  always  actual  not 
budgeted production volume that drives a cost variance.  

 

 

Actual costs incurred for the six months ended 

 

 

 

£ 

 

Flexed budgeted material cost (W1) 

1,184,000   

Material price variance 

1,100  (A) 

Material usage variance 

22,000  (A) 

Actual material cost 

1,207,100   

 

 

 

Flexed budgeted labour cost (W1) 

976,800   

Labour rate variance 

130,671  (F) 

Actual labour cost 

846,129   

 

 

 

Flexed budgeted variable overhead (W1) 

444,000   

Variable overhead expenditure variance 

11,000  (A) 

Actual variable overhead 

455,000   

 

 

 

Flexed budgeted fixed overhead (W1) 

710,400   

Fixed overhead expenditure variance 

18,000  (A) 

Fixed overhead volume variance 

9,600  (A) 

Actual fixed overhead 

738,000   

 

 

 

Summary financial statement for the six months ended 30 September 2003 
 

 

 

Actual material cost 

1,207,100   

Actual labour cost 

846,129   

Actual variable overhead 

455,000   

Actual fixed overhead 

738,000   

 

3,246,229   

 

 

 

 

 
 

background image

80 

 
 

 

 

                                

 

 
Example 5.10 Part (a) - continued 
 

W1 Flexed budgeted cost based on 29,600 services 

 

 

 

 

 

 

£ 

 

Material (£40 x 29,600) 

1,184,000   

Labour  (£33 x 29,600) 

976,800   

Variable overhead  (£15 x 29,600) 

444,000   

Fixed overhead  (£24 x 29,600) 

710,400   

 

3,315,200   

 
Example 5.10 Part (b) 
 

 

Tip:  A  good  report  format  will  make  your  report  well  presented.    A  good  approach 
here would be to consider each cost and associated variances one by one, thinking of 
good  reasons  that  can  support  an  adverse  or  favourable  variance  given,  as  well 
discussion of possible interrelationships between the variances that you discuss. 

 

 

REPORT 

 

To: Operations Director of Marshall Ltd 
From: 
Management Accountant 
Date: 
DD/MM/YY 
Subject: Performance of the service department 
 
1.0 Introduction 

 

The purpose of this report is to comment on the performance of the service department for the 
six months to 30 September 2003.  To suggest possible causes of such performance and also 
state  any  further  information  that  would  be  helpful  in  assessing  the  performance  of  this 
department. 
 
2.0 Sales volume 

 

The sales volume achieved for the six month period was 29600 services.  This is 400 short of 
the budgeted sales volume of 30000.  Even though 400 services do not seem to be materially 
significant,  the  overall  trend  from  month  4  to  6  is  downwards  and  therefore  this  should  be 
investigated. 

 

This downward spiral could be due to the following factors 

 

  A decline in business due to more intense competition  

  The business of servicing photocopiers is seasonal 

  A decline within the industry or market for photocopying servicing 

 
 

background image

81 

 
 

 

 

                                

 

 
 
Example 5.10 Part (b) - continued 

 

If business is not seasonal further information should be obtained about the competition and 
marketing methods they maybe using. As well as industry data which could be available e.g. 
from  financial  statements  of  competitors  or  trade  associations.    This  would  allow  a  better 
understanding of why sales maybe falling. 

 

2.1 Material 

 

The material price variance was favourable month 1 to 3 and now has become adverse over 
months 4 to 6.  This could be due to 

 

  The  increasing  cost  of  parts  and  components  required  for  photocopying  servicing 

within the industry 

  The purchasing department not negotiating the procurement of parts or  components 

at very good prices 

 

Further  investigation  will  be  required  as  well  as  perhaps  information  about  other  possible 
suppliers in order to find cheaper components should this trend continue. 
The material usage variance overall is significant for the six month period at £22,000 adverse. 
It also has been adverse for 4 out of the 6 months of performance.   

 

This could be due to  

 

  Greater wastage of components or parts by photocopying engineers 

  Poor  quality  components  or  parts  and  therefore  the  inability  to  use  them  due  to 

damage or obsolescence 

  Theft of components or parts 

 

The  adverse  price  variance  does  seem  to  suggest  that  wastage  is  perhaps  not  due  to  poor 
quality components. Although if prices are rising within the industry, perhaps poorer quality 
components  are  being  purchased  as  a  way  of  reducing  cost.    More  investigation  will  be 
needed.   

 

More  surprisingly  is  the  favourable  variance  in  month  2,  this  would  mean  less  than  the 
required  ‘2  sets’  of  materials  are  being  used  per  service  in  this  month.  This  could  mean 
customers  are  perhaps  being  short  changed  by  inadequate  servicing  e.g.  parts  are  not  being 
replaced.    If  this  affects  the  quality  of  service  Marshalls  provide  it  could  mean  significant 
business in the future could be lost. 

 

2.2 Labour 

 

The labour rate variance of £130,671 favourable is the most material of all variances.  This 
could  be  due  to  reduced  overtime  payments  e.g.  the  average  per  hour  falls,  or  cheaper  and 
perhaps less skilled labour is being used.  The efficiency variance in month 4 to 6 has been 
adverse which could suggest an interrelationship here.  Less skilled but cheaper labour could 
mean each service is taking longer than the average of 3 hours expected. 
 
 
 

background image

82 

 
 

 

 

                                

 

 
 
Example 5.10 Part (b) - continued 

 

Perhaps  because  Marshalls  are  paying  less  per  hour  than  £11,  key  staff  maybe  leaving  and 
being  replaced  with  cheaper  trainees  or  staff  are  taking  longer  because  of  lower  job 
satisfaction.  Both reasons can have an adverse impact on efficiency.  Further information on 
the composite of staff e.g. those fully, semi and untrained, as well as staff turnover rates need 
to be investigated to find out if this is the case.  Also Marshalls need to compare £11 an hour 
to  the  general  rate  paid  within  this  industry  e.g.  information  from  recruitment  media  or 
agencies. 

 

Given the significance of a £130,671 difference in budget there is also the possibility that the 
standard  of  £11  per  hour  is  wrong.    This  difference  perhaps  explained  by  a  planning  rather 
than operating variance.   

 

2.3 Variable overhead 

 

The variable overhead efficiency variance is directly linked to the labour efficiency variance 
e.g. if staff take longer then this drives more variable overhead being incurred.  The variable 
overhead  rate  variance  has  shifted  from  adverse  to  favourable  in  month  5  onwards.    This 
could indicate that less ‘consumables’ are being used for each service, which again could be 
due  to  the  customer  being  short  changed.  It  could  also  indicate  advancements  in  the 
techniques used when servicing photocopiers. 
 
2.4 Fixed overhead 

 

The  fixed  overhead  volume  variance  is  caused  by  under  or  over  absorption  of  production 
volume  for  each  period  e.g.  services  performed.    It  therefore  does  not  give  a  great  deal  of 
information for control purposes.  However the expenditure variance does give a great deal of 
concern  because  it  is  overall  £18,000  worse  than  budget  for  the  period,  although  has  got 
better from month 5 onwards.   

 

Perhaps the expenditure variance is due to unexpected rises in the fixed cost of running the 
department  e.g.  rent  increases  or  more  administration  or  support  staff  employed.    This 
therefore needs to be investigated by obtaining more recent data to analyse what costs have in 
fact risen.  It could be due to poor planning e.g. a rent increase not reflected in the budget in 
which case this is more a planning rather than operating variance. 

 

3.0 Conclusion 

 

Given  the  sum  of  all  expenditure  variances  together  are  £68,971  favourable  this  represents 
(£68,971  ÷  £3,315,200  flexed  budgeted  cost)  2%  below  budgeted  cost  for  29,600  services.  
Due  to  however  the  significance  of  the  variances  for  materials  usage,  labour  rate  and  fixed 
overhead expenditure, these  I advise should  be investigated further as a  priority and  further 
information sought as to what has caused these to be incurred for the period. 

 

 

Signed 

Management Accountant 

 
 

background image

83 

 
 

 

 

                                

 

Example 5.11 (a) 

 

A  pay  rise  was  given  to  kitchen  staff  as  from  the  beginning  of  last  month.  The  new  labour 
rate  payable  to  chefs  being  £11.25  rather  than  as  budgeted  £9.00  an  hour,  this  had  been 
overlooked and was not reflected in the budget. 
 

Flexed budget (based on 476 meals) 476 x 0.25hrs @ £9 per hr 

 

1,071   

 

 

 

 

Planning rate variance 

 

 

 

(476 meals x 0.25hrs) x £11.25 (revised standard rate) - £9.00 (old standard rate) 

268  (A) 

 

 

 

 

Operational rate variance 

 

 

 

120 hrs paid did cost  

1200   

 

120 hrs paid should cost (revised standard rate) £11.25 per hr 

1350   

 

 

 

150  (F) 

Operational efficiency variance 

Hrs 

 

 

476 meals did take (hours worked) 

114 

 

 

476 meals should take (x 0.25hrs per meal) 

119 

 

 

= 5hrs x (revised standard rate) £11.25 per hr 

 

56  (F) 

 

 

 

 

Operational idle time variance 

 

 

 

Hours paid (120hrs) - Hours worked (114hrs) x (revised standard rate) £11.25/hr 

68  (A) 

 

 

 

 

Actual cost of labour charged during the period 

 

1,200   

 
Note:  Before  planning  variances  were  introduced  the  operational  labour  rate  variance  was 
£120  adverse  but  now  as  above  £150  favourable.    No  one  should  get  the  blame  now  for 
overpaying staff. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

84 

 
 

 

 

                                

 

Example 5.11 (b) 
 
Expected  labour  efficiency  of  15  minutes  (0.25  hours)  per  meal  served  has  always  been 
considered by management as too generous, the budget was supposed to be updated last week 
using only 12 minutes (0.2 hours) per meal but was overlooked during the planning process. 
 

Flexed budget (based on 476 meals) 476 x 0.25hrs @ £9 per hr 

 

1,071   

 

 

 

 

Planning efficiency variance 

 

 

 

(476 meals x £9.00) x 0.2hrs (revised standard) - 0.25hrs (old standard) 

214  (F) 

 

 

 

 

Operational efficiency variance 

Hrs   

 

476 meals did take (hours worked) 

114   

 

476 meals should take x 0.2 hrs per meal (revised standard) 

95   

 

= 19hrs x £9.00 Std rate per hr 

 

171  (A) 

 

 

 

 

Operational rate variance 

 

 

 

120 hrs paid did cost  

1200   

 

120 hrs paid should cost £9.00 Std rate per hr 

1080   

 

 

 

120  (A) 

 

 

 

 

Operational idle time variance 

 

 

 

Hours paid (120hrs) - Hours worked (114hrs) x £9.00 Std rate per hr 

54  (A) 

 

 

 

 

Actual cost of labour charged during the period 

 

1,200   

 
Note:  Before  planning  variances  were  introduced  the  operational  labour  efficiency  variance 
was £45 favourable but now as above £171 adverse.  It seems chefs have not been as efficient 
as you would expect. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

85 

 
 

 

 

                                

 

Example 5.11 (c) 

 

Due to a salmonella scare across the country the price of chicken had fallen to £2 per kg at 
the beginning of the week. According to management this should be reflected in the budget. 
 

Flexed budget (based on 476 meals) 476 x 0.3kg @ £2.50 per kg 

 

357   

 

 

 

 

Planning price variance 

 

 

 

(476 meals x 0.3kg) x £2.00 (revised standard) - £2.50 (old standard) 

 

71  (F) 

 

 

 

 

Operational price variance 

 

 

 

180 Kg purchased did cost  

405   

 

180 Kg purchased should cost (revised standard) £2.00 per Kg 

360   

 

 

 

45  (A) 

Operational usage variance 

Kg   

 

476 meals did use  

165   

 

476 meals should use (x 0.3kg per meal) 

143   

 

= 22 Kg x (revised standard) £2.00 per Kg 

 

44  (A) 

 

 

 

 

 

 

 

 

180kg chicken did cost 

405   

 

Less 15kg closing stock valued at standard cost (revised standard) £2.00 a Kg 

30   

 

Actual cost of chicken charged during the period 

 

375   

 

 

 

 

 

Note:  Before  planning  variances  were  introduced  the  operational  price  variance  was  £45 
favourable but now as above £45 adverse.  It seems that staff responsible for purchasing the 
chicken have not been as efficient as you would expect when it came to getting a good price. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

86 

 
 

 

 

                                

 

Example 5.11 (d) 

 

Due to more skin and bone on the poultry purchased for the month, it was considered more 
realistic by management that 0.35kg of chicken should have been served for each meal rather 
than currently 0.3kg of chicken. 
 

Flexed budget (based on 476 meals) 476 x 0.3kg @ £2.50 per kg 

 

357   

 

 

 

 

Planning usage variance 

 

 

 

(476 meals x £2.50 per kg) x  0.3kg (old standard) - 0.35kg (revised standard) 

60  (A) 

 

 

 

 

Operational usage variance 

Kg   

 

476 meals did use  

165   

 

476 meals should use x 0.35kg per meal (revised standard) 

167   

 

2 Kg x £2.50 per Kg 

 

5  (F) 

 

 

 

 

Operational price variance 

 

 

 

180 Kg purchased did cost  

405   

 

180 Kg purchased should cost £2.50 per Kg 

450   

 

 

 

45  (F) 

180kg chicken did cost 

405   

 

Less 15kg closing stock valued at standard cost £2.50 per Kg 

38   

 

Actual cost of chicken charged during the period 

 

368   

 

Note:  Before  planning  variances  were  introduced  the  operational  usage  variance  was  £55 
adverse  but  now  as  above  £5  favourable.    It  seems  that  staff  responsible  for  serving  the 
chicken have been more lean when putting food on the customers plate. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

87 

 
 

 

 

                                

 

 
Example 5.12 
 
Machine expenditure and efficiency variances 
 
Standard cost of 25 pints £40 x 0.6 hrs = £24 per 25 pints. 
 
Expenditure 
 
42 hrs did cost  

 

 

 

1,880 

42 hrs should cost (42 x £40)   

 

1,680 

 

 

 

 

 

 

   200 (A) 

 
Efficiency 
 
1,900 pints did take    

 

 

 42.0 hrs 

1,900 pints should take (1,900/25 x 0.6 hrs)   45.6 hrs 
 

                                                                     3.6 hrs 

Standard cost per machine hour 

 

      x £40 

 

 

 

 

 

 

  144 (F) 

 
Operating statement 
 
Flexed budget based on actual output achieved Budget 1,900/25 x £24 =  1,824 
Efficiency 

 

 

 

 

   

 

 

 

   144 (F) 

Expenditure   

 

 

 

    

 

 

 

   200 (A) 

Actual cost 

 

 

 

 

 

 

 

 

1,880 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

88 

 
 

 

 

                                

 

 
Example 5.12 - continued 
 
What if you were told that the machine had been replaced at the beginning of the period 
with  a  machine  that  is  20%  faster  than  the  previous  model,  but  this  had  not  been 
reflected in the budget? 
 
Revise standard 0.6hrs x 0.8 (20% faster time!!) = 0.48 hours new standard efficiency.  
 
Planning machine efficiency variance 
 
1,900 pints should have taken according to old std (÷ 25 pints x 0.6 hours)   

46 hrs 

1,900 pints should have taken according to new std (÷ 25 pints x 0.48 hours) 

36 hrs 

 

 

 

 

 

 

 

 

 

 

            10 hrs 

 

 

 

 

 

 

 

 

 

 

              x £40  

Planning machine efficiency variance                                                                      400 (F) 
 
No change in machine expenditure operational variance  
 
Operational efficiency variance (revised due to the new standard time) 
 
Did take 

 

 

 

                                                                      36 hrs 

Should take (1,900 ÷ 25 pints) x (0.6 hrs x 0.8) 

 

 

 

          42 hrs 

 

 

 

 

 

 

 

 

 

 

            6 hrs 

 

 

 

 

 

 

 

 

 

 

            x £40 

 

 

 

 

 

 

 

 

 

                    240 (A) 

Operating statement  
 
Flexed budget based on actual output achieved (1,900 ÷ 25) x (0.6 x £40) =  1,824 
Planning (machine efficiency) 

 

 

 

 

  

 

 400 (F) 

Operational efficiency variance 

 

 

 

  

 

 

 240 (A) 

Operational expenditure variance 

 

 

 

 

 

             200 (A) 

Actual cost 

 

 

 

 

 

 

 

 

          1,880  

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

89 

 
 

 

 

                                

 

 
Example 5.13 
 
George  Ritver  within  his  book  ‘The  McDonaldisation  of  Society’  listed  the  advantages  of 
producing  standard  or  homogenous  products,  the  pinnacle  comparison  being  McDonalds, 
with its fast food strategy of uniformity of operations and standardised delivery on a global 
basis. Standardisation reduces cost and improves efficiency within organisations. 

 

By  the  introduction  of  a  McDonaldisation  approach  to  service  delivery,  the  likely  impact 
upon budgeting preparation and control for UV Ltd would be as follows. 

 

  Easier  to  create  a  pre-defined  standard  because  of  greater  uniformity  within  the 

specification  of  meals  produced.    Pricing  would  be  easier  and  less  time  consuming 
because of this. 

  Budget preparation would be easier, more accurate and less time consuming. 
  Greater  predictability,  UV  Ltd  always  will  have  a  uniform  standard  to  compare  to 

actual  cost  to  calculate  any  variances  e.g.  easier  flexed  budgeting  and  exception 
reporting. 

  Easier  to  manage,  organise,  train  and  control  catering  staff  because  of  the  greater 

uniformity  of  meals  they  produce.    The  proficiency  of  staff  can  be  assessed  more 
effectively. 

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

background image

90 

 
 

 

 

                                

 

 
Example 5.14 

 

 

Tip:  Try not to get too confused here.  The variances are no different to the normal 
variances that you encounter in your studies.  A clear layout, displaying the standard 
cost and the calculation of just three variances would have passed this question. 

 

  The nursing efficiency variances are similar to a labour efficiency variance.  It 

took 1 day longer at standard rate to deliver care for one patient.  Also 0.9 staff 
was  used  as  a  ratio  to  the  patient  rather  than  0.75.    Both  indicate  greater 
inefficiency. 

  One  day  extra  created  more  space  and  food  consumed  which  is  similar  to  a 

material usage variance. 

  Drugs and specific material is similar to an expenditure variance. 

 

 

 

 

 

      £ 

Standard cost of one procedure 

 

 

1,165 

 

 

 

 

Variances: 

 

 

 

Nursing efficiency (1 day x 0.75 nurse x £320 per day) 

240  (A)   

Nursing efficiency (0.9 - 0.75 nurse) x 3 days x £320 

144  (A)   

Space and food (1 day x £175) 

175  (A)   

Drugs and specific materials (£320 - £115) 

205  (A)   

Overhead (1 day x £110) 

110  (A)   

 

 

 

874  

Actual cost 

 

 

2,039 

 

 

 

 

Actual cost 

 

 

        £ 

Nursing (3 days x 0.9 nurse x £320) 

 

 

864 

Space and food (3 days x £175) 

 

 

525 

Drugs and specific materials (actual cost) 

 

 

320 

Overhead (3 days x £110 per day) 

 

 

330 

 

 

 

2,039 

 
 
 
 
 
 
 
 
 
 
 
 

background image

91 

 
 

 

 

                                

 

Example 5.15 
 
MCQ 1.1 Answer A 
 
(7300-6780) x 5.00 = sales volume variance £2,600 (A) 
6780 x (13.00-13.80) = sales price variance £5,424 (F) 
 
MCQ 1.2 Answer C 
 
(27.50-30.00) x 770 = £1,925 (A) 
 
MCQ 1.3 Answer A 
 
(0.4 x £30.00) x (770-800) = £360 (A) 
 
MCQ 1.4 Answer D 
 

 

 

 

 

 

 

 

 

Actual mix 

Standard mix  Difference    Price 

   £ 

Steak   

 

 852 

 

 921 

 

-69 

(3.50-5.60) 

 145 (F) 

Kidney  

 

 990 

 

 921 

 

+69 

(3.50-1.40)       145 (F) 

 

 

           1,842            1,842                                                      290 (F) 

 
Weighted average standard price per kg (0.6/1.2 x £5.60) + (0.6/1.2 x £1.40) = £3.50 
 
MCQ 1.5 Answer C 
 
1842kg should yield (1,842/1.2kg)  1,535 
1842kg did yield 

 

 

1,350 

 

 

 

 

 

   185 

 

 

 

 

 

x £4.20 

 

 

 

 

 

  777(A) 

MCQ 1.6 Answer A 
 
Using high/low method to separate fixed and variable cost 
 
High  18,000  

      £41,000 

Low     10,000  

      £25,000 

 

 8,000   

      £16,000 

 
Variable cost £16,000/8,000 = £2.00 
 
Therefore fixed cost (18,000 x 2 = 36,000) – 41,000 = 5,000 
 
Therefore 12,750 hours should cost ((12,750 x 2) + 5,000)   

30,500 

 

     12,750 hours did cost 

 

 

 

 

32,560 

 

 

 

 

 

 

 

 

 

  2,060 (A) 

 
 

background image

92 

 
 

 

 

                                

 

Example 5.15 - continued 
 
MCQ 1.7 Answer A 
 
2,386/5.60 = 426 variance in labour hours 
 
Should take 4hrs x 4,260 units = 17,040 hours therefore if adverse it took 426 hrs longer than 
expected. 
 
17,040 + 426 = 17,466 hours 
 
MCQ 1.8 Answer D 
 
Adverse variance £4,875/6.50 = 750kg variance in usage. 

 

Should have used 3,000 units x 2kg = 6,000kg 

 

Therefore actual usage 6,000kg + 750kg = 6,750kg 

 

Closing stock rose by 800kg therefore must have purchased 6,750kg + 800kg = 7,550kg 
 
MCQ 1.9 Answer A 
 
Flexed budget 950 x 4kg x £12.50 =   

 

£47,500 

Revised budget 950 x 4kg x £13.00 = 

           (£49,400) 

Planning price variance 

 

 

 

£1,900(A) 

 
3,800kg of material P did cost = 

 

 

£50,160 

 

3,800kg of material P should cost 

 

 

(3,800kg x revised standard £13.00) = 

           (£49,400) 

 

 

 

 

 

 

 

     £760(A) 

 
MCQ 1.10 Answer A 
 
68 hours did produce   

 

60.0 units 

68 should produce (68/1.1hrs) 

61.8 units 

 

 

 

 

 

  1.8 

 

 

 

 

 

x £5.20 

 

 

 

 

 

£9.36 (A) 

 
 
 
 
 
 
 
 
 
 

background image

93 

 
 

 

 

                                

 

Example 5.15 - continued 
 
MCQ 1.11 Answer C 
 
Planning rate variance 
40 hours x £7.50 (original standard)   

 

 

£300 

40 hours x £5.50 (revised standard)   

 

 

£220 

 

 

 

 

 

 

 

 

  £80(F) 

 
Operational rate variance 
40 hours x £5.50 (revised standard) should cost 

 

£220 

40 hours did cost 

 

 

 

 

 

£270   

 

 

 

 

 

 

 

 

 

              £50(A) 

 
MCQ 1.12 Answer A 
 
Planning 
60 x 0.6 (old standard) x £5.50 an hour 

 

£198 

60 x 0.5 (new standard) x £5.50 an hour 

 

£165 

 

 

 

 

 

 

 

  £33(F) 

Operational 
60 units did take 

 

 

 

 

40 hours    

60 units should take (x 0.5)   

 

 

30 hours 

 

 

 

 

 

 

 

 

10 hours 

 

 

 

 

 

 

 

x £5.50 

 

 

 

 

 

 

 

£55(A)  

 
MCQ 1.13 Answer B 
 

 

 

 

       % of one unit of output 

 

 

Kg  

 

 

3 kg after wastage  

75%  

 

1 kg of wastage 

25% or 25%/75% x 3kg 

Standard usage per unit of output 

100%  

 

 

 

 

 

 

 

3 kg (after wastage of 25%) x 100%/75% (after wastage) = 4 kg 

 

 

 

 

 

 

 

4 kg = 100% before wastage 

 

 

 

 

 

 

 

 

 

 

 
 
 
 
 
 
 
 

background image

94 

 
 

 

 

                                

 

Example 5.15 - continued 
 
MCQ 1.14 Answer A 
 
OAR = £300,000/40,000 = £7.50 
 
Standard  hours  would  be  the  standard  labour  time  per  unit  x  the  number  of  units  actually 
produced,  therefore  the  company  would  have  absorbed  fixed  overhead  for  the  period  of 
39,000 x £7.50 = £292,500 
 
Fixed overhead expenditure variance 
Budgeted expenditure  

 

 

 

 

 

£300,000 

Actual expenditure       

 

 

 

 

          (£315,000) 

 

 

 

   

 

 

 

 

 

  £15,000 (A) 

 
Fixed overhead volume variance 
Budgeted expenditure to be absorbed (£7.50 x 40,000 hours) =        £300,000 
Actual expenditure absorbed for the period   (£7.50 x 39,000) =  

 £292,500 

 

 

 

 

 

 

 

 

 

     £7,500 (A) 

 
or  

 

 

 

                 40,000 – 39,000 x £7.50 =      £7,500 (A) 

 
MCQ 1.15 Answer D 
 

Did use   

 

 

 

 

2,300 x 3.3 kg = 

 

 

7,590  

Should use 

 

 

 

 

2,300 x 3.5 kg = 

 

 

8,050  

 

 

 

 

460  

 

 

 

 

 

x Standard price   

 

£5.00  

 

 

 

 

 

 

Material usage variance 

 

£2,300.00 (F) 

 

 

 

 

 

 

or 2,300 x (3.3 kg - 3.5 kg) x £5.00 = 

£2,300.00 (F) 

 

 

 

 

 

 

 
MCQ 1.16 Answer B 
 

Did purchase 

 

 

 

 

6,700 kg  x (£7.60 - £ 7.00)  = 

£4,020 (A) 

 
 
 
 
 

background image

95 

 
 

 

 

                                

 

Example 5.15 - continued 
 
MCQ 1.17 Answer A 
 

Did work 

 

 

32,450  

Should work 

 

 

 

 

4,260 x 8 hours  =   

 

34,080  

 

 

 

 

1,630  

 

 

 

 

 

x Standard price   

 

£7.60  

 

 

 

 

 

 

Material usage variance 

 

£12,388 (F)