var nodeInfo=[{view: "view:_LVCagP5WEdmAzesbYywanQ", path: ["_LVCagP5WEdmAzesbYywanQ", "_4U33kAILEdq-_NKqZM1EhA", "_qIh6UABuEdqrKcHWz1HoWw", "{EE97A8CD-66CA-4A9B-9871-E3B94CCED528}", "2.0746098019135414E-305"]}, {view: "view:_FCx1oN7CEdmsEI4YDGX2ag", path: ["_FCx1oN7CEdmsEI4YDGX2ag", "_f6_YwN7DEdmsEI4YDGX2ag", "_qIh6UABuEdqrKcHWz1HoWw", "{EE97A8CD-66CA-4A9B-9871-E3B94CCED528}", "2.0746098019135414E-305"]}, {view: "view:_FCx1oN7CEdmsEI4YDGX2ag", path: ["_FCx1oN7CEdmsEI4YDGX2ag", "_jD8dUAIbEdqEutyfYo0quQ", "_vzRNgDIcEdqDs_9ORT1Rig", "2.0746098019135414E-305"]}];
contentPage.preload(imgPath, backPath, nodeInfo, '', false, false, false);
Concept: Estimating Project Effort
This guideline describes how to estimate project effort using estimating techniques based on Use Cases and the Wideband Delphi estimating technique.
Relationships
Related Elements
Project Manager
Main Description
Introduction
One of the most common desires in software development projects is to accurately determine in advance the total cost of
the project. With cost and schedule overruns being the industry norm, that desire is understandable. However, the
current state of software development practice isn't a predictive science, as clearly evidenced by the vast array of
project failures.
That said, it is still useful to attempt some estimation of project costs, then calibrate those estimates based on
actual findings as the project progresses. Here are some techniques that you may find useful in estimating software
project costs.
Use-Case Points
This technique originated from on work done at Objective Systems SF AB, and was first proposed in a 1993 paper by
Gustav Karner entitled Resource Estimation for Objectory Projects. This technique enables the estimation of the
resources needed to develop a software system by using the elements of the use-case model as a basis for that
estimation. The use-case points (UCP) that are derived from this method can then be used to determine the equivalent
function point (FP) count. Function Points (FP) are a common technique for estimations, proposed by Albrecht A. J.
(1979), Measuring application development productivity.
For more information, see the Whitepaper: The Estimation of Effort Based on Use Cases.
Wideband Delphi
Originating at the Rand Corporation in 1948, this technique began as the Delphi estimation method. The basic technique
called upon a small team of experts to anonymously generate individual estimates from a problem description and reach
consensus on a final set of estimates through iteration.
In the early 1970s, Barry Boehm and his Rand colleagues extended the basic method to include more estimation team
interaction, which resulted in the Wideband Delphi method; see Software Engineering Economics. [BOE81]. Mary Sakry and Neil Potter of The Process Group, a Dallas, Texas-based
consulting company, later created a repeatable procedure for performing Wideband Delphi estimation on software
projects. This guideline explains that procedure.
For more Information, see the Technique: Estimating Effort Using the Wideband Delphi Technique.
© Copyright IBM Corp. 1987, 2006. All Rights Reserved.
contentPage.onload();
Wyszukiwarka
Podobne podstrony:
project prasy do wyciskaniaAdvanced Project Management?ycja polska?promconceive new project?5322C0Fundamentowanie Project 1tailor process for projectlFD05E2prepare environment for project 602A4prepare environment for project?133D66The Babylon Project Eye of the ShadowProject manager CV example 1Projects SelFolderForm dfmTHE SHADOW BEAST PROJECTevaluate project scope and risk?77352close out project?C97419create project configuration management cm environmentsAB92128więcej podobnych podstron