project planning review A08073A0






Task: Project Planning Review









var defaultQueryStr = '?proc={EA0C1D32-E39A-4D96-B956-E178DB776A96}&path={EA0C1D32-E39A-4D96-B956-E178DB776A96},_Dt0jMBsuEdqXHNTdjKtnvA,_gKGwoEogEdqrjq4i3fchvA';
var backPath = './../../';
var imgPath = './../../images/';
var nodeInfo=null;
contentPage.preload(imgPath, backPath, nodeInfo, defaultQueryStr, true, true, false);










Task: Project Planning Review















This task describes how to review the Software Development Plan.






Purpose



To approve the initial Software Development Plan To review and approve changes to the Software Development Plan



Relationships



RolesMain:



Management Reviewer


Additional:
Assisting:



InputsMandatory:



Software Development Plan


Optional:



Business Case


Risk List


Vision


External:


None




Outputs


Review Record






Main Description



The initial Project Planning Review is held near the end of the Inception Phase, when the Software Development Plan is fully developed and includes a high level phase plan that the project team has a high degree of confidence in. Subsequent Project Planning Reviews are held at scheduled points where the Software Development Plan is expected to be revised (e.g. at the end of each iteration). They are also held at "un-scheduled" points triggered by the need to make changes to the plan as a result of problems in the project.



Steps




Schedule Project Planning Review Meeting



Attendees of the Project Planning Review meeting should include representatives from senior management, and all groups that will have to commit resources to the project as required by the Software Development Plan (e.g., Development/Engineering, Operations, QA, Test, Customer Support, etc.). Typically these would comprise the Project Review Authority, along with team leads for the various functional areas of the project team. Once the attendees of the Project Planning Review Meeting have been identified, set a date/time for the meeting to take place. It is important that you provide sufficient lead time to allow the participants to review the project materials that will be used as the basis for the approval decision.



Distribute Meeting Materials



Prior to the meeting, distribute the project materials to the reviewers. Make sure these materials are sent out sufficiently in advance of the Project Approval Review Meeting to allow the reviewers adequate time to review them. A minimum set of work products that should be presented for review is: Vision Business Case Risk List Software Development Plan (and its enclosed plans)



Conduct Project Planning Review Meeting



During the meeting, the reviewers assess the proposed Software Development Plan to determine whether it represents a program of activity that will deliver the project objectives. The reviewers also look for any erroneous assumptions or omissions in the plan. Consider such things as: Does the plan address the needs identified in the Business Case and Vision? Will the plan deliver the desired results within the schedule and budget outlined in the Business Case? Has the plan been developed to a sufficient level of detail that the outcome of the project can be realistically predicted? Have project estimates been prepared using sound analytical methods? Are review points and milestones scheduled at frequent enough intervals? Are plans in place to mitigate/avoid all serious risks? Are sufficient resources identified in the plan, and are these resources available/acquirable? Are roles and responsibilities clearly defined? Are the monitoring and control processes defined in the plan acceptable? Are all the supporting plans and guidelines completed to an acceptable level of detail? At the end of the meeting, the reviewers should make their approval decision. The result can be one of the following: Plan Approved  The project will proceed as planned. Senior management commits remaining funds and resources for the project.  Project Canceled  Project no longer viable given the known risks and project budget/schedule.  Decision deferred  More information is needed, or further investigation is required before an approval decision can be made. 



Record Decision



At the end of the meeting, a Review Record is completed capturing any important discussions or action items, and recording the result of the Project Planning Review. If the result was "decision deferred" a follow-up Project Planning Review Meeting should be scheduled for a later date.







Properties



Multiple Occurrences


Event Driven


Ongoing


Optional


Planned


Repeatable





©  Copyright IBM Corp. 1987, 2006.  All Rights Reserved.







contentPage.onload();
contentPage.processPage.fixDescriptorLinks();




Wyszukiwarka

Podobne podstrony:
project planning reviewt2A8F4E
project planning review?46897A
project approval review?65DDFD
project approval review?A2089B
review requirements tmS4695E9
REVIEWANSWERS
project prasy do wyciskania
Advanced Project Management?ycja polska?prom
JRC NRD 525 technical review
conceive new project?5322C0
Fundamentowanie Project 1
tailor process for projectlFD05E2
DoD Joint Services Weapon Safety Review Process
prepare environment for project 602A4

więcej podobnych podstron