Microsoft Office Project Project1 siatka

background image

Mechanical stubbing

Start: 11-05-13

ID: 3

Finish: 11-05-19

Dur: 5 days

Res:

Erecting fencing with wickets and gates

Start: 11-05-13

ID: 4

Finish: 11-05-16

Dur: 2 days

Res:

Erecting gateways

Start: 11-05-13

ID: 5

Finish: 11-05-13

Dur: 0,5 days

Res:

Timber wickets with lath and posts, steel posts - erecting

Start: 11-05-13

ID: 6

Finish: 11-05-13

Dur: 0,5 days

Res:

EARTHWORKS

Start: 11-05-20

ID: 7

Finish: 11-05-24

Dur: 3 days

Comp: 0%

Removal of humus with use of dozers, thickness of the layer up to 15 cm

Start: 11-05-20

ID: 8

Finish: 11-05-20

Dur: 0,5 days

Res:

Measurement during foundation trench, terrain low-lying and plain

Start: 11-05-20

ID: 9

Finish: 11-05-20

Dur: 0,5 days

Res:

Earthworks with push shovel with transport of excavated material by trucks, excavator 0,4m^3, soil category I-II

Start: 11-05-23

ID: 10

Finish: 11-05-24

Dur: 2 days

Res:

FOUNDATION

Start: 11-05-25

ID: 11

Finish: 11-06-14

Dur: 14,5 days

Comp: 0%

Concrete subfloor on the subsoil, concrete delivery with use of wheel-barrow

Start: 11-05-26

ID: 13

Finish: 11-05-26

Dur: 1 day

Res:

GROUND FLOOR

Start: 11-06-14

ID: 20

Finish: 11-07-15

Dur: 23,5 days

Comp: 0%

Floor on the soil

Start: 11-06-14

ID: 21

Finish: 11-06-29

Dur: 11,5 days

Comp: 0%

Subfloor made of compacted loose materials on the soil, sand

Start: 11-06-14

ID: 22

Finish: 11-06-17

Dur: 3 days

Res:

Formwork assembling

Start: 11-05-25

ID: 12

Finish: 11-05-25

Dur: 1 day

Res:

Formwork disassembling

Start: 11-06-01

ID: 14

Finish: 11-06-01

Dur: 1 day

Res:

BUILDING SITE PREPARATION WORKS

Start: 11-05-13

ID: 2

Finish: 11-05-19

Dur: 5 days

Comp: 0%

START

Milestone Date: Fri 11-05-13

ID: 1

Walls

Start: 11-06-30

ID: 28

Finish: 11-07-15

Dur: 12 days

Comp: 0%

Page 1

background image

Stairs

Start: 11-06-30

ID: 34

Finish: 11-06-30

Dur: 0,5 days

Comp: 0%

FLOOR

Start: 11-07-18

ID: 37

Finish: 11-08-17

Dur: 22,5 days

Comp: 0%

Slab

Start: 11-07-18

ID: 38

Finish: 11-08-01

Dur: 10,5 days

Comp: 0%

Page 2

background image

ATTIC

Start: 11-08-17

ID: 51

Finish: 11-09-02

Dur: 12,5 days

Comp: 0%

Page 3

background image

Page 4

background image

Page 5

background image

Foundation made of bricks with cement mortar

Start: 11-06-02

ID: 15

Finish: 11-06-03

Dur: 2 days

Res:

Damp insulation, double layer of building paper

Start: 11-06-06

ID: 16

Finish: 11-06-06

Dur: 1 day

Res:

Foundation walls made of bricks, common brick, cement mortar, thickness of 2 brick

Start: 11-06-07

ID: 17

Finish: 11-06-10

Dur: 4 days

Res:

Damp insulation of vertical surface, bulding paper, 1 layer

Start: 11-06-13

ID: 18

Finish: 11-06-13

Dur: 1 day

Res:

Backfilling of excavation with bulldozers, replacing on the distance up to 10 m , soil category I-II, bulldozer 74 kW (100 KM)

Start: 11-06-14

ID: 19

Finish: 11-06-14

Dur: 0,5 days

Res:

Concrete subfloor on the soil, concrete delivery by pump

Start: 11-06-20

ID: 24

Finish: 11-06-22

Dur: 2 days

Res:

Reinforcement of the concrete elements of the building, round ribbed steel bars, Fi 8-14 mm

Start: 11-06-22

ID: 25

Finish: 11-06-23

Dur: 1 day

Res:

Reinforced slab, concrete delivery by pump

Start: 11-06-23

ID: 26

Finish: 11-06-23

Dur: 0,5 days

Res:

Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks

Start: 11-06-30

ID: 29

Finish: 11-07-15

Dur: 12 days

Res:

Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 1-brick

Start: 11-06-30

ID: 30

Finish: 11-07-01

Dur: 1,5 days

Res:

Posts and fillars made of common brick , dimension: 2x2 of brick, cement - lime mortar

Start: 11-06-30

ID: 31

Finish: 11-06-30

Dur: 1 day

Res:

Lintels made by using PERI formwork, ratio perimeter/cross-section: up to 8 m/m2, version 1

Formwork assembling

Start: 11-06-17

ID: 23

Finish: 11-06-20

Dur: 1 day

Res:

Formwork disassembling

Start: 11-06-29

ID: 27

Finish: 11-06-29

Dur: 1 day

Res:

Page 6

background image

Start: 11-06-30

ID: 32

Finish: 11-06-30

Dur: 1 day

Res:

Chimney ducts made of hollow bricks

Start: 11-06-30

ID: 33

Finish: 11-06-30

Dur: 0,5 days

Res:

Buildings made of elements OWT-67N : staircase landing

Start: 11-06-30

ID: 35

Finish: 11-06-30

Dur: 0,5 days

Res:

Buildings made of elements OWT-67N : flight of the stairs

Start: 11-06-30

ID: 36

Finish: 11-06-30

Dur: 0,5 days

Res:

DZ type slab, hollow brick DZ-3, prefabricated beams

Start: 11-07-19

ID: 40

Finish: 11-07-22

Dur: 3,5 days

Res:

DZ type slab, hollow brick DZ-3, prefabricated beams, monolithic ring beam in the external walls with thickness up to 30 cm

Start: 11-07-25

ID: 41

Finish: 11-07-25

Dur: 0,5 days

Res:

Buildings made of elements OWT-65N: gravel concrete slab

Start: 11-07-19

ID: 44

Finish: 11-07-19

Dur: 0,5 days

Res:

Walls

Start: 11-08-01

ID: 45

Finish: 11-08-17

Dur: 12 days

Comp: 0%

Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks

Start: 11-08-01

ID: 46

Finish: 11-08-17

Dur: 12 days

Res:

Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks

Start: 11-08-01

ID: 47

Finish: 11-08-02

Dur: 1,5 days

Res:

Posts and fillars made of common brick , dimension: 2x2 of brick, cement - lime mortar

Start: 11-08-01

ID: 48

Finish: 11-08-02

Dur: 1 day

Res:

Lintels made by using PERI formwork, ratio perimeter/cross-section: up to 8 m/m2, version 1

Start: 11-08-01

ID: 49

Finish: 11-08-02

Dur: 1 day

Res:

Chimney ducts made of hollow bricks

Start: 11-08-01

ID: 50

Finish: 11-08-02

Dur: 1 day

Res:

Formwork assembling

Start: 11-07-18

ID: 39

Finish: 11-07-19

Dur: 1,5 days

Res:

Overconcrete pouring, concrete delivery by pump

Start: 11-07-25

ID: 42

Finish: 11-07-25

Dur: 1 day

Res:

Formwork disassembling

Start: 11-07-29

ID: 43

Finish: 11-08-01

Dur: 1,5 days

Res:

Page 7

background image

Slab

Start: 11-08-17

ID: 52

Finish: 11-08-31

Dur: 10,5 days

Comp: 0%

DZ type slab, hollow brick DZ-3, prefabricated beams

Start: 11-08-19

ID: 54

Finish: 11-08-24

Dur: 3,5 days

Res:

DZ type slab, hollow brick DZ-3, prefabricated beams, monolithic ring beam in the external walls with thickness

Start: 11-08-24

ID: 55

Finish: 11-08-24

Dur: 0,5 days

Res:

Wall beam

Start: 11-09-01

ID: 58

Finish: 11-09-02

Dur: 2 days

Comp: 0%

Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks

Start: 11-09-01

ID: 59

Finish: 11-09-02

Dur: 2 days

Res:

Chimney ducts made of hollow bricks

Start: 11-09-01

ID: 60

Finish: 11-09-01

Dur: 0,5 days

Res:

ROOF

Start: 11-09-05

ID: 61

Finish: 11-09-14

Dur: 8 days

Comp: 0%

Rafter framing

Start: 11-09-05

ID: 62

Finish: 11-09-08

Dur: 3,5 days

Comp: 0%

Collar roof with wall beam under plain tile double layered, rafter framing with span 12 m

Start: 11-09-05

ID: 63

Finish: 11-09-08

Dur: 3,5 days

Res:

Covering

Start: 11-09-08

ID: 64

Finish: 11-09-14

Dur: 4,5 days

Comp: 0%

Damp and water-proof insulation made of wide polyethylene sheeting, horizontal insulaton uder flooring

Start: 11-09-08

ID: 65

Finish: 11-09-12

Dur: 2 days

Res:

Thermal and acoustic insulation made of mineral wool, vertical

Start: 11-09-08

ID: 66

Finish: 11-09-09

Dur: 1,5 days

Res:

Placing asphalt shingles with width 8 cm

Start: 11-09-08

ID: 67

Finish: 11-09-14

Dur: 4,5 days

Res:

FINISHING WORKS

Start: 11-09-15

ID: 73

Finish: 11-10-19

Dur: 24,5 days

Comp: 0%

Partition walls

Start: 11-09-15

ID: 74

Finish: 11-09-16

Dur: 1,5 days

Comp: 0%

Woodwork

Start: 11-09-15

ID: 76

Finish: 11-09-16

Dur: 2 days

Comp: 0%

Formwork assembling

Start: 11-08-17

ID: 53

Finish: 11-08-18

Dur: 1,5 days

Res:

Overconcrete pouring, concrete delivery by pump

Start: 11-08-24

ID: 56

Finish: 11-08-25

Dur: 1 day

Res:

Formwork disassembling

Start: 11-08-30

ID: 57

Finish: 11-08-31

Dur: 1,5 days

Res:

Page 8

background image

Page 9

background image

Roof gutter made of galvanized iron, semicircular with diameter 15 cm

Start: 11-09-08

ID: 68

Finish: 11-09-09

Dur: 1 day

Res:

Downpipe made of galvanized iron, semicircular with diameter 15 cm

Start: 11-09-08

ID: 69

Finish: 11-09-09

Dur: 1 day

Res:

Different treatment made of galvanized iron with width up to 25 cm

Start: 11-09-08

ID: 70

Finish: 11-09-12

Dur: 2 days

Res:

Erecting chimney bench

Start: 11-09-08

ID: 71

Finish: 11-09-08

Dur: 0,5 days

Res:

Placing windows in the roof slope

Start: 11-09-08

ID: 72

Finish: 11-09-09

Dur: 1 day

Res:

Ironwork

Start: 11-09-15

ID: 93

Finish: 11-09-15

Dur: 1 day

Comp: 0%

KONIEC

Milestone Date: Wed 11-10-19

ID: 105

Page 10

background image

Page 11

background image

Page 12

background image

Partition walls of the mutli-storey buildings with thickness 12 cm, made of lime - sand blocks, type: 2NFD

Start: 11-09-15

ID: 75

Finish: 11-09-16

Dur: 1,5 days

Res:

External door frame, double painting on the building site

Start: 11-09-15

ID: 77

Finish: 11-09-15

Dur: 0,5 days

Res:

External door leaf panel, prefabricated up to 2 m2

Start: 11-09-15

ID: 78

Finish: 11-09-15

Dur: 0,5 days

Res:

Windows and balcony doors made of timber, composite

Start: 11-09-15

ID: 79

Finish: 11-09-16

Dur: 2 days

Res:

Casement window, without ventilator, 0,5-0,7 m2

Start: 11-09-15

ID: 80

Finish: 11-09-15

Dur: 0,5 days

Res:

Page 13

background image

Casement window, without ventilator, 0,7-1,0 m2

Start: 11-09-15

ID: 81

Finish: 11-09-15

Dur: 0,5 days

Res:

Casement window, without ventilator, 1,0-1,5 m2

Start: 11-09-15

ID: 82

Finish: 11-09-16

Dur: 2 days

Res:

Casement window, without ventilator, 1,5-2,0 m2

Start: 11-09-15

ID: 83

Finish: 11-09-16

Dur: 1,5 days

Res:

Casement window, without ventilator, 2,0-3,0 m2

Start: 11-09-15

ID: 84

Finish: 11-09-15

Dur: 0,5 days

Res:

Door frame with expansion slot

Start: 11-09-15

ID: 85

Finish: 11-09-15

Dur: 1 day

Res:

Portcullises to the garage, welded to concrete door frame

Start: 11-09-16

ID: 86

Finish: 11-09-16

Dur: 1 day

Res:

Horizontal insulation

Start: 11-09-19

ID: 87

Finish: 11-10-03

Dur: 11 days

Comp: 0%

Damp and water-proof insulation, made of wide polyethylene sheeting, horizontal insulaton uder flooring

Start: 11-09-19

ID: 88

Finish: 11-09-22

Dur: 3,5 days

Res:

Horizontal thermal and acoustic insulation made of polystyrene

Start: 11-09-22

ID: 89

Finish: 11-10-03

Dur: 7,5 days

Res:

Facade

Start: 11-09-19

ID: 90

Finish: 11-09-27

Dur: 7 days

Comp: 0%

Horizontal thermal and acoustic insulation made of polystyrene , vertical insulation with mortar with metal lath

Start: 11-09-19

ID: 91

Finish: 11-09-22

Dur: 4 days

Res:

Gypsum plaster of category II, external walls, mechanically made

Start: 11-09-23

ID: 92

Finish: 11-09-27

Dur: 3 days

Res:

Internal plasters

Start: 11-10-04

ID: 96

Finish: 11-10-10

Dur: 5 days

Comp: 0%

Common plasters, mechanically made, walls, category II, buildings up to 8 floors

Start: 11-10-04

ID: 97

Finish: 11-10-07

Dur: 4 days

Res:

Common plasters, mechanically made, slabs , category II, buildings up to 8 floors

Start: 11-10-04

ID: 98

Finish: 11-10-10

Dur: 5 days

Res:

Flooring

Start: 11-10-11

ID: 99

Finish: 11-10-19

Dur: 6,5 days

Comp: 0%

Leveling layers under flooring , made of cement mortar with thickness 20 mm, trowelled

Start: 11-10-11

ID: 100

Finish: 11-10-19

Dur: 6,5 days

Res:

Wood flooring

Start: 11-10-11

ID: 101

Finish: 11-10-18

Dur: 5,5 days

Res:

Lacquering of flooring and parquets

Start: 11-10-11

ID: 102

Page 14

background image

Stairs railing made of steel bars

Start: 11-09-15

ID: 94

Finish: 11-09-15

Dur: 0,5 days

Res:

Balcony railing with steel handrail

Start: 11-09-15

ID: 95

Finish: 11-09-15

Dur: 1 day

Res:

Finish: 11-10-12

Dur: 2 days

Res:

Flooring made of articial stones, preparing the base

Start: 11-10-11

ID: 103

Finish: 11-10-11

Dur: 0,5 days

Res:

Flooring made of articial stones, plates 15x15 cm, common method

Start: 11-10-11

ID: 104

Finish: 11-10-14

Dur: 3,5 days

Res:

Page 15

background image

Critical

Noncritical

Critical Milestone

Milestone

Critical Summary

Summary

Critical Inserted

Inserted

Critical Marked

Marked

Critical External

External

Project Summary

Highlighted Critical

Highlighted Noncritical

Page 16

Project: Project1
Date: Fri 11-05-27


Wyszukiwarka

Podobne podstrony:
Microsoft Office Project Project1 id 299062
Microsoft Office Project Project1 strony id 299064
BYT 2005 Microsoft Office Project 2003 Professional
Microsoft Office Project Harmonogram
Microsoft Office Project Project1 id 299062
Microsoft Office Project harmonogram OSTATECZNY
w aaaa1904 Microsoft Excel or Microsoft Project Why Microsoft Office Project 2007 is Easier and Mor
Microsoft Office Project harmonogram
Microsoft Office Project Project1
Cenniki bud ~$wy Dokument programu Microsoft Office Word
Nowy Dokument programu Microsoft Office Word (2)
Nowy Dokument programu Microsoft Office Word (16)
Nowy Dokument programu Microsoft Office Word (3)
Nowy Dokument programu Microsoft Office Word (19)
Nowy Dokument programu Microsoft Office Word (2)
Nowy Dokument programu Microsoft Office Word
Nowy Dokument programu Microsoft Office Word 6

więcej podobnych podstron