Mechanical stubbing
Start: 11-05-13
ID: 3
Finish: 11-05-19
Dur: 5 days
Res:
Erecting fencing with wickets and gates
Start: 11-05-13
ID: 4
Finish: 11-05-16
Dur: 2 days
Res:
Erecting gateways
Start: 11-05-13
ID: 5
Finish: 11-05-13
Dur: 0,5 days
Res:
Timber wickets with lath and posts, steel posts - erecting
Start: 11-05-13
ID: 6
Finish: 11-05-13
Dur: 0,5 days
Res:
EARTHWORKS
Start: 11-05-20
ID: 7
Finish: 11-05-24
Dur: 3 days
Comp: 0%
Removal of humus with use of dozers, thickness of the layer up to 15 cm
Start: 11-05-20
ID: 8
Finish: 11-05-20
Dur: 0,5 days
Res:
Measurement during foundation trench, terrain low-lying and plain
Start: 11-05-20
ID: 9
Finish: 11-05-20
Dur: 0,5 days
Res:
Earthworks with push shovel with transport of excavated material by trucks, excavator 0,4m^3, soil category I-II
Start: 11-05-23
ID: 10
Finish: 11-05-24
Dur: 2 days
Res:
FOUNDATION
Start: 11-05-25
ID: 11
Finish: 11-06-14
Dur: 14,5 days
Comp: 0%
Concrete subfloor on the subsoil, concrete delivery with use of wheel-barrow
Start: 11-05-26
ID: 13
Finish: 11-05-26
Dur: 1 day
Res:
GROUND FLOOR
Start: 11-06-14
ID: 20
Finish: 11-07-15
Dur: 23,5 days
Comp: 0%
Floor on the soil
Start: 11-06-14
ID: 21
Finish: 11-06-29
Dur: 11,5 days
Comp: 0%
Subfloor made of compacted loose materials on the soil, sand
Start: 11-06-14
ID: 22
Finish: 11-06-17
Dur: 3 days
Res:
Formwork assembling
Start: 11-05-25
ID: 12
Finish: 11-05-25
Dur: 1 day
Res:
Formwork disassembling
Start: 11-06-01
ID: 14
Finish: 11-06-01
Dur: 1 day
Res:
BUILDING SITE PREPARATION WORKS
Start: 11-05-13
ID: 2
Finish: 11-05-19
Dur: 5 days
Comp: 0%
START
Milestone Date: Fri 11-05-13
ID: 1
Walls
Start: 11-06-30
ID: 28
Finish: 11-07-15
Dur: 12 days
Comp: 0%
Page 1
Stairs
Start: 11-06-30
ID: 34
Finish: 11-06-30
Dur: 0,5 days
Comp: 0%
FLOOR
Start: 11-07-18
ID: 37
Finish: 11-08-17
Dur: 22,5 days
Comp: 0%
Slab
Start: 11-07-18
ID: 38
Finish: 11-08-01
Dur: 10,5 days
Comp: 0%
Page 2
ATTIC
Start: 11-08-17
ID: 51
Finish: 11-09-02
Dur: 12,5 days
Comp: 0%
Page 3
Page 4
Page 5
Foundation made of bricks with cement mortar
Start: 11-06-02
ID: 15
Finish: 11-06-03
Dur: 2 days
Res:
Damp insulation, double layer of building paper
Start: 11-06-06
ID: 16
Finish: 11-06-06
Dur: 1 day
Res:
Foundation walls made of bricks, common brick, cement mortar, thickness of 2 brick
Start: 11-06-07
ID: 17
Finish: 11-06-10
Dur: 4 days
Res:
Damp insulation of vertical surface, bulding paper, 1 layer
Start: 11-06-13
ID: 18
Finish: 11-06-13
Dur: 1 day
Res:
Backfilling of excavation with bulldozers, replacing on the distance up to 10 m , soil category I-II, bulldozer 74 kW (100 KM)
Start: 11-06-14
ID: 19
Finish: 11-06-14
Dur: 0,5 days
Res:
Concrete subfloor on the soil, concrete delivery by pump
Start: 11-06-20
ID: 24
Finish: 11-06-22
Dur: 2 days
Res:
Reinforcement of the concrete elements of the building, round ribbed steel bars, Fi 8-14 mm
Start: 11-06-22
ID: 25
Finish: 11-06-23
Dur: 1 day
Res:
Reinforced slab, concrete delivery by pump
Start: 11-06-23
ID: 26
Finish: 11-06-23
Dur: 0,5 days
Res:
Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks
Start: 11-06-30
ID: 29
Finish: 11-07-15
Dur: 12 days
Res:
Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 1-brick
Start: 11-06-30
ID: 30
Finish: 11-07-01
Dur: 1,5 days
Res:
Posts and fillars made of common brick , dimension: 2x2 of brick, cement - lime mortar
Start: 11-06-30
ID: 31
Finish: 11-06-30
Dur: 1 day
Res:
Lintels made by using PERI formwork, ratio perimeter/cross-section: up to 8 m/m2, version 1
Formwork assembling
Start: 11-06-17
ID: 23
Finish: 11-06-20
Dur: 1 day
Res:
Formwork disassembling
Start: 11-06-29
ID: 27
Finish: 11-06-29
Dur: 1 day
Res:
Page 6
Start: 11-06-30
ID: 32
Finish: 11-06-30
Dur: 1 day
Res:
Chimney ducts made of hollow bricks
Start: 11-06-30
ID: 33
Finish: 11-06-30
Dur: 0,5 days
Res:
Buildings made of elements OWT-67N : staircase landing
Start: 11-06-30
ID: 35
Finish: 11-06-30
Dur: 0,5 days
Res:
Buildings made of elements OWT-67N : flight of the stairs
Start: 11-06-30
ID: 36
Finish: 11-06-30
Dur: 0,5 days
Res:
DZ type slab, hollow brick DZ-3, prefabricated beams
Start: 11-07-19
ID: 40
Finish: 11-07-22
Dur: 3,5 days
Res:
DZ type slab, hollow brick DZ-3, prefabricated beams, monolithic ring beam in the external walls with thickness up to 30 cm
Start: 11-07-25
ID: 41
Finish: 11-07-25
Dur: 0,5 days
Res:
Buildings made of elements OWT-65N: gravel concrete slab
Start: 11-07-19
ID: 44
Finish: 11-07-19
Dur: 0,5 days
Res:
Walls
Start: 11-08-01
ID: 45
Finish: 11-08-17
Dur: 12 days
Comp: 0%
Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks
Start: 11-08-01
ID: 46
Finish: 11-08-17
Dur: 12 days
Res:
Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks
Start: 11-08-01
ID: 47
Finish: 11-08-02
Dur: 1,5 days
Res:
Posts and fillars made of common brick , dimension: 2x2 of brick, cement - lime mortar
Start: 11-08-01
ID: 48
Finish: 11-08-02
Dur: 1 day
Res:
Lintels made by using PERI formwork, ratio perimeter/cross-section: up to 8 m/m2, version 1
Start: 11-08-01
ID: 49
Finish: 11-08-02
Dur: 1 day
Res:
Chimney ducts made of hollow bricks
Start: 11-08-01
ID: 50
Finish: 11-08-02
Dur: 1 day
Res:
Formwork assembling
Start: 11-07-18
ID: 39
Finish: 11-07-19
Dur: 1,5 days
Res:
Overconcrete pouring, concrete delivery by pump
Start: 11-07-25
ID: 42
Finish: 11-07-25
Dur: 1 day
Res:
Formwork disassembling
Start: 11-07-29
ID: 43
Finish: 11-08-01
Dur: 1,5 days
Res:
Page 7
Slab
Start: 11-08-17
ID: 52
Finish: 11-08-31
Dur: 10,5 days
Comp: 0%
DZ type slab, hollow brick DZ-3, prefabricated beams
Start: 11-08-19
ID: 54
Finish: 11-08-24
Dur: 3,5 days
Res:
DZ type slab, hollow brick DZ-3, prefabricated beams, monolithic ring beam in the external walls with thickness
Start: 11-08-24
ID: 55
Finish: 11-08-24
Dur: 0,5 days
Res:
Wall beam
Start: 11-09-01
ID: 58
Finish: 11-09-02
Dur: 2 days
Comp: 0%
Walls of the multi-storey buildings made of bricks, common brick, cement mortar, thickness of the 2-bricks
Start: 11-09-01
ID: 59
Finish: 11-09-02
Dur: 2 days
Res:
Chimney ducts made of hollow bricks
Start: 11-09-01
ID: 60
Finish: 11-09-01
Dur: 0,5 days
Res:
ROOF
Start: 11-09-05
ID: 61
Finish: 11-09-14
Dur: 8 days
Comp: 0%
Rafter framing
Start: 11-09-05
ID: 62
Finish: 11-09-08
Dur: 3,5 days
Comp: 0%
Collar roof with wall beam under plain tile double layered, rafter framing with span 12 m
Start: 11-09-05
ID: 63
Finish: 11-09-08
Dur: 3,5 days
Res:
Covering
Start: 11-09-08
ID: 64
Finish: 11-09-14
Dur: 4,5 days
Comp: 0%
Damp and water-proof insulation made of wide polyethylene sheeting, horizontal insulaton uder flooring
Start: 11-09-08
ID: 65
Finish: 11-09-12
Dur: 2 days
Res:
Thermal and acoustic insulation made of mineral wool, vertical
Start: 11-09-08
ID: 66
Finish: 11-09-09
Dur: 1,5 days
Res:
Placing asphalt shingles with width 8 cm
Start: 11-09-08
ID: 67
Finish: 11-09-14
Dur: 4,5 days
Res:
FINISHING WORKS
Start: 11-09-15
ID: 73
Finish: 11-10-19
Dur: 24,5 days
Comp: 0%
Partition walls
Start: 11-09-15
ID: 74
Finish: 11-09-16
Dur: 1,5 days
Comp: 0%
Woodwork
Start: 11-09-15
ID: 76
Finish: 11-09-16
Dur: 2 days
Comp: 0%
Formwork assembling
Start: 11-08-17
ID: 53
Finish: 11-08-18
Dur: 1,5 days
Res:
Overconcrete pouring, concrete delivery by pump
Start: 11-08-24
ID: 56
Finish: 11-08-25
Dur: 1 day
Res:
Formwork disassembling
Start: 11-08-30
ID: 57
Finish: 11-08-31
Dur: 1,5 days
Res:
Page 8
Page 9
Roof gutter made of galvanized iron, semicircular with diameter 15 cm
Start: 11-09-08
ID: 68
Finish: 11-09-09
Dur: 1 day
Res:
Downpipe made of galvanized iron, semicircular with diameter 15 cm
Start: 11-09-08
ID: 69
Finish: 11-09-09
Dur: 1 day
Res:
Different treatment made of galvanized iron with width up to 25 cm
Start: 11-09-08
ID: 70
Finish: 11-09-12
Dur: 2 days
Res:
Erecting chimney bench
Start: 11-09-08
ID: 71
Finish: 11-09-08
Dur: 0,5 days
Res:
Placing windows in the roof slope
Start: 11-09-08
ID: 72
Finish: 11-09-09
Dur: 1 day
Res:
Ironwork
Start: 11-09-15
ID: 93
Finish: 11-09-15
Dur: 1 day
Comp: 0%
KONIEC
Milestone Date: Wed 11-10-19
ID: 105
Page 10
Page 11
Page 12
Partition walls of the mutli-storey buildings with thickness 12 cm, made of lime - sand blocks, type: 2NFD
Start: 11-09-15
ID: 75
Finish: 11-09-16
Dur: 1,5 days
Res:
External door frame, double painting on the building site
Start: 11-09-15
ID: 77
Finish: 11-09-15
Dur: 0,5 days
Res:
External door leaf panel, prefabricated up to 2 m2
Start: 11-09-15
ID: 78
Finish: 11-09-15
Dur: 0,5 days
Res:
Windows and balcony doors made of timber, composite
Start: 11-09-15
ID: 79
Finish: 11-09-16
Dur: 2 days
Res:
Casement window, without ventilator, 0,5-0,7 m2
Start: 11-09-15
ID: 80
Finish: 11-09-15
Dur: 0,5 days
Res:
Page 13
Casement window, without ventilator, 0,7-1,0 m2
Start: 11-09-15
ID: 81
Finish: 11-09-15
Dur: 0,5 days
Res:
Casement window, without ventilator, 1,0-1,5 m2
Start: 11-09-15
ID: 82
Finish: 11-09-16
Dur: 2 days
Res:
Casement window, without ventilator, 1,5-2,0 m2
Start: 11-09-15
ID: 83
Finish: 11-09-16
Dur: 1,5 days
Res:
Casement window, without ventilator, 2,0-3,0 m2
Start: 11-09-15
ID: 84
Finish: 11-09-15
Dur: 0,5 days
Res:
Door frame with expansion slot
Start: 11-09-15
ID: 85
Finish: 11-09-15
Dur: 1 day
Res:
Portcullises to the garage, welded to concrete door frame
Start: 11-09-16
ID: 86
Finish: 11-09-16
Dur: 1 day
Res:
Horizontal insulation
Start: 11-09-19
ID: 87
Finish: 11-10-03
Dur: 11 days
Comp: 0%
Damp and water-proof insulation, made of wide polyethylene sheeting, horizontal insulaton uder flooring
Start: 11-09-19
ID: 88
Finish: 11-09-22
Dur: 3,5 days
Res:
Horizontal thermal and acoustic insulation made of polystyrene
Start: 11-09-22
ID: 89
Finish: 11-10-03
Dur: 7,5 days
Res:
Facade
Start: 11-09-19
ID: 90
Finish: 11-09-27
Dur: 7 days
Comp: 0%
Horizontal thermal and acoustic insulation made of polystyrene , vertical insulation with mortar with metal lath
Start: 11-09-19
ID: 91
Finish: 11-09-22
Dur: 4 days
Res:
Gypsum plaster of category II, external walls, mechanically made
Start: 11-09-23
ID: 92
Finish: 11-09-27
Dur: 3 days
Res:
Internal plasters
Start: 11-10-04
ID: 96
Finish: 11-10-10
Dur: 5 days
Comp: 0%
Common plasters, mechanically made, walls, category II, buildings up to 8 floors
Start: 11-10-04
ID: 97
Finish: 11-10-07
Dur: 4 days
Res:
Common plasters, mechanically made, slabs , category II, buildings up to 8 floors
Start: 11-10-04
ID: 98
Finish: 11-10-10
Dur: 5 days
Res:
Flooring
Start: 11-10-11
ID: 99
Finish: 11-10-19
Dur: 6,5 days
Comp: 0%
Leveling layers under flooring , made of cement mortar with thickness 20 mm, trowelled
Start: 11-10-11
ID: 100
Finish: 11-10-19
Dur: 6,5 days
Res:
Wood flooring
Start: 11-10-11
ID: 101
Finish: 11-10-18
Dur: 5,5 days
Res:
Lacquering of flooring and parquets
Start: 11-10-11
ID: 102
Page 14
Stairs railing made of steel bars
Start: 11-09-15
ID: 94
Finish: 11-09-15
Dur: 0,5 days
Res:
Balcony railing with steel handrail
Start: 11-09-15
ID: 95
Finish: 11-09-15
Dur: 1 day
Res:
Finish: 11-10-12
Dur: 2 days
Res:
Flooring made of articial stones, preparing the base
Start: 11-10-11
ID: 103
Finish: 11-10-11
Dur: 0,5 days
Res:
Flooring made of articial stones, plates 15x15 cm, common method
Start: 11-10-11
ID: 104
Finish: 11-10-14
Dur: 3,5 days
Res:
Page 15
Critical
Noncritical
Critical Milestone
Milestone
Critical Summary
Summary
Critical Inserted
Inserted
Critical Marked
Marked
Critical External
External
Project Summary
Highlighted Critical
Highlighted Noncritical
Page 16
Project: Project1
Date: Fri 11-05-27