02 Plan for Implementing ISO 9001 2000 Rev 1 1 03

Approved by: IsoQual, Inc.
Title: Management Representative Quality Management System (QMS) Implementation/Training Schedule 15-I-22
Date: 1 October 2002 Applicable Standards/Requirements: ISO 9001:2000


< -----2002----- > < -------------------------------------2003------------------------------------ > < ----------------2004--------------- >
ACTIVITY Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Key Milestones























1. Conduct Initial On-Site Assessment o All personnel to participate (<1 hour each)


















Report of Findings issued NLT 10/6/02























2. Conduct Quality Policy Development Workshop o Top Management and all Department Heads to participate (8 hours each)


















Draft Quality Manual issued NLT 10/19/02























3. Conduct QMS Implementation Workshop o All personnel involved in SOP/WI development to participate (8 hours each)


















Final Quality Manual issued NLT: 10/31/02























4. Conduct Procedure (SOP) Development Workshops m o All personnel involved in SOP development to participate (4 hours / week for 6 weeks)

















All SOPs approved NLT: 11/30/02























5. Conduct Work Instruction (WI) Development Workshops
m o All personnel involved in WI development to participate (4 hours / week for 6 weeks)
















All WIs approved NLT: 12/31/02























6. Conduct Awareness and Internal Auditor Training

o Awareness Training to be attended by all employees (2 hours each)
















Course Certificates issued NLT: 12/31/02



o Internal Auditor Training to be attended by 4 personnel (14 hours each)
















Course Certificates issued NLT: 12/31/02























7. QMS Assessment and Follow-Up Support
o Registrar Selection

















Registrar Selected NLT: 11/30/02




o Pre-Assessment Audit performed by (Registrar)















Preassessment Completed NLT: 1/31/03






o Registration audit performed by (Registrar)













ISO Registration Achieved NLT: 3/31/03



m h h o Implement Corrective/Preventive Actions








h h h h h Corrective Actions Implemented (as required)
























Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

< -----2002----- > < -------------------------------------2003------------------------------------ > < ----------------2004--------------- >























STATUS KEY












































Planned Start Date: m







Planned Completion Date:






o



Actual Start Date: J







Actual Completion Date:






x













On-going Activity:






h



























POA&M Format

Wyszukiwarka

Podobne podstrony:
NORMA ISO 9001 2000 4 STR , Zarządzanie projektami, Zarządzanie(1)
koncepcja modularna a ISO 9001 2000, Zarządzanie i Inżynieria Produkcji - studia, Jakość
Podrecznik wdrazania ISO 9001 2000 podiso
Plan auditu ISO 9001
Norma ISO 9001 2008 ZUT sem 3 2014
03 2000 Revisions Overview Rev 3 1 03
2 PN ISO 9001 2 1996
02 PLAN POZYCJI RZUT STROPU
Normy ISO 9001 i 9004, Inżynieria materiałowa pwr, Zarządzanie jakością

więcej podobnych podstron