Approved by: |
IsoQual, Inc. |
|
Title: Management Representative |
Quality Management System (QMS) Implementation/Training Schedule |
15-I-22 |
Date: 1 October 2002 |
Applicable Standards/Requirements: ISO 9001:2000 |
|
|
|
< -----2002----- > |
< -------------------------------------2003------------------------------------ > |
< ----------------2004--------------- > |
|
ACTIVITY |
Oct |
Nov |
Dec |
Jan |
Feb |
Mar |
Apr |
May |
Jun |
Jul |
Aug |
Sep |
Oct |
Nov |
Dec |
Jan |
Feb |
Mar |
Apr |
May |
Jun |
Key Milestones |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Conduct Initial On-Site Assessment |
o |
All personnel to participate (<1 hour each) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Report of Findings issued NLT 10/6/02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2. Conduct Quality Policy Development Workshop |
o |
Top Management and all Department Heads to participate (8 hours each) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Draft Quality Manual issued NLT 10/19/02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3. Conduct QMS Implementation Workshop |
o |
All personnel involved in SOP/WI development to participate (8 hours each) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Final Quality Manual issued NLT: 10/31/02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4. Conduct Procedure (SOP) Development Workshops |
m |
o |
All personnel involved in SOP development to participate (4 hours / week for 6 weeks) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
All SOPs approved NLT: 11/30/02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5. Conduct Work Instruction (WI) Development Workshops |
|
m |
o |
All personnel involved in WI development to participate (4 hours / week for 6 weeks) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
All WIs approved NLT: 12/31/02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6. Conduct Awareness and Internal Auditor Training |
|
|
o |
Awareness Training to be attended by all employees (2 hours each) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Course Certificates issued NLT: 12/31/02 |
|
|
|
o |
Internal Auditor Training to be attended by 4 personnel (14 hours each) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Course Certificates issued NLT: 12/31/02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7. QMS Assessment and Follow-Up Support |
|
o |
Registrar Selection |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Registrar Selected NLT: 11/30/02 |
|
|
|
|
o |
Pre-Assessment Audit performed by (Registrar) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Preassessment Completed NLT: 1/31/03 |
|
|
|
|
|
|
o |
Registration audit performed by (Registrar) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ISO Registration Achieved NLT: 3/31/03 |
|
|
|
m |
h |
h |
o |
Implement Corrective/Preventive Actions |
|
|
|
|
|
|
|
|
|
h |
h |
h |
h |
h |
Corrective Actions Implemented (as required) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Oct |
Nov |
Dec |
Jan |
Feb |
Mar |
Apr |
May |
Jun |
Jul |
Aug |
Sep |
Oct |
Nov |
Dec |
Jan |
Feb |
Mar |
Apr |
May |
Jun |
|
|
< -----2002----- > |
< -------------------------------------2003------------------------------------ > |
< ----------------2004--------------- > |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
STATUS KEY |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Planned Start Date: |
m |
|
|
|
|
|
|
|
|
Planned Completion Date: |
|
|
|
|
|
|
|
o |
|
|
|
|
Actual Start Date: |
J |
|
|
|
|
|
|
|
|
Actual Completion Date: |
|
|
|
|
|
|
|
x |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
On-going Activity: |
|
|
|
|
|
|
|
h |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
POA&M Format |
|