RIKEN Accel. Próg. Rep. 24 (1990)
VI-2. Residual Activities in the Ring Cyclotron Facility
S. Fujita, T. Takagi, S. Okamoto, N. Nakanishi,
I. Sakamoto, T. Inamura, and H. Kamitsubo
Residual activities were measured at various points in the Ring Cyclotron Facility.
From June 18 to 24, an experiment was carried out with a 14N7' beam of 135 MeV/u in the experimental vault E4. However, because water leakage was found at a part of north side dee of the AVF cyclotron at the last day of the experi-
Fig. 1. Detection points around the injector AVF cyclotron. Dose rates are indicated in units of nSv/h.
nient, the acceleration chamber was opened. On June 27, residual activities in the AVF cyclotron
Fig. 2. Detection points around RIKEN Ring Cyclotron. EDC, an electrostatic deflection channel; MDC1, a magnetic deflection channel 1; MDC2, a magnetic deflection channel 2; MDP1, a main differential probe 1; MI)P2, a main differential probe 2; MI)P3, a main differential probe 3. Numerals indicated are dose rates in units of //Sv/h.
Fig. 3. Layout of RIKEN Ring Cyclotron facility as of 1990. Monitoring positions are denoted by x. Detection points of residual activity on the beam lines are denoted by alphabets.
Wyszukiwarka
Podobne podstrony:
209 RIKEN Accel. Próg. Rep. 24 (1990)VI-3. Leakage Radiation Measurements in the Ring Cyclotron Faci103 RIKEN Accel. Próg. Rep. 24 (1990)111-5-9. Test Experiment of the GARIS/IGISOL K. Morita, T. Nomu92 RIKEN Accel. Próg. Rep. 24 (1990)111-5. Instrumentation1. Design of a Microbeamline for a Compact94 RIKEN Accel. Próg. Rep. 24 (1990)111-5-2. Design of a Decay Muon Channel Using an Axially Symmetr102 RIKEN Accel Próg. Rep. 24 (1990)111-5-8. Performance of Isotopic Separation in RIPS T.Nakamura,105 RIKEN Accel. Próg. Rep. 24 (1990)111-5-10. Velocity Distribution of IGISOL lon Beams M. Koizumi,108 RIKEN Accel. Próg. Rep. 24 (1990)111-5-12. Status Report of the RIKEN Swinger-Magnetic Analyzer110 RIKEN Accel. Próg. Rep. 24 (1990)111-5-14. Test for Dispersive-Mode Beam Transportto the SMART116 RIKEN Accel. Próg. Rep. 24 (1990)111-5-19. Responses of Large Position-Sensitive Detectorsto Hea121 RIKEN Accel. Próg. Rep. 24 (1990)IM-5-23. A Test for SMART Neutron Detectors H. Orihara, K. HataRIKEN Accel. Próg. Rep. 24 (1990)111-5-25. High Speed Serial Data Link for PC-9801 J. Fujita > PC129 RIKEN Accel. Próg. Rep. 24 (1990)IV-2. Cross Section Data for 68Ge ProductionY. Tendow, A. Hashi132 RIKEN Accel. Próg. Rep. 24 (1990)IV-5. Cross Sections Calculated by an ALICE Codęin the A = 50 —133 RIKEN Accel. Próg. Rep. 24 (1990)V. DEVELOPMENT OF ACCELERATOR FACILITIES1. lon Accelerator Deve138 RIKEN Accel. Próg. Rep. 24 (1990)V-l-4. RIKEN (Japan)-RAL (U.K.) Collaboration on Muon Science R5 RIKEN Accel. Próg. Rep. 24 (1990)11-2. RILAC Operation Y. Chiba, M. Hemmi, M. Yanokura, M. Kasę, Ewięcej podobnych podstron