Air transportation problems regarding the MS-40 bridge 197
Reąuirements for mobility and erection of such a bridge in ffeely selected remote Crossing points, impose the need to examine the possibility of the air transport of bridge components.
Currently, the most popular means of tactical military transport in Poland is the C-130E Hercules (Fig. 8).
Fig. 8. C-130E Hercules transport aircraft. General view and cargo hołd interior
Overall dimensions of the hołd (excl. ramp): (LxWxH):12.5 m x 3.04 m x 2.74 m, maximum cargo weight 19,050 kg, payload depends on the reąuired flight rangę. For instance, if the reąuired flight rangę is ca. 1111 km, payload is lower at ca. 17,690 kg.
Theoretically, it is possible to transport the MS-40 bridge assembly using the C-130E aircraft with cargo space dimensions (LxWxH) of 12.5 m x 3.04 m x 2.74 m. This, however, reąuires the use of several transport aircraft.
In order for the laying vehicle (Fig. 9) fit in the cargo space of the aircraft, the JELCZ C662D.OP carrier truck needs to have the following parts dismantled: armoured cab, spare wheel support, suction system stack. The trailer needs to have the crane and layer dismantled. Additionally, the truck and layer have to be disconnected and treated as separate loads.
Then the approximate dimensions of the units are as follows: truck: (LxWxH: 7.5 m x2.55 m x 2.63 m), layer: (LxWxH: 10.8 m x 2.55 m x 2.25 m). The permissible weight
Wyszukiwarka
Podobne podstrony:
Air transportation problems regarding the MS-40 bridge 201 5. SUMMARY MS-40 bridge units can be tranAir transportation problems regarding the MS-40 bridge 193 Fig. 3. Front and rear overhang and rampAir transportation problems regarding the MS-40 bridge 195 the reąuired flying rangę of the aircraftAir transportation problems regarding the MS-40 bridge 199 The spans (folded) must be transported as98 Zbigniew RACZYŃSKIAIR TRANSPORTATION PROBLEMS REGARDING THE MS-40 BRIDGE Abstract. The article prSzybkobieżne Pojazdy Gąsienicowe (39) nr 1,2016 Zbigniew RACZYŃSKIAIR TRANSPORTATION PROBLEMS REGARDTheoretical and Methodological Problems 15 The growing interest in ecosystem services in cities andSikorzyńska wtorek NEXT AuLumn the BBC is to screon a serics for lesbians and homosexuals, possWe use this formula to fine the number of cells reąuired for Stavanger and Sandnes „ „ &The Cool Team members Cooling jacket for bottled and canned beverages CEO: Marcin Stoma Business20 Yalery Bialevich tion and reconstruction of such buildings are quite urgent and reąuire the use oENTITIES RESPONSIBLE FOR TRANSPORT > Responsibility for mobility and transport infrastructure RoaThis Exposure Draft of the proposed International Financial Reporting Standard for Smali and Medium-Report from the Organizing Committee Rapport du Comite d Organisation 1. History and Organization ofpsalm1263 The Lord has done great things for iw, and we are filled with joy. Psalm 126:3 * %Problemy transportu lotniczego mostu MS-40 97 Wymiary przestrzeni ładunkowej samolotu An-70 wynoszą:Problemy transportu lotniczego mostu MS-40 89 Rys. 3. Zwisy przedni i tylny oraz kąt rampowy stanowiProblemy transportu lotniczego mostu MS-40 91 użytecznego. W przypadku samolotu C-130E startującegowięcej podobnych podstron