checklist2[1]

background image

Steerprop

TECHNICAL INFORMATION

DESIGNERS' CHECKLIST No. 2

Offshore Support Vessels

background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels


TABLE OF CONTENTS

HULL FORM

1.

Stern Lines .................................................................................................. 1

2.

Hard Chine .................................................................................................. 2

3.

Round Bilge................................................................................................. 2

4.

Transom ...................................................................................................... 2

SKEG

5.

Skeg Size .................................................................................................... 3

WEIGHT, HYDROSTATIC, STABILITY

6.

Weight......................................................................................................... 4

7.

Trim and Draft.............................................................................................. 4

HULL STRENGTH

8.

Mounting Adapters....................................................................................... 4

9.

Navigation Mast........................................................................................... 5

10.

Shaft Bearing Support.................................................................................. 5

11.

Bulwark ....................................................................................................... 5

12.

Skeg............................................................................................................ 5

PROPULSOR INSTALLATION

13.

Propulsor Installation Alternatives................................................................. 5

14.

Distance between the Propulsor Units .......................................................... 7

15.

Propulsor Tilting and Heeling........................................................................ 8

INTERMEDIATE SHAFTS

16.

Shaft Arrangement....................................................................................... 9

17.

Shaft Angle................................................................................................ 12

18.

Cardan Joint Phasing................................................................................. 13

CONTROL LAYOUT

19.

Control Layout ........................................................................................... 13

PROPULSOR ROOM SPACE

20.

Propulsor Room Space .............................................................................. 14

MAIN ENGINE

21.

Main Engine Choice .................................................................................. 14

EXTERNAL CONNECTIONS

22.

Electricity................................................................................................... 14

23.

Cabling...................................................................................................... 14

24.

External Tanks........................................................................................... 15

25.

Cooling...................................................................................................... 15

background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels

This “checklist” is compiled in order to enable designers with no or little experience in

azimuth propulsion vessels to make significantly better preliminary designs and proposals

for azimuth propulsion vessels. The list can also well serve the experienced designer as a

checklist or reminder that important aspects have been considered in the design.

The list is based on a the experience of supporting naval architects, shipyards and owners

with comments, hints and suggestions on how to improve their designs in order to optimise

the available performance of vessels equipped with azimuth propulsion. When compiling

the list we have also used direct input from naval architects on what is special on vessels

with azimuth propulsion and what should be kept in mind when designing these kinds of

vessels.

The list is in no way exhaustive and does not include every important aspect of a good

azimuth propulsor vessel design. It is more to be seen as a reminder to details often not

known, forgotten or ignored.

The advice and details in the list should not be taken as requirements, nor can a vessel be

designed solely relying on the items in this list – the real work, and end result is still up to

the naval architect designing the vessel, as is the full responsibility. Steerprop Ltd. cannot

be held responsible for any possible negative influence on any design based on the

proposals in this list.

HULL FORM

1.

Stern Lines

Offshore support vessels with azimuth propulsors should be designed with
a “buttock flow” or - also called, “pram-type” – stern, where the water
inflow to the propellers is mainly along the buttocks, not from the sides.
The angle between the baseline and the buttocks in the stern should be

kept as small as possible. A good rule-of-thumb for maximum
recommended angle is 13º + 1º for each meter of immersion (hull draft).
Thus, the angle should normally be kept less than 17º …18º (fig. 1).

Fig.1.

Profile of a buttock flow stern. Maximum recommended angle a is 13º + 1º for each meter

of draft

background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels

2

Larger angles will cause the water flow to separate and cause turbulence
in front of the propeller, as well as water inflow from the sides – both of
which are prone to decrease propeller performance drastically.

The stern profile is often S-formed, but there is neither need nor benefit in

this neither in straightening the buttocks to be almost horizontal in way of
the propulsors.

The stern should, however, have a slight V-angle all the way to the

transom. There is no need for flattening the area in way of the propulsors.
A V-angle – even a slight one – will reduce the risk for stern slamming in
waves.

The propulsors may protrude below base line, as on some designs they do.

This should also be considered in the skeg dimensions.

2.

Hard Chine

Hard chine designs are possible, but only double chine type is
recommended. Alignment of the chine needs special attention, as flow
separation may occur where flow-lines cross the chine. This increases the

resistance and deteriorates the operating conditions for the propeller,
reducing the performance of the vessel correspondingly.

The double chine should extend all the way to the transom.

3.

Round Bilge

From the hydrodynamic point of view the best bilge form is a round bilge,

with a radius growing towards the stern.

4.

Transom

The transom should be designed with as little immersion as possible, as
the water “trapped” behind the transom causes a large increase in
resistance.

An immersed transom may be “cut off” at approximately 45º to the
waterline in way of the waterline in order to improve astern performance,
fig. 2. A cut off will have a substantial influence on both astern speed and

astern manoeuvrability.

The propulsor should not be installed too close to the transom in order to
avoid ventilation of the propeller while going astern or braking.

background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels

3

Fig. 2. A transom “cut-off”, as shown above, will improve the astern performance substantially

SKEG

5.

Skeg Size

The skeg can normally be very small without losing the directional
stability. A short skeg will make the vessel more manoeuvrable and will
improve astern course keeping and performance. In no case should the

skeg run all the way to the propulsors, when turned for astern sailing, fig.
3. A too long skeg will also make sidestepping difficult as the water flow
from the propulsor is re-directed by skeg.

Fig. 3. Maximum skeg length shown in the left figure. The right figure shows a too long skeg.

The draft of the skeg should preferably be large enough to go below the
azimuth propulsors by 100…300mm. However, dry-docking procedures

should be taken into account, especially when the propulsion units are
protruding below the bottom of the hull.

background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels

4

WEIGHT, HYDROSTATICS, STABILITY

6.

Weight

The weight of the azimuth propulsors may come as a surprise and often it

will be difficult to get a proper balance, if not accounted for in the basic
design. The units are way back in an area with little or no hull volume.
Hence, the centre of gravity for the rest of the vessel needs to be kept
more forward than on similar vessels with conventional propulsion.

7.

Trim and Draft

It should be possible to alter at least the trim in order to improve the

performance and to prevent ventilation of the propellers in waves or when
braking or when running astern. Supply vessels may be required to have
ample ballast tanks in order to compensate for cargo and to improve the

performance of the empty vessel.

HULL STRENGTH

8.

Mounting Adapters

Minimum recommended mounting adapter height is 300 …500 mm at the
lowest point, depending on size and form, fig. 4. Minimum height is

determined by strength requirements and installation procedure.

min. 300 mm

Mounting adapter

Fig. 4.

A drawing showing the mounting adapter and its minimum height.

The hull in way of the azimuth propulsors may require extra strength to

accomplish the correct sequence of damage, i.e. the propulsor should
break before tearing off the bottom.

background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels

5

9.

Navigation Mast

The mast needs to be stiff enough and possibly supported to reduce
excessive vibrations, especially in fast manoeuvres at high speed.

10.

Shaft Bearing Supports

The shaft bearing supports need to be stiff and strong enough to take the

load of the rotating shaft.

11.

Bulwark

The bulwark should be inclined inwards to prevent it from touching when
close to other vessels. Ideally the bulwark should not be as far to the sides
as possible, but some tens of centimetres inwards to enable easy stepping

onboard without having to jump the bulwark first.

The bulwark around aft deck need to be strong enough to take the whole
weight of the tow wire without shearing, if the vessel is equipped with an
aft winch and intended also for towing.

12.

Skeg

The skeg need to be supported inside the hull, not just welded to the
bottom plate. A “soft” skeg may cause severe vibration throughout the
vessel, not only to the skeg itself. The vessel is also supported by the skeg
during dry-docking and it is the first part to hit the bottom in case of

grounding, thus protecting the propeller nozzles.

PROPULSOR INSTALLATION

13.

Propulsor Installation Alternatives

The Steerprop propulsors may be installed in several different
configurations and variations thereof. Additional, customized installation

configurations can also be arranged. The main installation modes are:

Weld-in installation

Small bolt-in mounting cone

Large mounting adapter for thru-hull mounting

background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels

6

Weld-in Installation

The weld in installation is the strongest installation into the hull and the
propulsor is an integrated part of the hull structure. The propulsor is
usually installed in two parts – the upper part, that is welded into the hull,

from above and the lower part from below the hull.

Fig. 5.

Weld-in installation: 1) the upper part is installed from above; 2) the upper part is welded at

the hull bottom and at the top flange, the lower part is brought into place from below the

hull; 3) the lower part is bolted to the upper part

Small Bolt-in Mounting Cone

When the propulsor is installed using the small mounting cone there is no
need to compromise hull strength around the propulsors, as the needed

openings in the hull can be kept to a minimum. Mounting cone installation
allows the propulsor to be installed in one piece from below or in two
pieces, upper gearbox from above and lower gearbox from below.

Fig. 6.

Small bolt-in mounting cone installation – in one piece: 1) the propulsor is brought below

the hull; 2) the propulsor is turned in way of the trunk and lifted into position; 3) the

propulsor is bolted into the trunk and the clutch assembly is installed







background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels

7


Fig. 7.

Small bolt-in mounting cone installation – in two parts: 1) the upper part is installed from

above, the lower part is brought into place from below the hull; 2) the upper part is bolted

into the hull; 3) the lower part is lifted into place and bolted to the upper part

Large Mounting Adapter

The use of a large mounting adapter allows the complete propulsor to be
lifted onboard in one piece. Often it is possible to do so even with the
vessel in water. This feature also enables the propulsor to be lifted off the

vessel for repairs and maintenance without dry-docking the vessel. See
fig. 8.

Fig. 8.

Large bolt-in mounting adapter installation: 1) the propulsor is lifted onboard; 2) the

propulsor is bolted to the trunk flange; 3) the deck hatch is bolted or welded into place

above the propulsor


14.

Distance between the Propulsor Units

In order to improve the overall performance, especially the
manoeuvrability of the vessel, the unit should be installed as far from each

other as possible. Minimum recommended distance between the units is
the unit turning diameter + 500 mm.

background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels

8

It is also recommended that the distance from the vessel side to the unit
centre is more than ½ unit turning diameter + 500 mm, in order to
prevent the units from touching jetties or other vessels when heeling.

min.

500 mm

min.

500 mm

Fig. 9.

Minimum distance between the units as well as between the side and the units are 500 mm

The beam of the vessel should, of course, be designed to allow the
required units to be installed accordingly.

15.

Propulsor Tilting and Heeling

The propulsor units need not to be installed vertically, but can be both
tilted (longitudinally) and heeled (laterally) in order to achieve some

benefits. Typically the units are tilted, up to 3º …5º in order to decrease
the cardan shaft angles on the intermediate shaft. To achieve same
lifetime expectancy / maintenance interval for all the cardan bearings the
prime mover should be tilted correspondingly. Note that some main engine

manufacturers have strict maximum angles for engine tilt, thus also
restricting the propulsor tilt angle.

A tilt of 2º …3º is in any case recommended to improve the hydrodynamic

efficiency of the installation.

If the main engines need to be installed close to each other, the distance
between the propulsors can be maximized (and performance improved) by

a) using oblique intermediate shaft angles – note maximum cardan shaft
angles! – and/or b) by heeling the units outwards. Maximum heel angle is
to be determined case by case.

background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels

9

tilt 3

o

heel 5

o

heel 5

o

Fig. 10. The units can be installed either tilted or heeled, or both. A tilt of 2º …3º is recommended to

optimise the water inflow to the propeller.


INTERMEDIATE SHAFTS

16.

Shaft Arrangements

The power train between the prime mover and the propulsor is by an

intermediate shaft. Depending on application and installation there are
several different possibilities for the intermediate shaft layout. In the
shortest case the shaft is only a tooth coupling and a flexible coupling

between the engine flywheel and the propulsor input flange.

In order to prevent the forces from the propulsor and the shafts to
damage the prime mover a flexible coupling has always to be installed
between the engine flywheel and the intermediate shaft package.

Tooth Coupling and Flexible Coupling

This is the shortest possible intermediate shaft installation, where the
shaft is a mere tooth coupling connected to the propulsor flange at one

end and to the flexible coupling on the prime mover flywheel.

Fig. 11. Using only a tooth coupling and a flexible coupling results in the shortest possible

intermediate shaft line arrangement

background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels

10

Stub Shaft

The next shortest intermediate shaft is a short, so called stub shaft. The
shaft should be equipped with a pair of bearings to take the gravity load of
the shaft and thus the shortest possible length is one that provides for

space for the bearings. The stub shaft is usually fixed by flanges to the
propulsor input flange and the flexible coupling on the prime mover
flywheel.

Fig. 12. The stub shaft arrangement is another very compact installation method.

Centalink

If a short shaft without bearings is preferred a possibility is to use a so-
called flexible shaft, e.g. Centalink, where the shaft (normally of tube
type) is integrated to torsionally stiff flexible elements at each end of the
shaft.

Carbon Fibre Shaft

A novel solution for straight shaft installations is to use a large diameter
hollow carbon fibre shaft, which requires no bearings. The use of a carbon

fibre shaft is feasible in vessels, where a straight steel shaft otherwise
would be used. The carbon fibre shaft will save weight and installation
work compared to a conventional shaft with bearings and bearing

foundations. The carbon fibre shaft is using the same flexible elements as
in the Centalink solution above. Maximum length of a single piece shaft is
approx. 8 m.

background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels

11

Fig. 13. The “flexible” shaft line arrangement – with no bearings – enables a fast and easy

installation of the intermediate shaft.

Single Cardan Shaft

If the engine is installed close to the same level as the propulsor and
rather close to each other a single cardan shaft can be used as the
intermediate shaft. In order not to damage the engine a stub shaft is

required, at least for power ratings above, say 600 kW. The stub shaft
requires a pair of bearings capable of taking axial forces and to take the
shaft weight. Note that the cardan shaft cannot be used with very small
angles; a minimum of 1º is normally required to ensure that the joint

bearings are moving.

Fig. 14. Sometimes it is feasible to use the single cardan shaft solution. Also this installation will

require a stub shaft and flexible coupling.

background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels

12

Typical Intermediate Shaft

The typical intermediate shaft arrangement on an offshore support vessel
with direct diesel drive comprises cardan shafts and a rather long straight
shaft. Also this arrangement will require a stub shaft at the prime mover

end as well as a flexible coupling to save the prime mover from damage.

Fig. 15. The typical intermediate shaft comprise two cardan shafts with a long straight shaft in

between. At the prime mover end a stub shaft and a flexible coupling will be required


17.

Shaft Angle

The height difference between prime mover flywheel and azimuth
propulsor input flange should be kept as small as possible. Maximum
allowed height is dependent on distance between the prime mover and

cardan shafts chosen.

Maximum usable angle is approximately 7.5º per joint, due to cardan shaft

rpm, bearing lifetime, and vibration. Use of the maximum angle has to be
separately checked. In order to avoid later problems, maximum
recommended angle is 6 ...6.5º per joint.

max. 15

o

Fig. 16 The angle of the intermediate shaft should be minimized - maximum recommended angle is

usually 15º


background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels

13

18.

Cardan Joint Phasing.

In order to improve the performance and lifetime of the cardans as well as
to reduce the risk for vibration problems on the intermediate shaft, the

cardan shaft joints at each end of the intermediate shaft should be in the
same phase for an odd number of shaft bearings and in different phase for
an even number of bearings.

Fig. 17 Cardan shaft phasing. Above with same phase for intermediate shaft with odd number of

bearings. Below with different phasing for intermediate shafts with even number of

bearings.

CONTROL LAYOUT

19.

Control Layout

The azimuth propulsor controls should be positioned in a way to enable the

helmsman to easily concentrate on the operations, not on how to handle
his vessel. The optimum solution is to place the control cabinets on each
side of the steering position. The distance between the cabinets should

allow a helmsman’s chair to fit between them, but the distance between
the propulsor controls should be kept between 55 cm and 65 cm.

55 ...65 cm

Fig. 18 A typical single steering position layout with a “walk-through” control layout. The distance

between the azimuth propulsor controls should be 55-65 cm.

background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels

14

PROPULSOR ROOM SPACE

20.

Propulsor Room Space

There should be enough internal height in the propulsor room to allow for
installation as well as maintenance of the units. Recommended is a
minimum height of 200 …300 mm above the units. A separate bolted-on

maintenance hatch can be installed above the unit if enough height is
otherwise not available. The Steerprop Azimuth Propulsors are designed to
be as short as possible, i.e. the internal height requirement is minimised
and thus the units are suitable also for very low deck heights.

MAIN ENGINE

21.

Main Engine Choice

The propeller and main engine should be chosen together in order to
ensure that there is enough of torque available even in conditions with
negative water inflow to the propellers. If not, there is risk for engine

overload and stalling in a critical phase of ship handling.

EXTERNAL CONNECTIONS

22.

Electricity

The Steerprop propulsors require an external feed of electricity for the
control, for the display and emergency steering as well as for the alarms.

The system is of 24 V DC type and the electricity is required to the control
cabinets, normally situated in the engine room.

The electricity demand is approx. 300 W for the primary steering, approx
100 W for the emergency steering and display and approx. 50 W for the

alarms.

The electricity feed is required to be continuous with a battery backup.

23.

Cabling

The controls will require three cables for each propulsor to be drawn
between the wheelhouse control stand and the engine room / propulsor

room. There is one cable for the main control, one for the emergency
control and display and on cable for the alarms.

background image

2/2001

April 2001

DESIGNERS’ CHECKLIST Nº 2

Offshore Support Vessels

15

24.

External Tanks

The Steerprop propulsors require a shaft seal tank of approx. 20 litre
capacity for each propulsor to be installed in the propulsor room. For units

with hydraulic steering a hydraulic unit - comprising required tanks
(capacity 60 …100 litres), filters, valves and coolers – need to be installed
close to each propulsor. The unit is delivered as a part of the Steerprop
delivery. The hydraulic unit need to be connected to the propulsor with 6

pipes between the propulsor and the hydraulic unit and 5 pipes between
the hydraulic unit and the propulsor.

25.

Cooling

The Steerprop units are equipped with coolers that need to be connected
to a cooling water system (fresh or sea water) the water capacity need is

100 …200 litres/min, depending on propulsor size and power. These values
are for an input water temperature of +32º C.

background image





























Steerprop Ltd.

P.O. Box 217

FIN-26101 RAUMA
Finland


e-mail: steerprop@steerprop.com

phone: +358 2 8387 7900
fax:

+358 2 8387 7910

w w w . s t e e r p r o p . c o m


Wyszukiwarka

Podobne podstrony:
Palladium Checklist
Cessna 172XP Small Checklist
checklist forestry horticulture
checklist radio tv theatre events
checklist undertaker
SSAS TEST Checklist, Akademia Morska (Szczecin), Semestr V, Inspekcje Morskie
checkliste
checklist asphalt work
domain controller checklist OMO5UL6LZCXY75RCL5UP32W2O5HKIIJOVHWHHYY
PBO TD02 C01 Shipmaster Monthly Checklist
Checklist 7
A Surgical Safety Checklist to Reduce Morbidity and Mortality in a Global Population
Pilot Embarkation Checklist
Checklist 1
infrastructure server checklist Y67PKVZL2TBVBV3Z3IYCFN45BUIMBB2GKO4GCXY
STET SSP Checklist Ver2
CHECKLISTA
checklist sport centres
checklist1[1]

więcej podobnych podstron