Micro Application Example
Automatic Transfer switch
with LOGO! and SENTRON circuit breaker
Micro Automation Set 29
Table of contents
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
2/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
Note
The Micro Automation Sets are not binding and do not claim to be complete
regarding the circuits shown, equipping and any eventuality. The Micro
Automation Sets do not represent customer-specific solutions. They are only
intended to provide support for typical applications. You are responsible for
ensuring that the described products are correctly used. These Micro
Automation Sets do not relieve you of the responsibility of safely and
professionally using, installing, operating and servicing equipment. When using
these Micro Automation Sets, you recognize that Siemens cannot be made
liable for any damage/claims beyond the liability clause described.
We reserve the right to make changes to these Micro Automation Sets at any
time without prior notice. If there are any deviations between the
recommendations provided in these Micro Automation Sets and other Siemens
publications – e.g. catalogs – the contents of the other documents have priority.
Warranty, Liability and Support
We accept no liability for information contained in this document.
Any claims against us – based on whatever legal reason – resulting from the
use of the examples, information, programs, engineering and performance data
etc., described in this Micro Automation Set shall be excluded. Such an
exclusion shall not apply in the case of mandatory liability, e.g. under the
German Product Liability Act (“Produkthaftungsgesetz”), in case of intent, gross
negligence, or injury of life, body or health, guarantee for the quality of a
product, fraudulent concealment of a deficiency or breach of a condition which
goes to the root of the contract (“wesentliche Vertragspflichten”). However,
claims arising from a breach of a condition which goes to the root of the contract
shall be limited to the foreseeable damage which is intrinsic to the contract,
unless caused by intent or gross negligence or based on mandatory liability for
injury of life, body or health. The above provisions do not imply a change in the
burden of proof to your detriment.
Copyright© 2007 Siemens A&D. It is not permissible to transfer or copy
these Micro Automation Sets or excerpts of them without first having prior
authorization from Siemens A&D in writing.
Table of contents
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
3/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
Foreword
Micro Automation Sets are fully functional and tested automation
configurations based on A&D standard products for simple, fast and
inexpensive implementation of automation tasks for small-scale
automation. Each of the available Micro Automatic Sets covers a frequently
occurring subtask of a typical customer problem in the low-end
performance level.
The sets help you obtain answers with regard to required products and the
question how they function when combined.
However, depending on the system requirements, a variety of other
components (e.g. other CPUs, power supplies, etc.) can be used to
implement the functionality on which this set is based. Please refer to the
respective SIEMENS A&D catalogs for these components.
The Micro Automation Sets are also available by clicking the following link:
Table of contents
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
4/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
Table of contents
Wiring plan: Uninterruptible power supply with battery and change-over
Wiring plan: LOGO! Basic with expansion module DM8 and digital monitoring
Hardware and Software Components ......................................................... 12
Transfer switch process in automatic operation.............................................. 18
Depictions on the display of the LOGO! logic module .................................... 25
Configuring the Startup Software ............................................................... 27
Power supply and emergency power supply .................................................. 29
Scenario 1: AUT – short time grid failure ....................................................... 33
Scenario 2: AUT - Grid failure without procedure error when generator is
Scenario 3: AUT - Grid failure with procedure error when generator is
Scenario 4: AUT - Grid failure with subsequent grid return during generator
Table of contents
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
5/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
Scenario 5: MAN – Manual mode circuit breaker NET ................................... 43
Scenario 6: MAN – Manual mode circuit breaker GEN................................... 44
Scenario 8: SERVICE – Service operation ..................................................... 45
Fields of Application and Benefits
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
6/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
1
Fields of Application and Benefits
1.1 Automation
Task
On the event of a power failure in a shopping center the emergency lights and
other devices important to maintain the infrastructure are to be powered by a
generator.
A monitoring sensor is to be used to monitor the availability of the current network.
If it detects a power failure, a control unit requests power from the generator.
If a further monitoring sensor informs the control unit about the availability of the
generator current, it should trigger the network-circuit breaker to cut the main circuit
of the shopping center from the public grid.
After the power was cut from the public grid, the emergency power network of the
shopping center is to be connected to the generator.
This state is to be maintained until the first monitoring sensor signalizes that the
public grid is available again. As a result the control unit should then cut the circuit
breaker responsible for the emergency power supply from the emergency power
network of the shopping center.
After a successful disconnection from the emergency power network, the control
unit should switch the network circuit breaker on in order to supply the shopping
center with current from the public grid again. If this procedure is finished, the
control unit informs the generator to stop operation.
In order to guarantee a constant availability of the generator, its functionality has to
be checked once a month. To do so, the control unit should be able to switch the
network circuit breaker on/off in the manual mode using push buttons.
A mechanical interlock avoids the two circuit breakers being switched on at the
same time.
Figure 1-1
•
Generator
Shopping center
Control unit
Control unit
Fields of Application and Benefits
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
7/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
1.2
Automation solution Set 29
One circuit breaker of the type VL 160N connects the public grid to the main circuit
and one connects it to the emergency power system of the shopping center,
respectively.
Using the SIRIUS monitoring relay the availability of the three phases of the public
grid and of the emergency power system is monitored.
The LOGO! logic module disconnects the circuit breaker from the public grid if the
SIRIUS monitoring relay detects a phase error or a failure. It then triggers the
generator to switch on.
If the availability of the generator grid is confirmed by the SIRIUS monitoring relay,
the LOGO“ logic module cuts the circuit breaker to the generator grid.
If the SIRIUS monitoring relay signalizes that the public grid is available again, a
switch-back to the public grid and the switching off of the generator is triggered by
the LOGO! logic module.
The SITOP DC-UPS-MODULE ensures that the LOGO! logic module can operate
while switching between public grid and generator grid is carried out.
For maintenance purposes a knob switch is used to switch between automatic and
manual mode. Using a further knob switch, the circuit breaker on the one hand to
the public grid or on the other hand to the generator grid can be selected. Using a
push button it can be switched on or off.
Figure 1-2
Grid
Circuit breaker VL160 (Grid)
SITOP
Power supply
SITOP UPS DC24V
SITOP Batt. module
Circuit breaker VL160 (Generator)
2
3
4
5
LOGO! Logic module
7
4
1
5
Generator
1
2
3
4
7
10
G
1
LOGO! Expansion module
8
Knob switch
9
Buttons
10
SIRIUS Grid monitoring relay
11
9
I
II
0
I
II
0
8
s
13NO
21NC
31NC
21NC
A1+
DC 24V
14NO
22NC
32NC
44NO
A2-
6
11
SIRIUS
Contactor
6
Fields of Application and Benefits
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
8/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
1.3 Application
Areas
Industry
• Production lines for continuous production (foundries, chemical
processes, etc.)
• Engine rooms on ships
• Important additional equipment for thermal power plants
Infrastructure
• Docks and railway systems
• Airport
lighting
• Monitoring systems for military bases
Building technologies
• Operating rooms in hospitals
• Safety devices for high-rise buildings
• Computer rooms (banks, insurance companies, etc.)
• Lighting systems for shopping centers
1.4 Benefits
• The automatic transfer switch ensures a continuous power supply in
case of a power failure.
• The continuous grid monitoring is performed by the SIRIUS 3UG4
monitoring relay. The transfer operation is reliably controlled by the
LOGO! logic module
• The high demand of the transfer switch is implemented by the motor
driven SENTRON circuit-breakers.
• Safety – provided by the continuous power supply in case of a power
failure.
• Saving of time – by the automatic transfer switch in case of a power
failure and by the automatic resetting on the power return, service
engineers do not have to intervene.
• Optimum power management – by the option of power shedding when
switching to emergency power supply.
Wiring diagrams
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
9/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
2 Wiring
diagrams
2.1
Wiring plan: Uninterruptible power supply with battery and
change-over contactor of the supply mains
Figure 2-1
1
A1
A2
A3
L+
M
21 13 31 43
22 14 32 44
R3
A1
A2
R1\L1(4)
R2\L1(4)
R1\N(1)
R1\N(1)
A5\K14
L1
L2
L3
N
PE
L1
L2
L3
N
PE
Gr
id
G
ener
ator
SI
7.
5A
Sitop Smart
Sitop UPS
Sitop battery
M
L+
L+ M
X1.1
X1.2
X1.3
X1.4
X1.5
X1.6
X1.7
X1.8
The LOGO! Logic module is powered by an uninterruptible power supply
(UPS) (see “A1“and “A2“ in figure 2-1). While switching from grid to
generator and vice versa the battery buffers the LOGO! logic module.
The change-over contactor "R3“ connects the phase “L1” and the zero
conductor, depending on the availability of the generator between public
grid and generator grid, with the power supply “A1” and with the servo
motor of the circuit-breaker. As soon as the generator grid is available the
relay switches from the public grid to the generator grid.
Wiring diagrams
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
10/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
2.2
Wiring plan: LOGO! Basic with expansion module DM8 and
digital monitoring relay
Figure 2-2
R3\
14 (G
en
)
LO
GO
!
Lo
gi
c
m
od
ule
24V
DC
L1
I1
N
I3
I6
I2
I5
I7
Î4
I8
Q11
Q31
Q12
Q22
Q21
Q32Q41Q42
LO
GO
!
Lo
gi
c
m
od
ul
e
DM
8
L1
I1
N
I3
I2
Î4
Q11
Q31
Q12
Q22
Q21
Q32Q41Q42
L+
M
L1
L2
L3
22
24
21
12
14
11
S
IRI
US
Mo
n
ito
rin
g
re
la
y
R2\
S
2B
R
1
\A
S
.X
2
.6
(
tr
igg
e
re
d
)
R
1
\H
S
.X
2
.4
(
c
lo
s
e
d
)
A6
A7
A4
Gr
id
:L
1
Gr
id
:L
2
Gr
id
:L
3
R3\
22 (Net
z)
R1
\S
2
B
R
2
\H
S
.X
2
.4
(
c
lo
se
d
)
L1
L2
L3
22
24
21
12
14
11
S
IRI
US
Mo
n
ito
rin
g
re
la
y
A5
Ge
n
:L
1
Ge
n
:L
2
Ge
n
:L
3
R3\A1
AC
K
S1.S2
A
uto
M
an
S
erv
S1
Ö1
S2
Ö2
S1
Net
Gen
0
S1
Ö1
S2
S2
Ö2
S2.S2
R
1
\H
S.
X2.
1
S4
4
S3
3
2
S4
1
Knob switch
Buttons
R1\
S
A
:1.
\X
1.
1
R2
\H
S
.X
2
.1
St
a
rt
:G
e
n
\A
1
2\
I0
.7
R2\
S
A
:1
.X
1
.1
4
S5
3
R
2
\A
S.
X2.
6
(t
ri
g
g
er
ed
)
S1.S1
S5
A
u
to
M
ode
Of
f
S3
On
S2.S1
M
a
n
u
a
l Gr
id
M
a
nua
l G
e
n
On
Off
Ack
A2
\X
2
.9
A2
\X
2
.1
0
The transfer switch is controlled by a LOGO! logic module “A1“ and by an
expansion module DM8 “A2“. The SIRIUS monitoring relay monitors the
availability of the public grid or of the generator grid, respectively. Both
monitoring relays transmit the state via a digital signal to the LOGO! logic
module.
The knob switch “S1“ is responsible for selecting the operation mode. Using
this switch the operation modes “automatic” and “manual” can be selected.
If the “manual“ mode is selected, the knob switch “S2” is used to address
the circuit-breaker either to the public grid or to the generator grid. The
push button “S3“ is then used to switch the selected circuit-breaker on, the
push button “S4“ is used to switch it off again..
An error triggered by exceeding the timeout counter for instance, has to be
acknowledged by the push button “S5”.
Wiring diagrams
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
11/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
2.3
Wiring plan: Circuit breaker
Figure 2-3
R2\HS.X2.2
A7\Q32
Legend:
SA = Circuit switch
HS = auxiliary switch
AS = alarm switch
R3\K22
L1
L2
L3
N
PE
L1
L2
L3
N
PE
Gri
d
Gen
e
ra
to
r
1
2
3
4
5
6
HS.X2.1
HS.X2.2
HS.X2.3
HS.X2.4
AS.X2.5
AS.X2.6
SA:1(X1.1)
SA:2(X1.2)
R1
PE(X20.5)
S2A(X20.2)
L2-(X20.1)
L2+(X20.4)
S2B(X20.3)
M 24V
R3\K32
A6\Q12
A6\Q22
R2\S2A
A6\I7
L+ 24V
A6\I3
R1\HS.X2.2
A6\Q32
R3\K22
1
2
3
4
5
6
HS.X2.1
HS.X2.2
HS.X2.3
HS.X2.4
AS.X2.5
AS.X2.6
SA:1(X1.1)
SA:2(X1.2)
R2
PE(X20.5)
S2A(X20.2)
L2-(X20.1)
L2+(X20.4)
S2B(X20.3)
M 24V
R3\K32
A6\Q42
A7\Q22
R1\S2A
A6\I8
L+ 24V
A6\I4
The circuit breakers are operated via the LOGO! logic module. In order to
avoid both circuit breakers to be switched on at the same time, the digital
activation command has been looped to the circuit breaker “R1” (“R2”)
using an auxiliary contact to the circuit breaker “R2” (“R1”).
The servo motors of the circuit breakers are powered analogically to the
UPS via the currently available grid using the change-over contactor “R3”.
This enables both circuit breakers to be controllable even in the case of a
power failure in one of the grids.
Hardware and Software Components
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
12/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
3
Hardware and Software Components
3.1 Transfer
switch
Products
Table 3-1
Component
No.
MLFB/Order number
Note
LOGO! logic module
(12/24RC)
1 6ED1052-1MD00-0BA5
LOGO! DM8 24R
EXPANSION MODULE
1 6ED1055-1HB00-0BA0
SENTRON circuit breaker
VL 160N
2 3VL2705-1DC33-8CD1
Motorized operating
mechanism with spring
energy store
2 3VL9300-3MQ00
SIRIUS monitoring relay
3UG4
2 3UG4617-1CR20
SITOP SMART, closed-loop
controlled load power supply
unit
1 6EP1333-2BA01
SITOP DC UPS MODULE
24V/6A
1 6EP1931-2DC42
SITOP battery model 24V /
1.2 AH
1 6EP1935-6MC01
SIRIUS contactor relay
1
3RH1122-1BB40
RC element
1
3RT1916-1CB00
Selector switch
knob, I-0-II, latching
2 3SB3210-2DA11
Push button green, 1NO
1
3SB3202-0AA41
Pushbutton yellow, 1NO
1
3SB3202-0AA31
Push button red, 1NC
1
3SB3203-0AA21
Hardware and Software Components
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
13/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
Accessories
Table 3-2
Component
No.
MLFB/Order number
Note
LOGO! PC cable
1
6ED1057-1AA00-0BA0
Configuration software/tools
Table 3-3
Component
No.
MLFB/Order number
Note
LOGO! SOFT COMFORT V5.0
SP5, SINGLE LICENSE
1 6ED1058-0BA01-0YA0
Accessories for Live-Demo
Table 3-4
Component
No.
MLFB/Order number
Note
Automatic cut-out
2
5SX2316-5
• 3-pin
• 16A
Lamp for connection to
AC 230V
2
Function Principle
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
14/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
4 Function
Principle
4.1
Circuit breaker with motor drive
Overview
The circuit breaker comprises a 3-phase switch which connects the grid to
the load.
Figure 4-1
1
2
3
4
5
6
Shunt trip
Motorized operating
mechanism with spring
energy store
Auxiliary switch
„NO“
Auxiliary switch
„NC“
Alarms switch
„NO“
Main switch
In the present case the circuit breaker comprises the following components:
Table 4-1
No.
Component
Note
1. Circuit breaker unit
2. Motorized operating
mechanism with spring
energy store
The motorized operating mechanism with spring
energy store is mounted on the circuit breaker
and is used to open and to close it. It has a
manual and an automatic mode. The mode can
be selected using the slider on the motor drive.
3. Shunt
trip
This additional module is placed in the right-
hand slot of the circuit breaker. The relay of the
shunt trip can be accessed by the LOGO! Logic
module, for instance. If the current flow of the
Function Principle
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
15/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
No.
Component
Note
shunt trip is interrupted, the triggering
mechanism of the circuit breaker is activated
and it takes the position “triggered”.
4. Auxiliary
switch
This installation set comprises a NC and a NO.
The position of the auxiliary switches represents
the state of the circuit breaker.
• The NO-state provides the LOGO! logic
module with the current position of the
circuit breaker.
• The NC is used for locking purposes in
order to ensure both circuit breakers not to
be switched on at the same time.
5. Alarm
switch
This installation set comprises a NO. If this
alarm switch is closed it sends a signal to the
LOGO! logic module saying that the circuit
breaker has taken the switch position
“triggered”.
The 3 states of the circuit breaker
The circuit breaker can be in 3 different positions
Table 4-2
No.
Switch position
1. Closed
In this position the contacts of the circuit breaker
are closed The load is connected to the grid and
the current can flow.
2. Open
In this position the contacts of the circuit breaker
are open. The load is disconnected from the grid
and the current cannot flow.
3. Triggered
In this position the contacts of the circuit breaker
are open. The switch position “triggered“ can be
attained either with a mechanism directly activated
on the circuit breaker, or it is triggered via an
optional module (e.g. shunt trip).
After the circuit breaker was brought into the
“triggered” switch position, it cannot immediately
be switched on again. In order to switch the circuit
breaker on again, in other words to close it, it first
of all has to be opened. This is to avoid the circuit
breaker to be switched on after an error (e.g.
short-circuit after in public mains) without having
corrected the error.
Function Principle
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
16/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
4.2
SIRIUS Monitoring relay
The monitoring relay 3UG4617 monitors the phase sequence and a phase
failure of one of the phases. It furthermore monitors if a set voltage is
undershoot or exceeded and if a set asymmetry value is exceeded and it
monitors the difference between the highest and lowest phase voltage in
relation to the highest phase voltage (Ux-y max - Ux-y min) / Ux-y max in a
3-phase grid.
If the correct phase sequence at the terminals L1-L2-L3 is applied, the relay
A4 or A5 picks up. This is depicted on the display with a relay symbol. In
case of an incorrect phase sequence the relay will not pick up. In this case
no error message will occur on the display but the relay symbol will not
show up! If the monitored voltage (Ux-y) is higher then the specified lower
voltage value (U|) and lower then the specified higher voltage value (Ux),
meaning within the voltage limits, and if the grid voltage (Asy) is lower then
the specified value, the relay A4 or A5 (contact 11-12-14) will pick up
approx. 50ms after the reaction of A4 or A5, respectively. For the
3UG4617 the display shows the current voltage between lines L1 and L2.
The following grid faults are depicted on the display as diagnosis message
with flashing symbols:
• Failure of one phase (3UG4618 or failure of the zero conductor).
Symmetric (all 3 phase voltages / star voltages at the same time)
• Asymmetric (only one phase voltage / star voltage) undershoot or
exceeding of the voltages specified in the menu. Exceeding the
asymmetry specified in the menu.
In case of a phase failure the relay A4 or A5 will immediately be released.
In case of the errors voltage undershoot, voltage exceed or asymmetry
exceed the relay A4 or A5 will be released after the specified fault display
relay time (Del).
Function Principle
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
17/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
4.3 SITOP
UPS
Function
In combination with the SITOP battery modules the DC-UPS-module 6 is
used to buffer parts of the load current (max. 6A) of 24V-load current
supplies of the SITOP series.
The loads to be buffered are powered by the voltage of input using the
outputs “Output L+” and “Output M” of the DC-UPS module. If the 24V
DC-supply voltage fails or if the voltage drops below the specified cut-in
threshold, the loads are powered by switching on the battery module which
is kept in full charge in stand-by parallel operation.
Adjustable parameters
Figure 4-2
+2V
+1V
+0,5V
+1V
+1V
+0,5V
+0,2V
+0,2V
+0,1V
0,2A / 0,4A
Ladestrom
(charging current)
eingestellte Zeit / max. Zeit (set time / max.)
+320s
+160s
+ 80s
+ 40s
+ 20s
+ 10s +5s fest eingestellt (fixed)
Unterbrechung output (disconnection)
Betriebszustand Akku On / Off
(operating state battery)
Zuschaltschwelle
(cut-in threshold)
+22V fest eingestellt (fixed)
Ladeschlussspannung
(end-of-charge voltage)
+ 26,3V fest eingestellt (fixed)
Pufferzeit
(buffering time)
According to the DIP-switches depicted in figure 4-2 the following
parameters can be adjusted:
• Battery cut-in threshold
• End-of-charge
voltage
• Charging
current
• Buffering
time
Function Principle
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
18/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
Cut-in threshold
If the input voltage drops below the specified value of the cut-in threshold,
the UPS-module will switch to backup power operation. The loads are then
only powered by the battery module.
End-of-charge voltage
The end-of-charge voltage depends on the type of the battery used and of
the temperature the battery is exposed to. For detailed information on the
adjustment please refer to the manual.
Charging current
The battery module is charged with constant current until the specified end-
of-charge voltage is reached. The charging process is then stopped.
Buffering time
The buffering time can be set in 10 second steps from 5 seconds to 635
seconds. Using switch 1 (specified time/maximum time) you can select if
the backup power operation is stopped when the specified time is reached
or when the exceed discharge threshold of the battery (= maximum
buffering time) is reached.
4.4
Transfer switch process in automatic operation
Status diagram
The status diagram shows the behavior of the control program in automatic
mode. T*.* are the switch-over conditions that have to be fulfilled in order to
get from one phase P* to the next one.
Function Principle
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
19/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
Figure 4-3
Grid is
available
P1
Gen is
available
P2
switch Net
to Gen
P3
switch Gen
to Net
P4
error
recognized
P5
Switch to Net
and Gen
triggered
P6
T
1.1
T
1.2
T
4.1
T
4.2
T
3.1
T
3.2
T
2.2
T
2.1
T
5
start, Auto
error-
acknowledgeme
nt
P0
T
1.1
T
0.1
T
2.2
T
0.2
T
6.1
Table 4-3
Name of condition
Condition
1.
T
0.1
• Public grid is available
• Grid-circuit breaker closed
• Generator-circuit breaker open
2.
T
0.2
• Grid
failed
• Grid-circuit breaker open
• Generator-circuit
breaker
closed
3.
T
1.1
• Public grid failed
4.
T
1.2
• Grid-circuit breaker in “triggered”
• Generator not available
5.
T
2.1
• Public grid is available again
6.
T
2.2
• Generator-circuit breaker in “triggered”
• Public grid not available
7.
T
3.1
• Switching operation from “public grid” to
“generator grid” successfully carried out
8.
T
3.2
• Switching operation from “public grid” to
“generator grid” could not be carried out
within monitoring time
9.
T
4.1
• Switching operation from “generator” to
“public grid” successfully carried out
Function Principle
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
20/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
Name of condition
Condition
10.
T
4.2
• Switching operation from “generator” to
“public grid” could not be carried out within
monitoring time
11.
T
5
• At least one error pending
12.
T
6.1
• All errors acknowledged
• All
errors
corrected
Switching from public grid to generator grid
The switching process is based on the status diagram from figure 4-1. The
application is in state “P1” and has the following basic conditions:
• Selector switch for operation mode “S1”: “Automatic”
• Circuit breaker switch “S2”: “0“
• Public grid connected to load
• Generator is switched off
• Locking switch of both circuit breakers is in “auto” position
Switching into state „P3“ is effected, if the SIRIUS monitoring relay „A4“
sends a message to the LOGO! logic module stating that the public grid
has failed for at least 10 seconds. The LOGO! logic module then switches
the grid circuit breaker „R1“ to the state „triggered“ and, in doing so,
interrupts the connection between load and public grid. An inquiry in form of
a digital signal is simultaneously sent to the generator. If the SIRIUS
monitoring relay „A5“ transmits the information on the availability of the
generator grid to the LOGO! logic module “A6” the generator circuit breaker
“R2” switches from ”triggered” to “open” (motor loads the spring force
storage device). Then the circuit breaker „R2“ is closed (spring force
storage device is unload). Now a connection between generator grid and
partial load (loads for emergency light, lifts, etc.) is established.
After the successful switch to the generator grid the state “P2” is attained.
Here the SITOP DC-UPS-MODULE “A2” ensures that the LOGO! logic
module “A6” is supplied with power even during the switching process from
public grid to generator grid.
If the switching process could not be carried out during the monitoring time
of 30 seconds, error state “P5” is attained. This situation is depicted on the
display with an error message. For safety reasons the LOGO! logic module
“A6” switches both circuit breakers “R1” and “R2” to the state “triggered”.
This means that the load is disconnected from the public and from the
generator grid. State “P6” is attained.
Function Principle
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
21/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
Switch back from generator grid to public grid
The switching process is based on the status diagram from figure 4-1. The
application is in state “P2” and has the following basic conditions:
• Selector switch for operation mode “S1”: “Automatic”
• Circuit breaker switch “S2”: „0“
• Public grid is disconnected from load
• Generator is switched on and connected to partial load
• Locking switch of both circuit breakers is in “auto” position
Switching into state “P4“ is effected if the SIRIUS monitoring relay “A4“
sends a message to the LOGO! logic module stating that the public grid
has returned for at least 10 seconds. The LOGO! logic module then
switches the generator circuit breaker “R2“ to the state „triggered“ and, in
doing so, interrupts the connection between partial load and generator grid.
After successful disconnection the LOGO! logic module effects a state
change of the grid circuit breaker “R1” from “triggered” to “open” (motor
loads spring force storage device). Then the circuit breaker “R1“ is closed
(spring force storage device is unload). Now the connection between the
public grid and the load is re-established.
After the successful switch to the public grid state “P1“ is attained again.
Here the SITOP DC-UPS-MODULE “A2” ensures that the LOGO! logic
module “A6” is supplied with power even during the switching process from
public grid to generator grid.
If the switching process could not be carried out during the monitoring time
of 30 seconds, error state “P5” is attained. This situation is depicted on the
display with an error message. For safety reasons the LOGO! logic module
“A6” switches both circuit breakers “R1” and “R2” to the state “triggered”.
This means that the load is disconnected from the public and from the
generator grid. State “P6” is attained.
Function Principle
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
22/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
4.5 Service
functions
Manual control of the circuit breakers via application buttons
For maintenance purposes both circuit breakers can manually be opened
or closed. To do so the following settings have to be carried out.
• Operation mode switch “S1” “Manual”
• Circuit breaker switch “S2”: “Public grid” or “Generator”
The closing of the circuit breaker is effected by pushing the green push
button “S3”, if the spring of the motor has been tensioned in advance. If the
spring has not been tensioned, the circuit breaker remains in “triggered”
state, meaning no connection between load and power supply is
established.
The opening of the circuit breaker selected and the winding up of the
tension spring is carried out after the red button “S4” was pushed.
Service with onboard-control elements of the circuit breaker
If the selector switch is set to the “Off”-position, all outputs of the LOGO!
logic module are switched to “0”.
For the purpose of a function test of the circuit breaker it can also be
directly controlled via the control elements.
• In order to ensure that the LOGO! Logic module does not carry out
changes in the control outputs while the onboard service, the operation
mode switch “S1” has to be set to “0”
• The locking switch of the circuit breaker has to be set to “manual”
according to figure 4-7
Pushing the red onboard button “ON” effects the closing of the circuit
breaker if the spring was tensed before. If the spring is untensed, the circuit
breaker remains in the “triggered“ state.
Pushing the black onboard button “OFF” effects the opening of the circuit
breakers and the tensing of the spring.
Note
After the service operation has been finished the locking switch of the
circuit breaker has to be reset to “auto” again.
!
DANGER
Do not use this function if the public grid and the generator grid are
both available at the same time, as the circuit breakers do not
interlock each other when switched on. If both grids are connected
to the load at the same time, a short-circuit can occur!
Function Principle
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
23/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
4.6
Overview on the operator functions
Control elements
Figure 4-4
ACK
S1
S2
S5
S4
S3
A
uto
S
erv
M
an
N
etz
0
G
en
CLOSE
OPEN
Table 4-4
No.
Switch
Function
1.
S1
Operation mode selector switch for selecting the
operation modes automatic and manual
2.
S2
Circuit breaker selector switch for selecting the circuit
breaker
3.
S3
Push button for manual closing of the selected circuit
breaker in manual mode
4.
S4
Push button for manual opening of the selected circuit
breaker in manual mode
5.
S5
Push button for acknowledging an error message in
automatic mode
Automatic mode
Figure 4-5
Automatik
Manuell
Service
Automatikbetrieb
Öff. Netz
Generator
0
Funktion
Betriebsart
Wahlleistungsschalter
Taster
S1
S2
Function Principle
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
24/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
Manual switch on/off of circuit breaker
Figure 4-6
Manual
Switch public grid
on
Manual
Switch public grid
off
Manual
Switch generator
grid on
Manual
Switch generator
grid off
Function
Mode
Circuit breaker selector switch
Button
Automatic
Manual
Service
S1
Automatic
Manual
Service
S1
Automatic
Manual
Service
S1
Automatic
Manual
Service
S1
Public
grid
Generator
0
S2
Public
grid
Generator
0
S2
Public
grid
Generator
0
S2
Public
grid
Generator
0
S2
S3
S4
S3
S4
Acknowledgement of errors
Figure 4-7
Fehler qu ittieren
Function
Bet rieb sa rt
Wahlleistung ss chalt e r
Tast er
S4
Automatic
Manual
Service
S1
Function Principle
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
25/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
Service functions via the onboard-control elements of the circuit breaker
Figure 4-8
Service mode
Public grid
Generator
0
Function
Operation mode
Circuit breaker selector switch
Button
Close circuit breaker
Open circuit breaker
Manual
Spring tension lever
Selector switch to
„manual“
Spring tensed
Spring untensed
Automatic
Manual
Service
S1
S2
4.7
Depictions on the display of the LOGO! logic module
Status display
Figure 4-9
Betriebsart: Automatik Manuell oder Service
0: Keine Spannung am öffentlichen Netz oder Generator
1: Spannung am öffentlichen Netz oder Generator
0: Leistungsschalter öffentliches Netz offen
1: Leistungsschalter öffentliches Netz geschlossen
0: Leistungsschalter Generator offen
1: Leistungsschalter Generator geschlossen
Function Principle
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
26/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
Display of the switching process
Figure 4-10
Switching process from phase P1 to P2 is running
Switching process from phase P2 to P1 is running
Error message in case of time violation
Figure 4-11
Fehlermeldung nach Zeitüberschreitung beim
Umschalten von Generator zum öffentlichen
Netz
4.8 Load
shedding
Load shedding means, in contrast to operation on the public grid, the load
on the generator has to be limited to a minimum. Such partial loads
comprise for instance the emergency lights, lifts, and other emergency
systems.
Configuring the Startup Software
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
27/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
5
Configuring the Startup Software
5.1 Preliminary
remark
For the startup we offer you software examples with test code and test
parameters as download. The software examples support you during the
first steps and tests with your Micro Automation Sets. They enable quick
testing of hardware and software interfaces between the products
described in the Micro Automation Sets.
The software examples are always assigned to the components used in the
set and show their basic interaction. However, they are not real applications
in the sense of technological problem solving with definable properties.
5.2
Downloading the startup code
The software examples are available on the HTML page from which you
downloaded this document.
Table 5-1
Nr.
File name
Content
1 Set_29_LOGO!_code.lsc
LOGO! Soft Comfort project
file for transfer switch
5.3 Configuring
Components
Note
It is assumed here that the necessary software has been installed on
your computer and that you are familiar with handling the software.
Configuring the Startup Software
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
28/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
5.3.1
Installing and wiring hardware
Table 5-2
No.
Instructions
Note
6. Install the single components onto a
control panel
7.
For wiring purposes lay channel ducts
8.
Wire the set as explained in chapter 2
9. For the wiring of the UPS to the battery
and change-over contactor of the supply
mains please refer chapter 2.1
1
A1
A2
A3
L+
M
21 13 31 43
22 14 32 44
R3
A1
A2
R1\L1(4)
R2\L1(4)
R1\N(1)
R1\N(1)
A5\K14
L1
L2
L3
N
PE
L1
L2
L3
N
PE
Gr
id
Ge
n
e
ra
to
r
S
I 7.
5A
Sitop Smart
Sitop UPS
Sitop battery
M
L+
L+ M
X1.1
X1.2
X1.3
X1.4
X1.5
X1.6
X1.7
X1.8
chapter 2.1
10.
For the wiring of LOGO! Basic to the
expansion module DM8 and to the digital
monitoring relay please refer to chapter
2.2
R
3
\14 (
G
en
)
L
O
GO!
Log
ic
m
odul
e
24V
DC
L1
I1
N
I3
I6
I2
I5
I7
Î4
I8
Q11
Q31
Q12
Q22
Q21
Q32Q41Q42
L
O
GO!
Log
ic
m
odul
e
DM
8
L1
I1
N
I3
I2
Î4
Q11
Q31
Q12
Q22
Q21
Q32Q41Q42
L+
M
L1
L2
L3
22
24
21
12
14
11
SI
R
IU
S
Mo
ni
to
rin
g
re
la
y
R2
\S
2
B
R
1
\A
S
.X
2
.6 (
tr
ig
g
er
ed
)
R
1
\H
S
.X
2
.4 (
c
lo
s
e
d)
A6
A7
A4
Ne
tz
:L
1
Ne
tz
:L
2
Ne
tz
:L
3
R
3
\22 (
N
et
z)
R1
\S
2
B
R
2
\H
S
.X
2
.4 (
c
los
e
d)
L1
L2
L3
22
24
21
12
14
11
SI
R
IU
S
Mo
ni
to
rin
g
re
la
y
A5
Ge
n
:L
1
Ge
n
:L
2
Ge
n
:L
3
R3\A1
AC
K
S1.S2
A
uto
M
an
S
erv
S1
Ö1
S2
Ö2
S1
Net
Gen
0
S1
Ö1
S2
S2
Ö2
S2.S2
R
1
\H
S.
X2
.1
S4
4
S3
3
2
S4
1
Knob switch
Button
R
1\
S
A
:1.
\X
1.
1
R
2
\H
S.
X2
.1
S
tar
t:
G
en
\A
12
\I
0
.7
R2
\S
A
:1
.X
1
.1
4
S5
3
R
2
\A
S
.X
2
.6 (
tr
igg
e
red)
S1.S1
S5
Au
to
M
o
d
e
Of
f
S3
On
S2.S1
M
a
nua
l N
e
t
M
a
nua
l G
e
n
On
Off
Ack
A2
\X
2
.9
A
2
\X
2.
10
chapter 2.2
11.
For the wiring diagram of the circuit
breakers please refer to chapter 2.3
R2\HS.X2.2
A7\Q32
Legend:
SA = Circuit switch
HS = Auxiliary switch
AS = Alarm switch
R3\K22
L1
L2
L3
N
PE
L1
L2
L3
N
PE
Gr
id
G
enerat
or
1
2
3
4
5
6
HS.X2.1
HS.X2.2
HS.X2.3
HS.X2.4
AS.X2.5
AS.X2.6
SA:1(X1.1)
SA:2(X1.2)
R1
PE(X20.5)
S2A(X20.2)
L2-(X20.1)
L2+(X20.4)
S2B(X20.3)
M 24V
R3\K32
A6\Q12
A6\Q22
R2\S2A
A6\I7
L+ 24V
A6\I3
R1\HS.X2.2
A6\Q32
R3\K22
1
2
3
4
5
6
HS.X2.1
HS.X2.2
HS.X2.3
HS.X2.4
AS.X2.5
AS.X2.6
SA:1(X1.1)
SA:2(X1.2)
R2
PE(X20.5)
S2A(X20.2)
L2-(X20.1)
L2+(X20.4)
S2B(X20.3)
M 24V
R3\K32
A6\Q42
A7\Q22
R1\S2A
A6\I8
L+ 24V
A6\I4
chapter 2.3
Configuring the Startup Software
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
29/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
No.
Instructions
Note
12.
First of all set all DIL-switches of the UPS
to OFF
+2V
+1V
+0,5V
+1V
+1V
+0,5V
+0,2V
+0,2V
+0,1V
0,2A / 0,4A
Ladestrom
(charging current)
eingestellte Zeit / max. Zeit (set time / max.)
+320s
+160s
+ 80s
+ 40s
+ 20s
+ 10s +5s fest eingestellt (fixed)
Unterbrechung output (disconnection)
Betriebszustand Akku On / Off
(operating state battery)
Zuschaltschwelle
(cut-in threshold)
+22V fest eingestellt (fixed)
Ladeschlussspannung
(end-of-charge voltage)
+ 26,3V fest eingestellt (fixed)
Pufferzeit
(buffering time)
chapter 4.3
13.
On the bottom DIL-switch of the UPS the
DIL-switches 1-5 have to be set ON
Now the buffering time is limited to 10
minutes. An unwanted discharge of the
battery is now avoided.
14.
On the bottom DIL-switch of the UPS the
DIL-switch 9 has to be set ON
5.3.2
Power supply and emergency power supply
Table 5-3
No.
Instructions
Note
15.
In this set the power supply and the
emergency power supply are carried out
by the same source. Wire the automatic
cut-out as depicted in the example.
NET
GEN
400V
Configuring the Startup Software
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
30/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
5.4 Preparations
• Supply is to be carried out by the public grid
Table 5-4
Nr.
Instructions
Note
1. Make sure the 400 volt supply is still
disconnected
.
2. Make sure both circuit breakers are in
“automatic” mode.
NET / GEN
3. Make sure that the flat fuse of the battery
is installed.
4. Switch knob switch „S1“ to „service” mode
and knob switch “S2” to “0”.
In this mode LOGO! Is disabled and no
unwanted actions will occur.
ACK
S1
S2
S5
S4
S3
A
uto
S
erv
M
an
N
etz
0
G
en
CLOSE
OPEN
5. Switch the automatic cut-out “ON” for the
grid and “OFF” for the generator.
NET
GEN
6.
Switch the 400 volt supply on.
The main circuit is available.
The input of the SITOP power supply is
supplied with 220 volt.
The SITOP supplies the LOGO! with 24
volt via the UPS.
The LOGO! runs up.
Now you are in “service operation”.
7. Switch to "automatic" operation mode
using the knob switch "S1".
ACK
S1
S2
S5
S4
S3
A
uto
S
erv
M
an
N
etz
0
G
en
CLOSE
OPEN
Configuring the Startup Software
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
31/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
Nr.
Instructions
Note
8. The LOGO! is now in normal operation,
meaning in mains operation with closed
circuit breaker for the mains circuit.
Supply is now carried out via the public
grid.
Live-Demo
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
32/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
6 Live-Demo
The functions and features of the Micro Automation Set are displayed in
form of an example application for better understanding.
If the components have been correctly configured as described in the
previous chapters, the program code can be tested.
6.1 Overview
of all scenarios
Table 6-1
Mode
Scenario
Note
AUT
Short time grid failure
Without generator request
AUT
Grid failure without procedure error
when generator is requested
Without generator start-up error
AUT
Grid failure with procedure error
when generator is requested
With generator start-up error
AUT
Grid failure with subsequent grid
return during generator request
Grid return during generator request
MAN
Manual mode circuit breaker NET
CB NET
MAN
Manual mode circuit breaker GEN
CB GEN
SERVICE Service operation
CB NET / CB GEN
Live-Demo
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
33/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
6.1.1
Scenario 1: AUT – short time grid failure
• Automatic
mode
• Supply is now carried out via the public grid.
• Public grid has short time grid failure ( < 3sec )
Table 6-2
No.
Instructions
Note
1. Supply is now carried out via the public
grid.
2. Switch the automatic cut-out “OFF” for the
public grid.
NET
GEN
< 3sec
3. The public grid drops and a voltage dip
monitoring (here 3 secs) is effected in the
LOGO!
< 3sec
4. Switch the automatic cut-out for the public
grid “ON” within the line monitoring time.
NET
GEN
< 3sec
5. The public grid returns and, due to the
short time of the voltage dip, no switch to
“emergency power operation” is effected.
Live-Demo
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
34/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
6.1.2
Scenario 2: AUT - Grid failure without procedure error when generator
is requested
• Automatic
mode
• Supply is now carried out via the public grid.
• Public grid fails for longer period of time
• Generator is now responsible for the task of the public grid
• The public grid returns
Table 6-3
No.
Instructions
Note
1. Supply is now carried out via the public
grid.
2. Switch the automatic cut-out “OFF” for the
public grid.
NET
GEN
3. The public grid drops and a voltage dip
monitoring (here 3 secs) is effected in the
LOGO!
> 3sec
4. If the voltage dip monitoring is exceeded,
the switching process to “emergency
power operation” is effected in the LOGO!
and is processed as follows:
The generator for the „emergency power
grid“ is requested.
A monitoring time for the generator return
is started.
The circuit breaker for the public grid is
opened.
Live-Demo
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
35/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
No.
Instructions
Note
5. The generator has to announce its
availability for emergency power
operation within this monitoring time (here
60 seconds) (simulated by switching on
the automatic cut-out “GEN”).
NET
GEN
6. As soon as the monitoring relay for the
emergency power monitors that sufficient
supply is provided, a waiting period (here
10 seconds) is activated in the LOGO!.
This is to ensure that the emergency
power grid is stable.
NET
GEN
7. The circuit breaker of the emergency
power grid is closed then.
The switching process to „emergency
power operation” is finished.
Supply is now carried out via the
generator.
8. Switch the automatic cut-out “ON” for the
public grid again.
NET
GEN
9.
The public grid returns again.
10.
As soon as the monitoring relay for the
grid power monitors that sufficient supply
is provided, a waiting period (here 10
seconds) is activated in the LOGO!. This
is to ensure that the grid power is stable.
NET
GEN
Live-Demo
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
36/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
No.
Instructions
Note
11.
After this waiting period, the switching
process to “grid power operation” is
effected in the LOGO! and is processed
as follows:
A monitoring time for the grid power
operation return is started.
The circuit breaker for the emergency
power operation is opened.
The circuit breaker for the public grid is
closed.
12.
The switching process to “public grid” is
finished if the actions have been carried
out within this monitoring time (here 60
seconds) and when the circuit breaker for
the public grid announces its return.
Supply is now carried out via the public
grid again.
13.
Afterwards the generator for the
emergency power operation can be
switched off.
(Simulated by switching off the automatic
cut-out “GEN”).
NET
GEN
14.
The switching process is finished.
Live-Demo
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
37/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
6.1.3
Scenario 3: AUT - Grid failure with procedure error when generator is
requested
• Automatic
mode
• Supply is now carried out via the public grid.
• Public grid fails for longer period of time
• At first the generator cannot carry out the task of the public grid
• The generator can carry out the task of the public grid on the second
attempt
• The public grid returns
Table 6-4
No.
Instructions
Note
1.
Supply is carried out via the public grid.
2. Switch the automatic cut-out “OFF” for the
public grid.
NET
GEN
3. The public grid drops and a voltage dip
monitoring (here 3 secs) is effected in the
LOGO!
> 3sec
4. If the voltage dip monitoring is exceeded,
the switching process to “emergency
power operation” is effected in the LOGO!
and is processed as follows:
The generator for the „emergency power
grid“ is requested.
A monitoring time for the generator return
is started.
The circuit breaker for the public grid is
opened.
T: 60sec
Live-Demo
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
38/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
No.
Instructions
Note
5. Let the monitoring time (here 60 seconds)
for the availability of the generator pass.
(simulated by not switching on the
automatic cut-out “GEN”)
NET
GEN
> 60sec
6. As soon as the monitoring time for the
generator request is passed, the
switching process turns into a defined
error state.
The generator request for the emergency
power supply is reset.
7. Acknowledge the error with the button
“ACK”.
ACK
8. The generator request for the emergency
power grid is requested again by this
action and the monitoring time (60
seconds) for the generator return is
triggered again.
T: 60sec
9. Now you have to simulate the availability
of the generator within the monitoring time
by switching on the automatic cut-out
“GEN”.
NET
GEN
< 60 sec
10.
As soon as the monitoring relay for the
emergency power monitors that sufficient
supply is provided, a waiting period (here
10 seconds) is activated in the LOGO!.
This is to ensure that the emergency
power grid is stable.
NET
GEN
Live-Demo
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
39/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
No.
Instructions
Note
11.
The circuit breaker of the emergency
power grid is closed then.
The switching process to „emergency
power operation” is finished.
Supply is now carried out via the
generator.
12.
Switch the automatic cut-out “ON” for the
public grid again.
NET
GEN
13.
The public grid returns again.
14.
As soon as the monitoring relay for the
grid power monitors that sufficient supply
is provided, a waiting period (here 10
seconds) is activated in the LOGO!. This
is to ensure that the grid power is stable.
NET
GEN
15.
After this waiting period, the switching
process to “grid power operation” is
effected in the LOGO! and is processed
as follows:
A monitoring time for the grid power
operation return is started.
The circuit breaker for the emergency
power operation is opened.
The circuit breaker for the public grid is
closed.
16.
The switching process to “public grid” is
finished if the actions have been carried
out within this monitoring time (here 60
seconds) and when the circuit breaker for
the public grid announces its return.
Supply is now carried out via the public
grid again.
Live-Demo
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
40/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
No.
Instructions
Note
17.
Afterwards the generator for the
emergency power operation can be
switched off.
(simulated by switching off the automatic
cut-out “GEN”)
NET
GEN
18.
The switching process is finished.
Live-Demo
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
41/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
6.1.4
Scenario 4: AUT - Grid failure with subsequent grid return during
generator request
• Automatic
mode
• Public grid fails ( > 3sec) and returns while the generator is requested
• Generator does not start operation
Table 6-5
No.
Instructions
Note
1. Supply is now carried out via the public
grid.
2. Switch the automatic cut-out “OFF” for the
public grid.
NET
GEN
3. The public grid drops and a voltage dip
monitoring (here 3 secs) is effected in the
LOGO!
> 3sec
4. If the voltage dip monitoring is exceeded,
the switching process to “emergency
power operation” is effected in the LOGO!
and is processed as follows:
The generator for the „emergency power
grid“ is requested.
A monitoring time for the generator return
is started.
The circuit breaker for the public grid is
opened.
T: 60sec
5. Now you have to simulate the return of
the public grid within the monitoring time
by switching on the automatic cut-out
“NET”.
NET
GEN
< 50sec
Live-Demo
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
42/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
No.
Instructions
Note
6. The return of the public grid for the
effected generator request is ignored at
first. You have to wait for the generator to
return.
7. As soon as the monitoring time for the
generator request is passed, the
switching process turns into a defined
error state.
The generator request for the emergency
power supply is reset.
8. Acknowledge the error with the button
“ACK”.
ACK
9. By this acknowledgement the switching
process to “grid power operation” is
effected in the LOGO! and is processed
as follows:
A monitoring time for the grid power
operation return is started.
The circuit breaker for the emergency
power operation is opened.
The circuit breaker for the public grid is
closed.
10.
The switching process to “public grid” is
finished if the actions have been carried
out within this monitoring time (here 60
seconds) and when the circuit breaker for
the public grid announces its return.
Supply is now carried out via the public
grid again.
Live-Demo
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
43/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
6.1.5
Scenario 5: MAN – Manual mode circuit breaker NET
Table 6-6
No.
Instructions
Note
1. Set the knob switch "S1" to mode
“manual”.
ACK
S1
S2
S5
S4
S3
A
uto
S
erv
M
an
N
etz
0
G
en
CLOSE
OPEN
2. Set the knob switch "S2" to circuit breaker
selection “Net”.
ACK
S1
S2
S5
S4
S3
A
uto
S
erv
M
an
N
etz
0
G
en
CLOSE
OPEN
3. Now you are in manual mode and the grid
circuit breaker is selected.
4. Using the „
OPEN
“ button the grid circuit
breaker is opened or loaded, respectively.
Using the „CLOSE“ button the grid circuit
breaker is closed again.
Repeat this process several times.
OPEN
CLOSE
The two circuit breakers are electrically
interlocked with each other. The grid
circuit breaker can only be closed if the
emergency power circuit breaker is
opened.
5. The final action is to open the grid circuit
breaker.
Live-Demo
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
44/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
6.1.6
Scenario 6: MAN – Manual mode circuit breaker GEN
Table 6-7
No.
Instructions
Note
1. Set the knob switch "S1" to mode
“manual”.
ACK
S1
S2
S5
S4
S3
A
uto
S
erv
M
an
N
etz
0
G
en
CLOSE
OPEN
2. Set the knob switch "S2" to circuit breaker
selection “Gen”.
ACK
S1
S2
S5
S4
S3
A
uto
S
erv
M
an
N
etz
0
G
en
CLOSE
OPEN
3. Now you are in manual mode and the
emergency power circuit breaker is
selected.
4. Using the „
OPEN
“ button the emergency
power circuit breaker is opened or loaded,
respectively.
Using the „CLOSE“ button the emergency
power circuit breaker is closed again.
Repeat this process several times.
OPEN
CLOSE
The two circuit breakers are electrically
interlocked with each other. The
emergency power circuit breaker can only
be closed if the grid circuit breaker is
opened.
The final action is to open the emergency
power circuit breaker.
Live-Demo
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
45/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
6.1.7
Scenario 8: SERVICE – Service operation
Table 6-8
No.
Instructions
Note
1. Make sure the circuit breakers are
powered by the public grid or by the
emergency power operation.
NET
GEN
In this scenario it is powered by the public
grid!
2. Switch the knob switch “S2“ to “0” and
knob switch “S1” to “service”.
ACK
S1
S2
S5
S4
S3
A
uto
S
erv
M
an
N
etz
0
G
en
CLOSE
OPEN
In this mode LOGO! is disabled and no
unwanted actions will occur.
3.
Now you are in “service operation”.
By this selection the circuit breakers are
powered by the public grid.
Both circuit breakers are open.
4. Switch both circuit breakers to “manual”
mode.
The circuit breakers are not interlocked
with each other. The two circuit breakers
must not be switched on at the same time
if grid voltage and generator voltage is
available.
NET
GEN
Live-Demo
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
46/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
No.
Instructions
Note
5. Now for the circuit breakers of the public
grid.
Using the „
OPEN
“ button the circuit
breaker is opened or loaded, respectively.
Using the „CLOSE“ button the circuit
breaker is closed again.
Repeat this process several times.
The final action is to open the grid circuit
breaker.
NET
6. Now for the circuit breaker of the
generator
Using the „
OPEN
“-button the circuit
breaker is opened or loaded, respectively.
Using the „CLOSE“-button the circuit
breaker is closed again.
Repeat this process several times.
The final action is to open the emergency
power circuit breaker.
GEN
7. The scenario for this service operation is
now completed.
Both circuit breakers are open.
Technical data
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
47/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
7 Technical
data
7.1 SITOP
Table 7-1
Criterion
Technical data
Additional note
SITOP Power
INPUT VOLTAGE :
AC120/230V, 50/60Hz
OUTPUT VOLTAGE: 24V+/-
3%
PERMISSIBLE RANGE :
93...132/187...264V
ADJUSTMENT RANGE :
22.8...26.4V
SITOP DC-UPS-Module 6
SITOP DC-UPS-MODULE 24V
/ 6A WITH POTENTIAL-FREE
USB-INTERFACE INPUT: DC
24V / 6.85A OUTPUT: DC 24V
/ 6A
SITOP POWER BATTERY
MODULE
SITOP POWER BATTERY
MODULE 1.2 AH WITH
MAINTENANCE-FREE,
SEALED LEAD BATTERIES
FOR SITOP POWER DC-
UPS-MODULE 6
7.2 LOGO!
Table 7-2
Criterion
Technical data
Additional note
LOGO! logic module
(12/24RC)
PS/ I/O DC12/24V / DC12/24V
/ relay 8DE (2AE 0..10V)/4DA
Logic module with display
and keys
130 blocks
expandable in modules
LOGO! DM8 24R EXPANSION
MODULE
PS/ I/O AC/DC 24V / AC/DC
24V PNP and NPN / relay
4DE/4DA
2TE
Technical data
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
48/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
7.3 SENTRON
Table 7-3
Criterion
Technical data
Additional note
SENTRON circuit breaker VL
160N
ICU=40kA, 415V AC 3-pin,
Shunt trip 24V AC/DC auxiliary
switch installation set 2 HS
(1NO+1NC)
Plant protection
over current release TM, LI
IN=50A, rated current
IR=40...50A,
Overload protection
II=300...600A, short circuit
protection, protection
Motorized operating
mechanism with spring energy
store
220...250V AC/DC
7.4 SIRIUS
Table 7-4
Criterion
Technical data
Additional note
SIRIUS monitoring relay 3UG4
PHASE FAILURE 3X 160 TO
690V AC 50 TO 60 HZ
UNDERVOLTAGE AND
OVERVOLTAGE 160-690V
HYSTERESIS 1-20V
OFF-DELAY 0-20S
ASYMMETRY 0-20%
1W FOR PHASE
CORRECTION
1 W FOR GRID ERROR
DIGITAL MONITORING
RELAY FOR 3-PHASE
GRID VOLTAGE
AUTOMATIC
CORRECTION OF PHASE
SEQUENCE
SCREW CONNECTION
Contactor
2NO+2NC, DC 24V
SCREW CONNECTION
Resetting element
RC ELEMENT AC 24...48V,
DC 24...70V
SURGE SUPPRESSOR
FOR PLUGGING ONTO
CONTACTORS
Technical data
Micro Automation Set 29
Beitrags-ID 27074055
V01.00 05.11.2007
49/49
C
opyr
ight
©
Si
em
ens
AG 2
007
Al
l r
ights r
e
s
e
rv
ed
Set2
9_D
ocT
e
ch_v
1d3
_
en.
doc
7.5
Instruction and display devices
Table 7-4
Criterion
Technical data
Additional note
Knob switch
ACTUATING ANGLE 2 X 50
DEGREES BLACK,
1NO, 1NO WITH SUPPORT
COMPLETE UNIT,
ROUND KNOB SWITCH,
I-O-II, LATCHING,
SCREW CONNECTION
Push button (yellow)
1NO WITH SUPPORT
COMPLETE UNIT,
ROUND PUSH BUTTON
WITH FLAT BUTTON
YELLOW, SCREW
CONNECTION
Push button (green)
1NO WITH SUPPORT
COMPLETE UNIT,
ROUND PUSH BUTTON
WITH FLAT BUTTON
GREEN, SCREW
CONNECTION
Push button (red)
1NC WITH SUPPORT
COMPLETE UNIT,
ROUND PUSH BUTTON
WITH FLAT BUTTON
RED, SCREW
CONNECTION