Automatyka Budynkow MAS29

background image



Micro Application Example

Automatic Transfer switch
with LOGO! and SENTRON circuit breaker

Micro Automation Set 29

background image

Table of contents

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

2/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

Note

The Micro Automation Sets are not binding and do not claim to be complete
regarding the circuits shown, equipping and any eventuality. The Micro
Automation Sets do not represent customer-specific solutions. They are only
intended to provide support for typical applications. You are responsible for
ensuring that the described products are correctly used. These Micro
Automation Sets do not relieve you of the responsibility of safely and
professionally using, installing, operating and servicing equipment. When using
these Micro Automation Sets, you recognize that Siemens cannot be made
liable for any damage/claims beyond the liability clause described.

We reserve the right to make changes to these Micro Automation Sets at any
time without prior notice. If there are any deviations between the
recommendations provided in these Micro Automation Sets and other Siemens
publications – e.g. catalogs – the contents of the other documents have priority.

Warranty, Liability and Support

We accept no liability for information contained in this document.

Any claims against us – based on whatever legal reason – resulting from the
use of the examples, information, programs, engineering and performance data
etc., described in this Micro Automation Set shall be excluded. Such an
exclusion shall not apply in the case of mandatory liability, e.g. under the
German Product Liability Act (“Produkthaftungsgesetz”), in case of intent, gross
negligence, or injury of life, body or health, guarantee for the quality of a
product, fraudulent concealment of a deficiency or breach of a condition which
goes to the root of the contract (“wesentliche Vertragspflichten”). However,
claims arising from a breach of a condition which goes to the root of the contract
shall be limited to the foreseeable damage which is intrinsic to the contract,
unless caused by intent or gross negligence or based on mandatory liability for
injury of life, body or health. The above provisions do not imply a change in the
burden of proof to your detriment.

Copyright© 2007 Siemens A&D. It is not permissible to transfer or copy
these Micro Automation Sets or excerpts of them without first having prior
authorization from Siemens A&D in writing.

background image

Table of contents

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

3/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

Foreword

Micro Automation Sets are fully functional and tested automation
configurations based on A&D standard products for simple, fast and
inexpensive implementation of automation tasks for small-scale
automation. Each of the available Micro Automatic Sets covers a frequently
occurring subtask of a typical customer problem in the low-end
performance level.

The sets help you obtain answers with regard to required products and the
question how they function when combined.

However, depending on the system requirements, a variety of other
components (e.g. other CPUs, power supplies, etc.) can be used to
implement the functionality on which this set is based. Please refer to the
respective SIEMENS A&D catalogs for these components.
The Micro Automation Sets are also available by clicking the following link:

http://www.siemens.en/microset

background image

Table of contents

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

4/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

Table of contents

Table of contents .......................................................................................................... 4

1

Fields of Application and Benefits ................................................................ 6

1.1

Automation Task............................................................................................... 6

1.2

Automation solution Set 29 ............................................................................... 7

1.3

Application Areas.............................................................................................. 8

1.4

Benefits............................................................................................................. 8

2

Wiring diagrams.............................................................................................. 9

2.1

Wiring plan: Uninterruptible power supply with battery and change-over

contactor of the supply mains. ..................................................................... 9

2.2

Wiring plan: LOGO! Basic with expansion module DM8 and digital monitoring

relay ........................................................................................................... 10

2.3

Wiring plan: Circuit breaker ............................................................................ 11

3

Hardware and Software Components ......................................................... 12

3.1

Transfer switch ............................................................................................... 12

4

Function Principle ........................................................................................ 14

4.1

Circuit breaker with motor drive ...................................................................... 14

4.2

SIRIUS Monitoring relay ................................................................................. 16

4.3

SITOP UPS..................................................................................................... 17

4.4

Transfer switch process in automatic operation.............................................. 18

4.5

Service functions ............................................................................................ 22

4.6

Overview on the operator functions ................................................................ 23

4.7

Depictions on the display of the LOGO! logic module .................................... 25

4.8

Load shedding ................................................................................................ 26

5

Configuring the Startup Software ............................................................... 27

5.1

Preliminary remark.......................................................................................... 27

5.2

Downloading the startup code ........................................................................ 27

5.3

Configuring Components ................................................................................ 27

5.3.1

Installing and wiring hardware ........................................................................ 28

5.3.2

Power supply and emergency power supply .................................................. 29

5.4

Preparations ................................................................................................... 30

6

Live-Demo ..................................................................................................... 32

6.1

Overview of all scenarios................................................................................ 32

6.1.1

Scenario 1: AUT – short time grid failure ....................................................... 33

6.1.2

Scenario 2: AUT - Grid failure without procedure error when generator is

requested ................................................................................................... 34

6.1.3

Scenario 3: AUT - Grid failure with procedure error when generator is

requested ................................................................................................... 37

6.1.4

Scenario 4: AUT - Grid failure with subsequent grid return during generator

request ....................................................................................................... 41

background image

Table of contents

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

5/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

6.1.5

Scenario 5: MAN – Manual mode circuit breaker NET ................................... 43

6.1.6

Scenario 6: MAN – Manual mode circuit breaker GEN................................... 44

6.1.7

Scenario 8: SERVICE – Service operation ..................................................... 45

7

Technical data............................................................................................... 47

7.1

SITOP ............................................................................................................. 47

7.2

LOGO! ............................................................................................................ 47

7.3

SENTRON ...................................................................................................... 48

7.4

SIRIUS ............................................................................................................ 48

7.5

Instruction and display devices ....................................................................... 49

background image

Fields of Application and Benefits

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

6/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

1

Fields of Application and Benefits

1.1 Automation

Task

On the event of a power failure in a shopping center the emergency lights and
other devices important to maintain the infrastructure are to be powered by a
generator.

A monitoring sensor is to be used to monitor the availability of the current network.
If it detects a power failure, a control unit requests power from the generator.

If a further monitoring sensor informs the control unit about the availability of the
generator current, it should trigger the network-circuit breaker to cut the main circuit
of the shopping center from the public grid.

After the power was cut from the public grid, the emergency power network of the
shopping center is to be connected to the generator.

This state is to be maintained until the first monitoring sensor signalizes that the
public grid is available again. As a result the control unit should then cut the circuit
breaker responsible for the emergency power supply from the emergency power
network of the shopping center.

After a successful disconnection from the emergency power network, the control
unit should switch the network circuit breaker on in order to supply the shopping
center with current from the public grid again. If this procedure is finished, the
control unit informs the generator to stop operation.

In order to guarantee a constant availability of the generator, its functionality has to
be checked once a month. To do so, the control unit should be able to switch the
network circuit breaker on/off in the manual mode using push buttons.
A mechanical interlock avoids the two circuit breakers being switched on at the
same time.

Figure 1-1

Generator

Shopping center

Control unit

Control unit

background image

Fields of Application and Benefits

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

7/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

1.2

Automation solution Set 29

One circuit breaker of the type VL 160N connects the public grid to the main circuit
and one connects it to the emergency power system of the shopping center,
respectively.

Using the SIRIUS monitoring relay the availability of the three phases of the public
grid and of the emergency power system is monitored.

The LOGO! logic module disconnects the circuit breaker from the public grid if the
SIRIUS monitoring relay detects a phase error or a failure. It then triggers the
generator to switch on.

If the availability of the generator grid is confirmed by the SIRIUS monitoring relay,
the LOGO“ logic module cuts the circuit breaker to the generator grid.

If the SIRIUS monitoring relay signalizes that the public grid is available again, a
switch-back to the public grid and the switching off of the generator is triggered by
the LOGO! logic module.

The SITOP DC-UPS-MODULE ensures that the LOGO! logic module can operate
while switching between public grid and generator grid is carried out.

For maintenance purposes a knob switch is used to switch between automatic and
manual mode. Using a further knob switch, the circuit breaker on the one hand to
the public grid or on the other hand to the generator grid can be selected. Using a
push button it can be switched on or off.

Figure 1-2

Grid

Circuit breaker VL160 (Grid)

SITOP

Power supply

SITOP UPS DC24V

SITOP Batt. module

Circuit breaker VL160 (Generator)

2

3

4

5

LOGO! Logic module

7

4

1

5

Generator

1

2

3

4

7

10

G

1

LOGO! Expansion module

8

Knob switch

9

Buttons

10

SIRIUS Grid monitoring relay

11

9

I

II

0

I

II

0

8

s

13NO

21NC

31NC

21NC

A1+

DC 24V

14NO

22NC

32NC

44NO

A2-

6

11

SIRIUS

Contactor

6

background image

Fields of Application and Benefits

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

8/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

1.3 Application

Areas

Industry

• Production lines for continuous production (foundries, chemical

processes, etc.)

• Engine rooms on ships
• Important additional equipment for thermal power plants

Infrastructure

• Docks and railway systems

• Airport

lighting

• Monitoring systems for military bases

Building technologies

• Operating rooms in hospitals

• Safety devices for high-rise buildings

• Computer rooms (banks, insurance companies, etc.)

• Lighting systems for shopping centers

1.4 Benefits

• The automatic transfer switch ensures a continuous power supply in

case of a power failure.

• The continuous grid monitoring is performed by the SIRIUS 3UG4

monitoring relay. The transfer operation is reliably controlled by the
LOGO! logic module

• The high demand of the transfer switch is implemented by the motor

driven SENTRON circuit-breakers.

• Safety – provided by the continuous power supply in case of a power

failure.

• Saving of time – by the automatic transfer switch in case of a power

failure and by the automatic resetting on the power return, service
engineers do not have to intervene.

• Optimum power management – by the option of power shedding when

switching to emergency power supply.

background image

Wiring diagrams

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

9/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

2 Wiring

diagrams

2.1

Wiring plan: Uninterruptible power supply with battery and
change-over contactor of the supply mains

Figure 2-1

1

A1

A2

A3

L+

M

21 13 31 43

22 14 32 44

R3

A1

A2

R1\L1(4)

R2\L1(4)

R1\N(1)

R1\N(1)

A5\K14

L1

L2

L3

N

PE

L1

L2

L3

N
PE

Gr
id

G

ener

ator

SI

7.

5A

Sitop Smart

Sitop UPS

Sitop battery

M

L+

L+ M

X1.1
X1.2
X1.3
X1.4
X1.5
X1.6
X1.7
X1.8

The LOGO! Logic module is powered by an uninterruptible power supply
(UPS) (see “A1“and “A2“ in figure 2-1). While switching from grid to
generator and vice versa the battery buffers the LOGO! logic module.

The change-over contactor "R3“ connects the phase “L1” and the zero
conductor, depending on the availability of the generator between public
grid and generator grid, with the power supply “A1” and with the servo
motor of the circuit-breaker. As soon as the generator grid is available the
relay switches from the public grid to the generator grid.

background image

Wiring diagrams

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

10/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

2.2

Wiring plan: LOGO! Basic with expansion module DM8 and
digital monitoring relay

Figure 2-2

R3\

14 (G

en

)

LO
GO

!

Lo
gi

c

m

od
ule

24V

DC

L1

I1

N

I3

I6

I2

I5

I7

Î4

I8

Q11

Q31

Q12

Q22

Q21

Q32Q41Q42

LO
GO

!

Lo
gi

c

m

od
ul

e

DM

8

L1

I1

N

I3

I2

Î4

Q11

Q31

Q12

Q22

Q21

Q32Q41Q42

L+

M

L1

L2

L3

22

24

21

12

14

11

S

IRI
US

Mo
n

ito

rin

g

re

la

y

R2\

S

2B

R

1

\A

S

.X

2

.6

(

tr

igg

e

re

d

)

R

1

\H

S

.X

2

.4

(

c

lo

s

e

d

)

A6

A7

A4

Gr

id

:L

1

Gr

id

:L

2

Gr

id

:L

3

R3\

22 (Net

z)

R1

\S

2

B

R

2

\H

S

.X

2

.4

(

c

lo

se

d

)

L1

L2

L3

22

24

21

12

14

11

S

IRI
US

Mo
n

ito

rin

g

re

la

y

A5

Ge

n

:L

1

Ge

n

:L

2

Ge

n

:L

3

R3\A1

AC

K

S1.S2

A

uto

M

an

S

erv

S1
Ö1

S2
Ö2

S1

Net

Gen

0

S1
Ö1

S2

S2
Ö2

S2.S2

R

1

\H

S.

X2.

1

S4

4

S3

3

2

S4

1

Knob switch

Buttons

R1\

S

A

:1.

\X

1.

1

R2

\H

S

.X

2

.1

St

a

rt

:G

e

n

\A

1

2\

I0

.7

R2\

S

A

:1

.X

1

.1

4

S5

3

R

2

\A

S.

X2.

6

(t

ri

g

g

er

ed

)

S1.S1

S5

A

u

to

M

ode

Of

f

S3

On

S2.S1

M

a

n

u

a

l Gr

id

M

a

nua

l G

e

n

On

Off

Ack

A2

\X

2

.9

A2

\X

2

.1

0

The transfer switch is controlled by a LOGO! logic module “A1“ and by an
expansion module DM8 “A2“. The SIRIUS monitoring relay monitors the
availability of the public grid or of the generator grid, respectively. Both
monitoring relays transmit the state via a digital signal to the LOGO! logic
module.

The knob switch “S1“ is responsible for selecting the operation mode. Using
this switch the operation modes “automatic” and “manual” can be selected.

If the “manual“ mode is selected, the knob switch “S2” is used to address
the circuit-breaker either to the public grid or to the generator grid. The
push button “S3“ is then used to switch the selected circuit-breaker on, the
push button “S4“ is used to switch it off again..

An error triggered by exceeding the timeout counter for instance, has to be
acknowledged by the push button “S5”.

background image

Wiring diagrams

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

11/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

2.3

Wiring plan: Circuit breaker

Figure 2-3

R2\HS.X2.2

A7\Q32

Legend:
SA = Circuit switch
HS = auxiliary switch
AS = alarm switch

R3\K22

L1

L2

L3

N

PE

L1

L2

L3

N
PE

Gri
d

Gen

e

ra

to

r

1

2

3

4

5

6

HS.X2.1

HS.X2.2

HS.X2.3

HS.X2.4

AS.X2.5

AS.X2.6

SA:1(X1.1)

SA:2(X1.2)

R1

PE(X20.5)

S2A(X20.2)

L2-(X20.1)

L2+(X20.4)

S2B(X20.3)

M 24V

R3\K32

A6\Q12

A6\Q22

R2\S2A

A6\I7

L+ 24V

A6\I3

R1\HS.X2.2

A6\Q32

R3\K22

1

2

3

4

5

6

HS.X2.1

HS.X2.2

HS.X2.3

HS.X2.4

AS.X2.5

AS.X2.6

SA:1(X1.1)

SA:2(X1.2)

R2

PE(X20.5)

S2A(X20.2)

L2-(X20.1)

L2+(X20.4)

S2B(X20.3)

M 24V

R3\K32

A6\Q42

A7\Q22

R1\S2A

A6\I8

L+ 24V

A6\I4

The circuit breakers are operated via the LOGO! logic module. In order to
avoid both circuit breakers to be switched on at the same time, the digital
activation command has been looped to the circuit breaker “R1” (“R2”)
using an auxiliary contact to the circuit breaker “R2” (“R1”).

The servo motors of the circuit breakers are powered analogically to the
UPS via the currently available grid using the change-over contactor “R3”.
This enables both circuit breakers to be controllable even in the case of a
power failure in one of the grids.

background image

Hardware and Software Components

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

12/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

3

Hardware and Software Components

3.1 Transfer

switch

Products

Table 3-1

Component

No.

MLFB/Order number

Note

LOGO! logic module
(12/24RC)

1 6ED1052-1MD00-0BA5

LOGO! DM8 24R
EXPANSION MODULE

1 6ED1055-1HB00-0BA0

SENTRON circuit breaker
VL 160N

2 3VL2705-1DC33-8CD1

Motorized operating
mechanism with spring
energy store

2 3VL9300-3MQ00

SIRIUS monitoring relay
3UG4

2 3UG4617-1CR20

SITOP SMART, closed-loop
controlled load power supply
unit

1 6EP1333-2BA01

SITOP DC UPS MODULE
24V/6A

1 6EP1931-2DC42

SITOP battery model 24V /
1.2 AH

1 6EP1935-6MC01

SIRIUS contactor relay

1

3RH1122-1BB40

RC element

1

3RT1916-1CB00

Selector switch
knob, I-0-II, latching

2 3SB3210-2DA11

Push button green, 1NO

1

3SB3202-0AA41

Pushbutton yellow, 1NO

1

3SB3202-0AA31

Push button red, 1NC

1

3SB3203-0AA21

background image

Hardware and Software Components

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

13/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

Accessories

Table 3-2

Component

No.

MLFB/Order number

Note

LOGO! PC cable

1

6ED1057-1AA00-0BA0

Configuration software/tools

Table 3-3

Component

No.

MLFB/Order number

Note

LOGO! SOFT COMFORT V5.0
SP5, SINGLE LICENSE

1 6ED1058-0BA01-0YA0

Accessories for Live-Demo

Table 3-4

Component

No.

MLFB/Order number

Note

Automatic cut-out

2

5SX2316-5

• 3-pin
• 16A

Lamp for connection to
AC 230V

2

background image

Function Principle

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

14/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

4 Function

Principle

4.1

Circuit breaker with motor drive

Overview

The circuit breaker comprises a 3-phase switch which connects the grid to
the load.

Figure 4-1

1

2

3

4

5

6

Shunt trip

Motorized operating
mechanism with spring
energy store

Auxiliary switch
„NO“

Auxiliary switch
„NC“

Alarms switch
„NO“

Main switch

In the present case the circuit breaker comprises the following components:

Table 4-1

No.

Component

Note

1. Circuit breaker unit

2. Motorized operating

mechanism with spring
energy store

The motorized operating mechanism with spring
energy store is mounted on the circuit breaker
and is used to open and to close it. It has a
manual and an automatic mode. The mode can
be selected using the slider on the motor drive.

3. Shunt

trip

This additional module is placed in the right-
hand slot of the circuit breaker. The relay of the
shunt trip can be accessed by the LOGO! Logic
module, for instance. If the current flow of the

background image

Function Principle

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

15/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

No.

Component

Note

shunt trip is interrupted, the triggering
mechanism of the circuit breaker is activated
and it takes the position “triggered”.

4. Auxiliary

switch

This installation set comprises a NC and a NO.
The position of the auxiliary switches represents
the state of the circuit breaker.
• The NO-state provides the LOGO! logic

module with the current position of the
circuit breaker.

• The NC is used for locking purposes in

order to ensure both circuit breakers not to
be switched on at the same time.

5. Alarm

switch

This installation set comprises a NO. If this
alarm switch is closed it sends a signal to the
LOGO! logic module saying that the circuit
breaker has taken the switch position
“triggered”.

The 3 states of the circuit breaker

The circuit breaker can be in 3 different positions

Table 4-2

No.

Switch position

1. Closed

In this position the contacts of the circuit breaker
are closed The load is connected to the grid and
the current can flow.

2. Open

In this position the contacts of the circuit breaker
are open. The load is disconnected from the grid
and the current cannot flow.

3. Triggered

In this position the contacts of the circuit breaker
are open. The switch position “triggered“ can be
attained either with a mechanism directly activated
on the circuit breaker, or it is triggered via an
optional module (e.g. shunt trip).
After the circuit breaker was brought into the
“triggered” switch position, it cannot immediately
be switched on again. In order to switch the circuit
breaker on again, in other words to close it, it first
of all has to be opened. This is to avoid the circuit
breaker to be switched on after an error (e.g.
short-circuit after in public mains) without having
corrected the error.

background image

Function Principle

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

16/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

4.2

SIRIUS Monitoring relay

The monitoring relay 3UG4617 monitors the phase sequence and a phase
failure of one of the phases. It furthermore monitors if a set voltage is
undershoot or exceeded and if a set asymmetry value is exceeded and it
monitors the difference between the highest and lowest phase voltage in
relation to the highest phase voltage (Ux-y max - Ux-y min) / Ux-y max in a
3-phase grid.

If the correct phase sequence at the terminals L1-L2-L3 is applied, the relay
A4 or A5 picks up. This is depicted on the display with a relay symbol. In
case of an incorrect phase sequence the relay will not pick up. In this case
no error message will occur on the display but the relay symbol will not
show up! If the monitored voltage (Ux-y) is higher then the specified lower
voltage value (U|) and lower then the specified higher voltage value (Ux),
meaning within the voltage limits, and if the grid voltage (Asy) is lower then
the specified value, the relay A4 or A5 (contact 11-12-14) will pick up
approx. 50ms after the reaction of A4 or A5, respectively. For the
3UG4617 the display shows the current voltage between lines L1 and L2.

The following grid faults are depicted on the display as diagnosis message
with flashing symbols:

• Failure of one phase (3UG4618 or failure of the zero conductor).

Symmetric (all 3 phase voltages / star voltages at the same time)

• Asymmetric (only one phase voltage / star voltage) undershoot or

exceeding of the voltages specified in the menu. Exceeding the
asymmetry specified in the menu.

In case of a phase failure the relay A4 or A5 will immediately be released.
In case of the errors voltage undershoot, voltage exceed or asymmetry
exceed the relay A4 or A5 will be released after the specified fault display
relay time (Del).

background image

Function Principle

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

17/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

4.3 SITOP

UPS

Function

In combination with the SITOP battery modules the DC-UPS-module 6 is
used to buffer parts of the load current (max. 6A) of 24V-load current
supplies of the SITOP series.

The loads to be buffered are powered by the voltage of input using the
outputs “Output L+” and “Output M” of the DC-UPS module. If the 24V
DC-supply voltage fails or if the voltage drops below the specified cut-in
threshold, the loads are powered by switching on the battery module which
is kept in full charge in stand-by parallel operation.

Adjustable parameters

Figure 4-2

+2V
+1V
+0,5V
+1V
+1V
+0,5V
+0,2V
+0,2V
+0,1V
0,2A / 0,4A

Ladestrom

(charging current)

eingestellte Zeit / max. Zeit (set time / max.)
+320s
+160s
+ 80s
+ 40s
+ 20s
+ 10s +5s fest eingestellt (fixed)
Unterbrechung output (disconnection)
Betriebszustand Akku On / Off
(operating state battery)

Zuschaltschwelle

(cut-in threshold)
+22V fest eingestellt (fixed)

Ladeschlussspannung

(end-of-charge voltage)
+ 26,3V fest eingestellt (fixed)

Pufferzeit

(buffering time)

According to the DIP-switches depicted in figure 4-2 the following
parameters can be adjusted:

• Battery cut-in threshold
• End-of-charge

voltage

• Charging

current

• Buffering

time

background image

Function Principle

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

18/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

Cut-in threshold

If the input voltage drops below the specified value of the cut-in threshold,
the UPS-module will switch to backup power operation. The loads are then
only powered by the battery module.

End-of-charge voltage

The end-of-charge voltage depends on the type of the battery used and of
the temperature the battery is exposed to. For detailed information on the
adjustment please refer to the manual.

Charging current

The battery module is charged with constant current until the specified end-
of-charge voltage is reached. The charging process is then stopped.

Buffering time

The buffering time can be set in 10 second steps from 5 seconds to 635
seconds. Using switch 1 (specified time/maximum time) you can select if
the backup power operation is stopped when the specified time is reached
or when the exceed discharge threshold of the battery (= maximum
buffering time) is reached.

4.4

Transfer switch process in automatic operation

Status diagram

The status diagram shows the behavior of the control program in automatic
mode. T*.* are the switch-over conditions that have to be fulfilled in order to
get from one phase P* to the next one.

background image

Function Principle

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

19/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

Figure 4-3

Grid is

available

P1

Gen is

available

P2

switch Net

to Gen

P3

switch Gen

to Net

P4

error

recognized

P5

Switch to Net

and Gen

triggered

P6

T

1.1

T

1.2

T

4.1

T

4.2

T

3.1

T

3.2

T

2.2

T

2.1

T

5

start, Auto

error-

acknowledgeme

nt

P0

T

1.1

T

0.1

T

2.2

T

0.2

T

6.1

Table 4-3

Name of condition

Condition

1.

T

0.1

• Public grid is available
• Grid-circuit breaker closed
• Generator-circuit breaker open

2.

T

0.2

• Grid

failed

• Grid-circuit breaker open
• Generator-circuit

breaker

closed

3.

T

1.1

• Public grid failed

4.

T

1.2

• Grid-circuit breaker in “triggered”
• Generator not available

5.

T

2.1

• Public grid is available again

6.

T

2.2

• Generator-circuit breaker in “triggered”
• Public grid not available

7.

T

3.1

• Switching operation from “public grid” to

“generator grid” successfully carried out

8.

T

3.2

• Switching operation from “public grid” to

“generator grid” could not be carried out
within monitoring time

9.

T

4.1

• Switching operation from “generator” to

“public grid” successfully carried out

background image

Function Principle

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

20/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

Name of condition

Condition

10.

T

4.2

• Switching operation from “generator” to

“public grid” could not be carried out within
monitoring time

11.

T

5

• At least one error pending

12.

T

6.1

• All errors acknowledged
• All

errors

corrected

Switching from public grid to generator grid

The switching process is based on the status diagram from figure 4-1. The
application is in state “P1” and has the following basic conditions:

• Selector switch for operation mode “S1”: “Automatic”
• Circuit breaker switch “S2”: “0“
• Public grid connected to load
• Generator is switched off
• Locking switch of both circuit breakers is in “auto” position

Switching into state „P3“ is effected, if the SIRIUS monitoring relay „A4“
sends a message to the LOGO! logic module stating that the public grid
has failed for at least 10 seconds. The LOGO! logic module then switches
the grid circuit breaker „R1“ to the state „triggered“ and, in doing so,
interrupts the connection between load and public grid. An inquiry in form of
a digital signal is simultaneously sent to the generator. If the SIRIUS
monitoring relay „A5“ transmits the information on the availability of the
generator grid to the LOGO! logic module “A6” the generator circuit breaker
“R2” switches from ”triggered” to “open” (motor loads the spring force
storage device). Then the circuit breaker „R2“ is closed (spring force
storage device is unload). Now a connection between generator grid and
partial load (loads for emergency light, lifts, etc.) is established.

After the successful switch to the generator grid the state “P2” is attained.

Here the SITOP DC-UPS-MODULE “A2” ensures that the LOGO! logic
module “A6” is supplied with power even during the switching process from
public grid to generator grid.

If the switching process could not be carried out during the monitoring time
of 30 seconds, error state “P5” is attained. This situation is depicted on the
display with an error message. For safety reasons the LOGO! logic module
“A6” switches both circuit breakers “R1” and “R2” to the state “triggered”.
This means that the load is disconnected from the public and from the
generator grid. State “P6” is attained.

background image

Function Principle

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

21/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

Switch back from generator grid to public grid

The switching process is based on the status diagram from figure 4-1. The
application is in state “P2” and has the following basic conditions:

• Selector switch for operation mode “S1”: “Automatic”
• Circuit breaker switch “S2”: „0“
• Public grid is disconnected from load
• Generator is switched on and connected to partial load
• Locking switch of both circuit breakers is in “auto” position

Switching into state “P4“ is effected if the SIRIUS monitoring relay “A4“
sends a message to the LOGO! logic module stating that the public grid
has returned for at least 10 seconds. The LOGO! logic module then
switches the generator circuit breaker “R2“ to the state „triggered“ and, in
doing so, interrupts the connection between partial load and generator grid.
After successful disconnection the LOGO! logic module effects a state
change of the grid circuit breaker “R1” from “triggered” to “open” (motor
loads spring force storage device). Then the circuit breaker “R1“ is closed
(spring force storage device is unload). Now the connection between the
public grid and the load is re-established.

After the successful switch to the public grid state “P1“ is attained again.

Here the SITOP DC-UPS-MODULE “A2” ensures that the LOGO! logic
module “A6” is supplied with power even during the switching process from
public grid to generator grid.

If the switching process could not be carried out during the monitoring time
of 30 seconds, error state “P5” is attained. This situation is depicted on the
display with an error message. For safety reasons the LOGO! logic module
“A6” switches both circuit breakers “R1” and “R2” to the state “triggered”.
This means that the load is disconnected from the public and from the
generator grid. State “P6” is attained.

background image

Function Principle

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

22/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

4.5 Service

functions

Manual control of the circuit breakers via application buttons

For maintenance purposes both circuit breakers can manually be opened
or closed. To do so the following settings have to be carried out.

• Operation mode switch “S1” “Manual”
• Circuit breaker switch “S2”: “Public grid” or “Generator”

The closing of the circuit breaker is effected by pushing the green push
button “S3”, if the spring of the motor has been tensioned in advance. If the
spring has not been tensioned, the circuit breaker remains in “triggered”
state, meaning no connection between load and power supply is
established.

The opening of the circuit breaker selected and the winding up of the
tension spring is carried out after the red button “S4” was pushed.

Service with onboard-control elements of the circuit breaker

If the selector switch is set to the “Off”-position, all outputs of the LOGO!
logic module are switched to “0”.

For the purpose of a function test of the circuit breaker it can also be
directly controlled via the control elements.

• In order to ensure that the LOGO! Logic module does not carry out

changes in the control outputs while the onboard service, the operation
mode switch “S1” has to be set to “0”

• The locking switch of the circuit breaker has to be set to “manual”

according to figure 4-7

Pushing the red onboard button “ON” effects the closing of the circuit
breaker if the spring was tensed before. If the spring is untensed, the circuit
breaker remains in the “triggered“ state.

Pushing the black onboard button “OFF” effects the opening of the circuit
breakers and the tensing of the spring.

Note

After the service operation has been finished the locking switch of the
circuit breaker has to be reset to “auto” again.

!

DANGER

Do not use this function if the public grid and the generator grid are
both available at the same time, as the circuit breakers do not
interlock each other when switched on. If both grids are connected
to the load at the same time, a short-circuit can occur!

background image

Function Principle

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

23/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

4.6

Overview on the operator functions

Control elements

Figure 4-4

ACK

S1

S2

S5

S4

S3

A

uto

S

erv

M

an

N

etz

0

G

en

CLOSE

OPEN

Table 4-4

No.

Switch

Function

1.

S1

Operation mode selector switch for selecting the
operation modes automatic and manual

2.

S2

Circuit breaker selector switch for selecting the circuit
breaker

3.

S3

Push button for manual closing of the selected circuit
breaker in manual mode

4.

S4

Push button for manual opening of the selected circuit
breaker in manual mode

5.

S5

Push button for acknowledging an error message in
automatic mode

Automatic mode

Figure 4-5

Automatik

Manuell

Service

Automatikbetrieb

Öff. Netz

Generator

0

Funktion

Betriebsart

Wahlleistungsschalter

Taster

S1

S2

background image

Function Principle

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

24/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

Manual switch on/off of circuit breaker

Figure 4-6

Manual
Switch public grid
on

Manual
Switch public grid
off

Manual
Switch generator
grid on

Manual
Switch generator
grid off

Function

Mode

Circuit breaker selector switch

Button

Automatic

Manual

Service

S1

Automatic

Manual

Service

S1

Automatic

Manual

Service

S1

Automatic

Manual

Service

S1

Public
grid

Generator

0

S2

Public
grid

Generator

0

S2

Public
grid

Generator

0

S2

Public
grid

Generator

0

S2

S3

S4

S3

S4

Acknowledgement of errors

Figure 4-7

Fehler qu ittieren

Function

Bet rieb sa rt

Wahlleistung ss chalt e r

Tast er

S4

Automatic

Manual

Service

S1

background image

Function Principle

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

25/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

Service functions via the onboard-control elements of the circuit breaker

Figure 4-8

Service mode

Public grid

Generator

0

Function

Operation mode

Circuit breaker selector switch

Button

Close circuit breaker

Open circuit breaker

Manual
Spring tension lever

Selector switch to
„manual“

Spring tensed

Spring untensed

Automatic

Manual

Service

S1

S2

4.7

Depictions on the display of the LOGO! logic module

Status display

Figure 4-9

Betriebsart: Automatik Manuell oder Service

0: Keine Spannung am öffentlichen Netz oder Generator
1: Spannung am öffentlichen Netz oder Generator

0: Leistungsschalter öffentliches Netz offen
1: Leistungsschalter öffentliches Netz geschlossen

0: Leistungsschalter Generator offen
1: Leistungsschalter Generator geschlossen

background image

Function Principle

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

26/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

Display of the switching process

Figure 4-10

Switching process from phase P1 to P2 is running

Switching process from phase P2 to P1 is running

Error message in case of time violation

Figure 4-11

Fehlermeldung nach Zeitüberschreitung beim
Umschalten von Generator zum öffentlichen
Netz

4.8 Load

shedding

Load shedding means, in contrast to operation on the public grid, the load
on the generator has to be limited to a minimum. Such partial loads
comprise for instance the emergency lights, lifts, and other emergency
systems.

background image

Configuring the Startup Software

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

27/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

5

Configuring the Startup Software

5.1 Preliminary

remark

For the startup we offer you software examples with test code and test
parameters as download. The software examples support you during the
first steps and tests with your Micro Automation Sets. They enable quick
testing of hardware and software interfaces between the products
described in the Micro Automation Sets.

The software examples are always assigned to the components used in the
set and show their basic interaction. However, they are not real applications
in the sense of technological problem solving with definable properties.

5.2

Downloading the startup code

The software examples are available on the HTML page from which you
downloaded this document.

Table 5-1

Nr.

File name

Content

1 Set_29_LOGO!_code.lsc

LOGO! Soft Comfort project
file for transfer switch

5.3 Configuring

Components

Note

It is assumed here that the necessary software has been installed on
your computer and that you are familiar with handling the software.

background image

Configuring the Startup Software

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

28/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

5.3.1

Installing and wiring hardware

Table 5-2

No.

Instructions

Note

6. Install the single components onto a

control panel

7.

For wiring purposes lay channel ducts

8.

Wire the set as explained in chapter 2


9. For the wiring of the UPS to the battery

and change-over contactor of the supply
mains please refer chapter 2.1

1

A1

A2

A3

L+

M

21 13 31 43

22 14 32 44

R3

A1

A2

R1\L1(4)

R2\L1(4)

R1\N(1)

R1\N(1)

A5\K14

L1

L2

L3

N
PE

L1

L2

L3

N

PE

Gr
id

Ge
n

e

ra

to

r

S

I 7.

5A

Sitop Smart

Sitop UPS

Sitop battery

M

L+

L+ M

X1.1
X1.2
X1.3
X1.4
X1.5
X1.6
X1.7
X1.8

chapter 2.1

10.

For the wiring of LOGO! Basic to the
expansion module DM8 and to the digital
monitoring relay please refer to chapter
2.2

R

3

\14 (

G

en

)

L

O

GO!

Log

ic

m

odul

e

24V

DC

L1

I1

N

I3

I6

I2

I5

I7

Î4

I8

Q11

Q31

Q12

Q22

Q21

Q32Q41Q42

L

O

GO!

Log

ic

m

odul

e

DM

8

L1

I1

N

I3

I2

Î4

Q11

Q31

Q12

Q22

Q21

Q32Q41Q42

L+
M

L1

L2

L3

22

24

21

12

14

11

SI
R

IU

S

Mo
ni

to

rin

g

re

la

y

R2

\S

2

B

R

1

\A

S

.X

2

.6 (

tr

ig

g

er

ed

)

R

1

\H

S

.X

2

.4 (

c

lo

s

e

d)

A6

A7

A4

Ne

tz

:L

1

Ne

tz

:L

2

Ne

tz

:L

3

R

3

\22 (

N

et

z)

R1

\S

2

B

R

2

\H

S

.X

2

.4 (

c

los

e

d)

L1

L2

L3

22

24

21

12

14

11

SI
R

IU

S

Mo
ni

to

rin

g

re

la

y

A5

Ge

n

:L

1

Ge

n

:L

2

Ge

n

:L

3

R3\A1

AC

K

S1.S2

A

uto

M

an

S

erv

S1
Ö1

S2
Ö2

S1

Net

Gen

0

S1
Ö1

S2

S2
Ö2

S2.S2

R

1

\H

S.

X2

.1

S4

4

S3

3

2

S4

1

Knob switch

Button

R

1\

S

A

:1.

\X

1.

1

R

2

\H

S.

X2

.1

S

tar

t:

G

en

\A

12

\I

0

.7

R2

\S

A

:1

.X

1

.1

4

S5

3

R

2

\A

S

.X

2

.6 (

tr

igg

e

red)

S1.S1

S5

Au

to

M

o

d

e

Of

f

S3

On

S2.S1

M

a

nua

l N

e

t

M

a

nua

l G

e

n

On

Off

Ack

A2

\X

2

.9

A

2

\X

2.

10

chapter 2.2

11.

For the wiring diagram of the circuit
breakers please refer to chapter 2.3

R2\HS.X2.2

A7\Q32

Legend:
SA = Circuit switch
HS = Auxiliary switch
AS = Alarm switch

R3\K22

L1

L2

L3

N
PE

L1

L2

L3

N

PE

Gr
id

G

enerat

or

1

2

3

4

5

6

HS.X2.1

HS.X2.2

HS.X2.3

HS.X2.4

AS.X2.5

AS.X2.6

SA:1(X1.1)

SA:2(X1.2)

R1

PE(X20.5)

S2A(X20.2)

L2-(X20.1)

L2+(X20.4)

S2B(X20.3)

M 24V

R3\K32

A6\Q12

A6\Q22

R2\S2A

A6\I7

L+ 24V

A6\I3

R1\HS.X2.2

A6\Q32

R3\K22

1

2

3

4

5

6

HS.X2.1

HS.X2.2

HS.X2.3

HS.X2.4

AS.X2.5

AS.X2.6

SA:1(X1.1)

SA:2(X1.2)

R2

PE(X20.5)

S2A(X20.2)

L2-(X20.1)

L2+(X20.4)

S2B(X20.3)

M 24V

R3\K32

A6\Q42

A7\Q22

R1\S2A

A6\I8

L+ 24V

A6\I4

chapter 2.3

background image

Configuring the Startup Software

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

29/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

No.

Instructions

Note

12.

First of all set all DIL-switches of the UPS
to OFF

+2V
+1V
+0,5V
+1V
+1V
+0,5V
+0,2V
+0,2V
+0,1V
0,2A / 0,4A

Ladestrom

(charging current)

eingestellte Zeit / max. Zeit (set time / max.)
+320s
+160s
+ 80s
+ 40s
+ 20s
+ 10s +5s fest eingestellt (fixed)
Unterbrechung output (disconnection)
Betriebszustand Akku On / Off
(operating state battery)

Zuschaltschwelle

(cut-in threshold)
+22V fest eingestellt (fixed)

Ladeschlussspannung

(end-of-charge voltage)
+ 26,3V fest eingestellt (fixed)

Pufferzeit

(buffering time)


chapter 4.3

13.

On the bottom DIL-switch of the UPS the
DIL-switches 1-5 have to be set ON

Now the buffering time is limited to 10
minutes. An unwanted discharge of the
battery is now avoided.

14.

On the bottom DIL-switch of the UPS the
DIL-switch 9 has to be set ON

5.3.2

Power supply and emergency power supply

Table 5-3

No.

Instructions

Note

15.

In this set the power supply and the
emergency power supply are carried out
by the same source. Wire the automatic
cut-out as depicted in the example.

NET

GEN

400V

background image

Configuring the Startup Software

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

30/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

5.4 Preparations

• Supply is to be carried out by the public grid

Table 5-4

Nr.

Instructions

Note

1. Make sure the 400 volt supply is still

disconnected

.

2. Make sure both circuit breakers are in

“automatic” mode.

NET / GEN

3. Make sure that the flat fuse of the battery

is installed.

4. Switch knob switch „S1“ to „service” mode

and knob switch “S2” to “0”.
In this mode LOGO! Is disabled and no
unwanted actions will occur.

ACK

S1

S2

S5

S4

S3

A

uto

S

erv

M

an

N

etz

0

G

en

CLOSE

OPEN

5. Switch the automatic cut-out “ON” for the

grid and “OFF” for the generator.

NET

GEN

6.

Switch the 400 volt supply on.

The main circuit is available.
The input of the SITOP power supply is
supplied with 220 volt.
The SITOP supplies the LOGO! with 24
volt via the UPS.
The LOGO! runs up.
Now you are in “service operation”.

7. Switch to "automatic" operation mode

using the knob switch "S1".

ACK

S1

S2

S5

S4

S3

A

uto

S

erv

M

an

N

etz

0

G

en

CLOSE

OPEN

background image

Configuring the Startup Software

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

31/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

Nr.

Instructions

Note

8. The LOGO! is now in normal operation,

meaning in mains operation with closed
circuit breaker for the mains circuit.

Supply is now carried out via the public
grid.

background image

Live-Demo

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

32/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

6 Live-Demo

The functions and features of the Micro Automation Set are displayed in
form of an example application for better understanding.

If the components have been correctly configured as described in the
previous chapters, the program code can be tested.

6.1 Overview

of all scenarios

Table 6-1

Mode

Scenario

Note

AUT

Short time grid failure

Without generator request

AUT

Grid failure without procedure error
when generator is requested

Without generator start-up error

AUT

Grid failure with procedure error
when generator is requested

With generator start-up error

AUT

Grid failure with subsequent grid
return during generator request

Grid return during generator request

MAN

Manual mode circuit breaker NET

CB NET

MAN

Manual mode circuit breaker GEN

CB GEN

SERVICE Service operation

CB NET / CB GEN

background image

Live-Demo

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

33/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

6.1.1

Scenario 1: AUT – short time grid failure

• Automatic

mode

• Supply is now carried out via the public grid.
• Public grid has short time grid failure ( < 3sec )

Table 6-2

No.

Instructions

Note

1. Supply is now carried out via the public

grid.

2. Switch the automatic cut-out “OFF” for the

public grid.

NET

GEN

< 3sec

3. The public grid drops and a voltage dip

monitoring (here 3 secs) is effected in the
LOGO!

< 3sec

4. Switch the automatic cut-out for the public

grid “ON” within the line monitoring time.

NET

GEN

< 3sec

5. The public grid returns and, due to the

short time of the voltage dip, no switch to
“emergency power operation” is effected.

background image

Live-Demo

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

34/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

6.1.2

Scenario 2: AUT - Grid failure without procedure error when generator
is requested

• Automatic

mode

• Supply is now carried out via the public grid.
• Public grid fails for longer period of time
• Generator is now responsible for the task of the public grid
• The public grid returns

Table 6-3

No.

Instructions

Note

1. Supply is now carried out via the public

grid.

2. Switch the automatic cut-out “OFF” for the

public grid.

NET

GEN

3. The public grid drops and a voltage dip

monitoring (here 3 secs) is effected in the
LOGO!

> 3sec

4. If the voltage dip monitoring is exceeded,

the switching process to “emergency
power operation” is effected in the LOGO!
and is processed as follows:
The generator for the „emergency power
grid“ is requested.
A monitoring time for the generator return
is started.
The circuit breaker for the public grid is
opened.

background image

Live-Demo

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

35/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

No.

Instructions

Note

5. The generator has to announce its

availability for emergency power
operation within this monitoring time (here
60 seconds) (simulated by switching on
the automatic cut-out “GEN”).

NET

GEN

6. As soon as the monitoring relay for the

emergency power monitors that sufficient
supply is provided, a waiting period (here
10 seconds) is activated in the LOGO!.
This is to ensure that the emergency
power grid is stable.

NET

GEN

7. The circuit breaker of the emergency

power grid is closed then.
The switching process to „emergency
power operation” is finished.
Supply is now carried out via the
generator.

8. Switch the automatic cut-out “ON” for the

public grid again.

NET

GEN

9.

The public grid returns again.

10.

As soon as the monitoring relay for the
grid power monitors that sufficient supply
is provided, a waiting period (here 10
seconds) is activated in the LOGO!. This
is to ensure that the grid power is stable.

NET

GEN

background image

Live-Demo

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

36/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

No.

Instructions

Note

11.

After this waiting period, the switching
process to “grid power operation” is
effected in the LOGO! and is processed
as follows:
A monitoring time for the grid power
operation return is started.
The circuit breaker for the emergency
power operation is opened.
The circuit breaker for the public grid is
closed.

12.

The switching process to “public grid” is
finished if the actions have been carried
out within this monitoring time (here 60
seconds) and when the circuit breaker for
the public grid announces its return.

Supply is now carried out via the public
grid again.

13.

Afterwards the generator for the
emergency power operation can be
switched off.
(Simulated by switching off the automatic
cut-out “GEN”).

NET

GEN

14.

The switching process is finished.

background image

Live-Demo

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

37/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

6.1.3

Scenario 3: AUT - Grid failure with procedure error when generator is
requested

• Automatic

mode

• Supply is now carried out via the public grid.
• Public grid fails for longer period of time
• At first the generator cannot carry out the task of the public grid
• The generator can carry out the task of the public grid on the second

attempt

• The public grid returns

Table 6-4

No.

Instructions

Note

1.

Supply is carried out via the public grid.

2. Switch the automatic cut-out “OFF” for the

public grid.

NET

GEN

3. The public grid drops and a voltage dip

monitoring (here 3 secs) is effected in the
LOGO!

> 3sec

4. If the voltage dip monitoring is exceeded,

the switching process to “emergency
power operation” is effected in the LOGO!
and is processed as follows:
The generator for the „emergency power
grid“ is requested.
A monitoring time for the generator return
is started.
The circuit breaker for the public grid is
opened.

T: 60sec

background image

Live-Demo

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

38/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

No.

Instructions

Note

5. Let the monitoring time (here 60 seconds)

for the availability of the generator pass.
(simulated by not switching on the
automatic cut-out “GEN”)

NET

GEN

> 60sec

6. As soon as the monitoring time for the

generator request is passed, the
switching process turns into a defined
error state.
The generator request for the emergency
power supply is reset.

7. Acknowledge the error with the button

“ACK”.

ACK

8. The generator request for the emergency

power grid is requested again by this
action and the monitoring time (60
seconds) for the generator return is
triggered again.

T: 60sec

9. Now you have to simulate the availability

of the generator within the monitoring time
by switching on the automatic cut-out
“GEN”.

NET

GEN

< 60 sec

10.

As soon as the monitoring relay for the
emergency power monitors that sufficient
supply is provided, a waiting period (here
10 seconds) is activated in the LOGO!.
This is to ensure that the emergency
power grid is stable.

NET

GEN

background image

Live-Demo

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

39/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

No.

Instructions

Note

11.

The circuit breaker of the emergency
power grid is closed then.
The switching process to „emergency
power operation” is finished.
Supply is now carried out via the
generator.

12.

Switch the automatic cut-out “ON” for the
public grid again.

NET

GEN

13.

The public grid returns again.

14.

As soon as the monitoring relay for the
grid power monitors that sufficient supply
is provided, a waiting period (here 10
seconds) is activated in the LOGO!. This
is to ensure that the grid power is stable.

NET

GEN

15.

After this waiting period, the switching
process to “grid power operation” is
effected in the LOGO! and is processed
as follows:
A monitoring time for the grid power
operation return is started.
The circuit breaker for the emergency
power operation is opened.
The circuit breaker for the public grid is
closed.

16.

The switching process to “public grid” is
finished if the actions have been carried
out within this monitoring time (here 60
seconds) and when the circuit breaker for
the public grid announces its return.

Supply is now carried out via the public
grid again.

background image

Live-Demo

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

40/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

No.

Instructions

Note

17.

Afterwards the generator for the
emergency power operation can be
switched off.
(simulated by switching off the automatic
cut-out “GEN”)

NET

GEN

18.

The switching process is finished.

background image

Live-Demo

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

41/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

6.1.4

Scenario 4: AUT - Grid failure with subsequent grid return during
generator request

• Automatic

mode

• Public grid fails ( > 3sec) and returns while the generator is requested
• Generator does not start operation

Table 6-5

No.

Instructions

Note

1. Supply is now carried out via the public

grid.

2. Switch the automatic cut-out “OFF” for the

public grid.

NET

GEN

3. The public grid drops and a voltage dip

monitoring (here 3 secs) is effected in the
LOGO!

> 3sec

4. If the voltage dip monitoring is exceeded,

the switching process to “emergency
power operation” is effected in the LOGO!
and is processed as follows:
The generator for the „emergency power
grid“ is requested.
A monitoring time for the generator return
is started.
The circuit breaker for the public grid is
opened.

T: 60sec

5. Now you have to simulate the return of

the public grid within the monitoring time
by switching on the automatic cut-out
“NET”.

NET

GEN

< 50sec

background image

Live-Demo

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

42/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

No.

Instructions

Note

6. The return of the public grid for the

effected generator request is ignored at
first. You have to wait for the generator to
return.

7. As soon as the monitoring time for the

generator request is passed, the
switching process turns into a defined
error state.
The generator request for the emergency
power supply is reset.

8. Acknowledge the error with the button

“ACK”.

ACK

9. By this acknowledgement the switching

process to “grid power operation” is
effected in the LOGO! and is processed
as follows:
A monitoring time for the grid power
operation return is started.
The circuit breaker for the emergency
power operation is opened.
The circuit breaker for the public grid is
closed.

10.

The switching process to “public grid” is
finished if the actions have been carried
out within this monitoring time (here 60
seconds) and when the circuit breaker for
the public grid announces its return.

Supply is now carried out via the public
grid again.

background image

Live-Demo

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

43/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

6.1.5

Scenario 5: MAN – Manual mode circuit breaker NET

Table 6-6

No.

Instructions

Note

1. Set the knob switch "S1" to mode

“manual”.

ACK

S1

S2

S5

S4

S3

A

uto

S

erv

M

an

N

etz

0

G

en

CLOSE

OPEN

2. Set the knob switch "S2" to circuit breaker

selection “Net”.

ACK

S1

S2

S5

S4

S3

A

uto

S

erv

M

an

N

etz

0

G

en

CLOSE

OPEN

3. Now you are in manual mode and the grid

circuit breaker is selected.

4. Using the „

OPEN

“ button the grid circuit

breaker is opened or loaded, respectively.

Using the „CLOSE“ button the grid circuit
breaker is closed again.

Repeat this process several times.

OPEN

CLOSE


The two circuit breakers are electrically
interlocked with each other. The grid
circuit breaker can only be closed if the
emergency power circuit breaker is
opened.

5. The final action is to open the grid circuit

breaker.

background image

Live-Demo

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

44/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

6.1.6

Scenario 6: MAN – Manual mode circuit breaker GEN

Table 6-7

No.

Instructions

Note

1. Set the knob switch "S1" to mode

“manual”.

ACK

S1

S2

S5

S4

S3

A

uto

S

erv

M

an

N

etz

0

G

en

CLOSE

OPEN

2. Set the knob switch "S2" to circuit breaker

selection “Gen”.

ACK

S1

S2

S5

S4

S3

A

uto

S

erv

M

an

N

etz

0

G

en

CLOSE

OPEN

3. Now you are in manual mode and the

emergency power circuit breaker is
selected.

4. Using the „

OPEN

“ button the emergency

power circuit breaker is opened or loaded,
respectively.

Using the „CLOSE“ button the emergency
power circuit breaker is closed again.

Repeat this process several times.

OPEN

CLOSE


The two circuit breakers are electrically
interlocked with each other. The
emergency power circuit breaker can only
be closed if the grid circuit breaker is
opened.

The final action is to open the emergency
power circuit breaker.

background image

Live-Demo

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

45/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

6.1.7

Scenario 8: SERVICE – Service operation

Table 6-8

No.

Instructions

Note

1. Make sure the circuit breakers are

powered by the public grid or by the
emergency power operation.

NET

GEN

In this scenario it is powered by the public
grid!

2. Switch the knob switch “S2“ to “0” and

knob switch “S1” to “service”.

ACK

S1

S2

S5

S4

S3

A

uto

S

erv

M

an

N

etz

0

G

en

CLOSE

OPEN


In this mode LOGO! is disabled and no
unwanted actions will occur.

3.

Now you are in “service operation”.
By this selection the circuit breakers are
powered by the public grid.
Both circuit breakers are open.

4. Switch both circuit breakers to “manual”

mode.


The circuit breakers are not interlocked
with each other. The two circuit breakers
must not be switched on at the same time
if grid voltage and generator voltage is
available.

NET

GEN

background image

Live-Demo

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

46/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

No.

Instructions

Note

5. Now for the circuit breakers of the public

grid.

Using the „

OPEN

“ button the circuit

breaker is opened or loaded, respectively.
Using the „CLOSE“ button the circuit
breaker is closed again.

Repeat this process several times.

The final action is to open the grid circuit
breaker.

NET

6. Now for the circuit breaker of the

generator

Using the „

OPEN

“-button the circuit

breaker is opened or loaded, respectively.
Using the „CLOSE“-button the circuit
breaker is closed again.

Repeat this process several times.

The final action is to open the emergency
power circuit breaker.

GEN

7. The scenario for this service operation is

now completed.

Both circuit breakers are open.

background image

Technical data

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

47/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

7 Technical

data

7.1 SITOP

Table 7-1

Criterion

Technical data

Additional note

SITOP Power

INPUT VOLTAGE :
AC120/230V, 50/60Hz
OUTPUT VOLTAGE: 24V+/-
3%
PERMISSIBLE RANGE :
93...132/187...264V
ADJUSTMENT RANGE :
22.8...26.4V

SITOP DC-UPS-Module 6

SITOP DC-UPS-MODULE 24V
/ 6A WITH POTENTIAL-FREE
USB-INTERFACE INPUT: DC
24V / 6.85A OUTPUT: DC 24V
/ 6A

SITOP POWER BATTERY
MODULE

SITOP POWER BATTERY
MODULE 1.2 AH WITH
MAINTENANCE-FREE,
SEALED LEAD BATTERIES
FOR SITOP POWER DC-
UPS-MODULE 6

7.2 LOGO!

Table 7-2

Criterion

Technical data

Additional note

LOGO! logic module
(12/24RC)

PS/ I/O DC12/24V / DC12/24V
/ relay 8DE (2AE 0..10V)/4DA

Logic module with display
and keys
130 blocks
expandable in modules

LOGO! DM8 24R EXPANSION
MODULE

PS/ I/O AC/DC 24V / AC/DC
24V PNP and NPN / relay
4DE/4DA

2TE

background image

Technical data

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

48/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

7.3 SENTRON

Table 7-3

Criterion

Technical data

Additional note

SENTRON circuit breaker VL
160N

ICU=40kA, 415V AC 3-pin,
Shunt trip 24V AC/DC auxiliary
switch installation set 2 HS
(1NO+1NC)

Plant protection
over current release TM, LI
IN=50A, rated current
IR=40...50A,
Overload protection
II=300...600A, short circuit
protection, protection

Motorized operating
mechanism with spring energy
store

220...250V AC/DC

7.4 SIRIUS

Table 7-4

Criterion

Technical data

Additional note

SIRIUS monitoring relay 3UG4

PHASE FAILURE 3X 160 TO
690V AC 50 TO 60 HZ
UNDERVOLTAGE AND
OVERVOLTAGE 160-690V
HYSTERESIS 1-20V
OFF-DELAY 0-20S
ASYMMETRY 0-20%
1W FOR PHASE
CORRECTION
1 W FOR GRID ERROR

DIGITAL MONITORING
RELAY FOR 3-PHASE
GRID VOLTAGE
AUTOMATIC
CORRECTION OF PHASE
SEQUENCE
SCREW CONNECTION

Contactor

2NO+2NC, DC 24V

SCREW CONNECTION

Resetting element

RC ELEMENT AC 24...48V,
DC 24...70V

SURGE SUPPRESSOR
FOR PLUGGING ONTO
CONTACTORS

background image

Technical data

Micro Automation Set 29

Beitrags-ID 27074055

V01.00 05.11.2007

49/49

C

opyr

ight

©

Si

em

ens

AG 2

007

Al

l r

ights r

e

s

e

rv

ed

Set2

9_D

ocT

e

ch_v

1d3

_

en.

doc

7.5

Instruction and display devices

Table 7-4

Criterion

Technical data

Additional note

Knob switch

ACTUATING ANGLE 2 X 50
DEGREES BLACK,
1NO, 1NO WITH SUPPORT

COMPLETE UNIT,
ROUND KNOB SWITCH,
I-O-II, LATCHING,
SCREW CONNECTION

Push button (yellow)

1NO WITH SUPPORT

COMPLETE UNIT,
ROUND PUSH BUTTON
WITH FLAT BUTTON
YELLOW, SCREW
CONNECTION

Push button (green)

1NO WITH SUPPORT

COMPLETE UNIT,
ROUND PUSH BUTTON
WITH FLAT BUTTON
GREEN, SCREW
CONNECTION

Push button (red)

1NC WITH SUPPORT

COMPLETE UNIT,
ROUND PUSH BUTTON
WITH FLAT BUTTON
RED, SCREW
CONNECTION


Document Outline


Wyszukiwarka

Podobne podstrony:
Automatyka Budynkow MAS8 id 732 Nieznany
Automatyka budynkowa wybrane systemy inteligentnych instalacji elektrycznych A Klajn
Automatyka Budynkow MAS28
automatyka budynkowa
Firma BNT z Sosnowca, system automatyki budynkowej LOOX
Automatyka Budynku broszura
Automatyzacja w KiC (w 12) Zarzadzanie energia w budynkach
FESTO Podstawy automatyzacji
Automatyka (wyk 3i4) Przel zawory reg
Automatyzacja w KiC (w 2) Obiekty reg
AutomatykaII 18

więcej podobnych podstron