Lp. |
Podst. wyceny przez Zamaw. |
Opis i wyliczenia |
j.m. |
Poszcz |
Razem |
1 |
|
PARTER |
|
|
|
1.01.2008 |
45262410-8 |
ROBOTY KONSTRUKCYJNE |
|
|
|
1.01.2001 |
|
ŚCIANY |
|
|
|
1 d.1.1.1 |
KNR 4-01 0349-02 |
Rozebranie ścian,filarów i kolumn z cegieł na zaprawie cementowo-wapiennej |
m3 |
|
|
|
|
0.25*4.0*2.35 |
m3 |
2.350 |
|
|
|
0.23*0.48*2.35 |
m3 |
0.259 |
|
|
|
0.10*0.48*2.35 |
m3 |
0.113 |
|
|
|
0.21*0.48*2.35 |
m3 |
0.237 |
|
|
|
0.22*0.48*2.35 |
m3 |
0.248 |
|
|
|
0.50*0.55*2.35 |
m3 |
0.646 |
|
|
|
0.17*0.52*2.0 |
m3 |
0.177 |
|
|
|
<ściany kl. schod.>(0.15*4.25*3.0)+(0.15*4.10*3.25)+(0.15*3.25*3.25) |
m3 |
5.496 |
|
|
|
0.25*3.0*4.10 |
m3 |
3.075 |
|
|
|
0.20*0.41*3.0 |
m3 |
0.246 |
|
|
|
|
|
RAZEM |
12.847 |
2 d.1.1.1 |
KNR 4-01 0348-03 |
Rozebranie ścianki z cegieł o grub. 1/2 ceg. na zaprawie cementowo-wapiennej |
m2 |
|
|
|
|
(1.21*2.10)+(3.0*2.0)+(3.0*1.20)+(3.0*3.43)+(3.0*3.45)+(3.0*3.60)+(3.0*1.40) |
m2 |
47.781 |
|
|
|
|
|
RAZEM |
47.781 |
3 d.1.1.1 |
KNR 4-01 0348-02 |
Rozebranie ścianki z cegieł o grub. 1/4 ceg. na zaprawie cementowo-wapiennej |
m2 |
|
|
|
|
(3.20*4.17)+(3.0*1.50)+(3.0*1.25)+(3.0*1.25)+(3.0*1.70) |
m2 |
30.444 |
|
|
|
|
|
RAZEM |
30.444 |
4 d.1.1.1 |
KNR 4-01 0304-01 |
Uzupełnienie ścian lub zamurowanie otworów w ścianach na zaprawie cementowo-wapiennej cegłami |
m3 |
|
|
|
|
(3.20*0.50*0.40)+(3.20*0.50*0.40)+(2.0*0.46*0.86)+(0.43*1.15*1.45) |
m3 |
2.788 |
|
|
|
|
|
RAZEM |
2.788 |
5 d.1.1.1 |
KNR 2-02 0103-01 |
Ściany budynków jednokondygnacyjnych o wysokości do 4.5 m z cegieł pełnych na zaprawie wapiennej lub cementowo-wapiennej grubości 1 ceg. |
m2 |
|
|
|
|
3.0*(1.48+1.58) |
m2 |
9.180 |
|
|
|
-1.0*2.0*2.0 |
m2 |
-4.000 |
|
|
|
|
|
RAZEM |
5.180 |
6 d.1.1.1 |
KNR 2-02 0103-02 |
Ściany budynków jednokondygnacyjnych o wysokości do 4.5 m z cegieł pełnych na zaprawie wapiennej lub cementowo-wapiennej grubości 1 1/2 ceg. |
m2 |
|
|
|
|
3.0*1.72 |
m2 |
5.160 |
|
|
|
-1.10*2.0 |
m2 |
-2.200 |
|
|
|
|
|
RAZEM |
2.960 |
7 d.1.1.1 |
KNR 2-02 0219-05 |
Nadproża nad tablicami elektrycznymi o średniej grubości 6 cm |
m2 |
|
|
|
|
0.18*1.25*1.0 |
m2 |
0.225 |
|
|
|
|
|
RAZEM |
0.225 |
8 d.1.1.1 |
KNR 2-02 0290-01 |
Przygotowanie i montaż zbrojenia elementów budynków i budowli - pręty gładkie |
t |
|
|
|
|
0.002 |
t |
0.002 |
|
|
|
|
|
RAZEM |
0.002 |
9 d.1.1.1 |
KNR 4-01 0313-04 |
Wykonanie przesklepień otworów w ścianach z cegiel - dostarcz.i obsadz.belek stalowych do I NP 180 mm |
m |
|
|
|
|
<POZ 3.1>1.75*4.0*3.0 |
m |
21.000 |
|
|
|
<POZ 3.2>3.30*1.0*3.0 |
m |
9.900 |
|
|
|
<POZ 3.1E>1.75*1.0*3.0 |
m |
5.250 |
|
|
|
|
|
RAZEM |
36.150 |
10 d.1.1.1 |
KNR 4-01 0703-01 |
Umocowanie siatki cięto-ciągnionej na ścianach,filarach,pilastrach |
m2 |
|
|
|
|
<POZ 3.1>(0.40+0.42)*1.75*4.0 |
m2 |
5.740 |
|
|
|
<POZ 3.2>(0.40+0.44)*3.30*1.0 |
m2 |
2.772 |
|
|
|
<POZ 3.1E>(0.40+0.35)*1.75*1.0 |
m2 |
1.313 |
|
|
|
|
|
RAZEM |
9.824 |
11 d.1.1.1 |
KNR 4-01 0704-01 |
Powlekanie siatki cięto-ciągnionej na ścianach i stropach zaprawą cementową |
m2 |
|
|
|
|
9.824 |
m2 |
9.824 |
|
|
|
|
|
RAZEM |
9.824 |
12 d.1.1.1 |
KNR 4-01 0716-01 |
Tynki wewn.zwykłe kat. III wykonyw.ręcznie na belkach stalowych, filarach. |
m2 |
|
|
|
|
9.824 |
m2 |
9.824 |
|
|
|
|
|
RAZEM |
9.824 |
1.01.2002 |
|
PODKŁADY POD POSADZKI |
|
|
|
13 d.1.1.2 |
KNR 4-01 0428-03 |
Rozebranie podłóg białych na wpust |
m2 |
|
|
|
|
46.29+46.02+31.33+24.70 |
m2 |
148.340 |
|
|
|
|
|
RAZEM |
148.340 |
14 d.1.1.2 |
KNR 4-01 0428-04 |
Rozebranie legarów |
m |
|
|
|
|
148.340*1.31<m/m2> |
m |
194.325 |
|
|
|
|
|
RAZEM |
194.325 |
15 d.1.1.2 |
KNR 4-01 0811-07 |
Rozebranie posadzki z płytek na zaprawie cementowej |
m2 |
|
|
|
|
4.10+9.02+5.85+6.71 |
m2 |
25.680 |
|
|
|
|
|
RAZEM |
25.680 |
16 d.1.1.2 |
KNR 4-01 0818-05 |
Zerwanie posadzki z tworzyw sztucznych |
m2 |
|
|
|
|
20.020 |
m2 |
20.020 |
|
|
|
|
|
RAZEM |
20.020 |
17 d.1.1.2 |
KNR 2-02 1101-01 |
Podkłady betonowe na podłożu gruntowym |
m3 |
|
|
|
|
(46.29+46.02+31.33+24.70)*0.10 |
m3 |
14.834 |
|
|
|
|
|
RAZEM |
14.834 |
18 d.1.1.2 |
KNR 2-02 0604-05 |
Izolacje przeciwwilgociowe z papy powierzchni poziomych na lepiku na zimno - pierwsza warstwa |
m2 |
|
|
|
|
46.29+46.02+31.33+24.70 |
m2 |
148.340 |
|
|
|
|
|
RAZEM |
148.340 |
19 d.1.1.2 |
KNR 2-02 0609-03 |
Izolacje cieplne i przeciwdźwiękowe z płyt styropianowych poziome na wierzchu konstrukcji na sucho - jedna warstwa |
m2 |
|
|
|
|
46.29+46.02+31.33+24.70 |
m2 |
148.340 |
|
|
|
|
|
RAZEM |
148.340 |
20 d.1.1.2 |
KNR 2-02 0607-01 |
Izolacje przeciwwilgoc.i przeciwwodne z folii polietylen.szerokiej poziome podposadzkowe |
m2 |
|
|
|
|
46.29+46.02+31.33+24.70 |
m2 |
148.340 |
|
|
|
|
|
RAZEM |
148.340 |
21 d.1.1.2 |
KNR 2-02 1106-02 |
Posadzki cementowe wraz z cokolikami zatarte na gładko gr.25mm |
m2 |
|
|
|
|
46.29+46.02+31.33+24.70 |
m2 |
148.340 |
|
|
|
|
|
RAZEM |
148.340 |
22 d.1.1.2 |
KNR 2-02 1106-03 |
Posadzki cementowe wraz z cokolikami zatarte - pogrubienie posadzki o 1cm Krotność = 1.5 |
m2 |
|
|
|
|
46.29+46.02+31.33+24.70 |
m2 |
148.340 |
|
|
|
|
|
RAZEM |
148.340 |
23 d.1.1.2 |
KNR 2-02 1106-07 |
Posadzki cementowe wraz z cokolikami - dopłata za zbrojenie siatką stalową |
m2 |
|
|
|
|
46.29+46.02+31.33+24.70 |
m2 |
148.340 |
|
|
|
|
|
RAZEM |
148.340 |
1.02.2009 |
45400000-1 |
ROBOTY WYKOŃCZENIOWE |
|
|
|
1.02.2001 |
|
ŚCIANKI DZIAŁOWE |
|
|
|
24 d.1.2.1 |
KNR AT-12 0103-03 |
Ścianki działowe z płyt gipsowo-kartonowych NIDA na pojedynczej konstrukcji nośnej, z pokryciem obustronnym jednowarstwowym 100-01; System NIDA Ściana 125A100 GR 12 CM. |
m2 |
|
|
|
|
3.0*(1.18+7.90+2.35+2.45+3.57+1.60+3.60+1.40+1.0) |
m2 |
75.150 |
|
|
|
-1.0*2.0*5.0 |
m2 |
-10.000 |
|
|
|
-0.90*2.0*1.0 |
m2 |
-1.800 |
|
|
|
3.13*(0.60+2.10+0.80) |
m2 |
10.955 |
|
|
|
|
|
RAZEM |
74.305 |
25 d.1.2.1 |
KNR AT-12 0302-01 |
Obudowy szybów instalacyjnych z płyt gipsowo-kartonowych NIDA Ogień na konstrukcji nośnej NIDA C50 - system NIDA Szacht 75X50 o odporności ogniowej F 0,5/EI 30 |
m2 |
|
|
|
|
OBUDOWA PRZEWODÓW WENTYLACYJNECH I PIONÓW INSTALACYJNYCH |
|
|
|
|
|
3.0*(1.20+0.47+0.47) |
m2 |
6.420 |
|
|
|
3.13*(0.55+0.63) |
m2 |
3.693 |
|
|
|
|
|
RAZEM |
10.113 |
1.02.2002 |
|
TYNKI I OKŁADZINY |
|
|
|
26 d.1.2.2 |
KNR 4-01 0426-04 analogia |
Rozebranie boazerii ze sklejki. |
m2 |
|
|
|
|
1.33*(27.94+27.93+22.40+20.10+26.32+17.14+12.76+15.35) |
m2 |
226.020 |
|
|
|
|
|
RAZEM |
226.020 |
27 d.1.2.2 |
KNR-W 4-01 0820-08 |
Rozebranie okładziny ściennej -glazura. |
m2 |
|
|
|
|
2.0*(9.72+10.05+5.72+4.21+4.17+10.45+4.28+4.22+8.51) |
m2 |
122.660 |
|
|
|
-1.0*2.0*15.00 |
m2 |
-30.000 |
|
|
|
|
|
RAZEM |
92.660 |
28 d.1.2.2 |
KNR 4-01 0701-10 |
Odbicie tynków wewnętrznych z zaprawy wapiennej na stropach płaskich, belkach, biegach i spocznikach schodów ponad 5 m2 |
m2 |
|
|
|
|
BRYŁA A |
|
|
|
|
|
24.25+30.99+45.40+46.95+39.62+23.78 |
|
210.990 |
|
|
|
A (obliczenia pomocnicze) |
|
|
= |
|
|
|
|
210.990 |
|
|
|
210.99*50% |
m2 |
105.495 |
|
|
|
B (suma częściowa) |
|
|
- |
|
|
|
m2 |
105.495 |
|
|
|
|
|
RAZEM |
105.495 |
29 d.1.2.2 |
KNR 4-01 0701-05 |
Odbicie tynków wewnętrznych z zaprawy cementowo-wapiennej na ścianach, filarach, pilastrach o powierzchni odbicia ponad 5 m2 |
m2 |
|
|
|
|
3.0*(18.47+44.15+10.10+9.06) |
|
245.340 |
|
|
|
-1.0*2.0*7.0 |
|
-14.000 |
|
|
|
A (obliczenia pomocnicze) |
|
|
= |
|
|
|
|
231.340 |
|
|
|
|
|
|
|
|
|
231.340*20% |
m2 |
46.268 |
|
|
|
B (suma częściowa) |
|
|
- |
|
|
|
m2 |
46.268 |
|
|
|
|
|
|
|
|
|
|
|
RAZEM |
46.268 |
30 d.1.2.2 |
KNR 9-03 0302-01 |
Wyprawy tynkarskie wykonywane na stropach sposobem maszynowym jednowarstwowe gr. 10 mm wapienne i cem.-wap. zatarte |
m2 |
|
|
|
|
105.50 |
m2 |
105.500 |
|
|
|
|
|
RAZEM |
105.500 |
31 d.1.2.2 |
KNR 9-03 0109-02 |
Dodatek za zmianę gr. tynku o 1 mm - wyprawa cem.-wap. i cem. wykonywana maszynowo Krotność = 5 |
m2 |
|
|
|
|
105.50 |
m2 |
105.500 |
|
|
|
|
|
RAZEM |
105.500 |
32 d.1.2.2 |
KNR 9-03 0102-01 |
Wyprawy tynkarskie wykonywane na ścianach sposobem maszynowym jednowarstwowe gr. 10 mm wapienne i cem.-wap. zatarte |
m2 |
|
|
|
|
46.268 |
m2 |
46.268 |
|
|
|
|
|
RAZEM |
46.268 |
33 d.1.2.2 |
KNR 9-03 0109-02 |
Dodatek za zmianę gr. tynku o 1 mm - wyprawa cem.-wap. i cem. wykonywana maszynowo Krotność = 5 |
m2 |
|
|
|
|
46.268 |
m2 |
46.268 |
|
|
|
|
|
RAZEM |
46.268 |
34 d.1.2.2 |
KNR K-04 0104-01 |
Ochrona narożników wypukłych prostych kątownikiem |
m |
|
|
|
|
0.52<mb/m2>*491.946 |
m |
255.812 |
|
|
|
|
|
RAZEM |
255.812 |
35 d.1.2.2 |
KNR-W 2-02 0830-06 |
Wewnętrzne gładzie gipsowe dwuwarstwowe na sufitach. |
m2 |
|
|
|
|
371.72 |
m2 |
371.720 |
|
|
|
|
|
RAZEM |
371.720 |
36 d.1.2.2 |
KNR-W 2-02 0830-04 |
Wewnętrzne gładzie gipsowe dwuwarstwowe na ścianach . |
m2 |
|
|
|
|
231.340+445.67 |
m2 |
677.010 |
|
|
|
|
|
RAZEM |
677.010 |
37 d.1.2.2 |
KNR-W 2-02 0840-05 |
Licowanie ścian płytkami z kamieni sztucznych o wym. 20x25 cm na zaprawie klejowej |
m2 |
|
|
|
|
<łazienki>2.0*(21.45+7.34+8.42+5.02+10.41+10.46) |
m2 |
126.200 |
|
|
|
-1.0*2.0*6.0 |
m2 |
-12.000 |
|
|
|
<ciągi technologiczne>0.80*(7.85+2.26+1.0+1.0+1.0+1.0) |
m2 |
11.288 |
|
|
|
|
|
RAZEM |
125.488 |
1.02.2003 |
|
MALOWANIE |
|
|
|
38 d.1.2.3 |
KNR-W 2-02 1510-03 |
Dwukrotne malowanie farbami emulsyjnymi powierzchni wewnętrznych - podłoży gipsowych z gruntowaniem |
m2 |
|
|
|
|
<sufity>101.340+270.38 |
m2 |
371.720 |
|
|
|
<ściany>677.01 |
m2 |
677.010 |
|
|
|
<ścianki działowe>74.305*2.0 |
m2 |
148.610 |
|
|
|
<obudowa pinów, kominów>10.113 |
m2 |
10.113 |
|
|
|
|
|
RAZEM |
1207.453 |
1.02.2004 |
|
POSADZKI |
|
|
|
39 d.1.2.4 |
NNRNKB 202 1136-01 |
(z.VIII) Posadzki z paneli podłogowych |
m2 |
|
|
|
|
198.27 |
m2 |
198.270 |
|
|
|
|
|
RAZEM |
198.270 |
40 d.1.2.4 |
KNR 0-12 1118-03 |
Posadzki z płytek o wymiarach 30 x 30 cm, układanych metodą zwykłą (TERAKOTA) |
m2 |
|
|
|
|
138.00 |
m2 |
138.000 |
|
|
|
|
|
RAZEM |
138.000 |
41 d.1.2.4 |
KNR 0-12 1119-02 |
Cokoliki, z płytek o wymiarach 30 x 30 cm i wysokości cokolika równej 15 cm (TERAKOTA) |
m |
|
|
|
|
1.16<m/m2>*48.30 |
m |
56.028 |
|
|
|
|
|
RAZEM |
56.028 |
1.02.2005 |
|
ELEMENTY KOWALSKO ŚLUSARSKIE |
|
|
|
42 d.1.2.5 |
KNR 4-01 1306-01 |
Demontaż balustrad schodowych i balkonowych oraz konstrukcji schodów i świetlików stalowych |
szt. |
|
|
|
|
(6.50+4.40+2.05)*10.0 |
szt. |
129.500 |
|
|
|
|
|
RAZEM |
129.500 |
43 d.1.2.5 |
KNR 2-02 1207-03 |
Balustrady schodowe z prętów stalowych osadzone i zabetonowane w co trzecim stopniu o masie do 14 kg |
m |
|
|
|
|
6.50+4.40+2.05 |
m |
12.950 |
|
|
|
|
|
RAZEM |
12.950 |
44 d.1.2.5 |
KNR 4-01 0914-02 |
Poręcz schodowa z drewna twardego |
m |
|
|
|
|
6.50+4.40+2.05 |
m |
12.950 |
|
|
|
|
|
RAZEM |
12.950 |
45 d.1.2.5 |
KNR 2-02 1208-03 |
Pochwyt stalowy na wspornikach |
m |
|
|
|
|
2.67+2.67+5.11 |
m |
10.450 |
|
|
|
|
|
RAZEM |
10.450 |
46 d.1.2.5 |
KNR 2-02 1219-03 |
Wycieraczki do obuwia typowe 0.27 m2 ACO lub równoważny. |
szt. |
|
|
|
|
2.000 |
szt. |
2.000 |
|
|
|
|
|
RAZEM |
2.000 |
47 d.1.2.5 |
analiza indywidualna |
Montaż uchwytów dla osób niepełnosprawnych w łazienkach. |
szt |
|
|
|
|
8.000 |
szt |
8.000 |
|
|
|
|
|
RAZEM |
8.000 |
1.02.2006 |
|
STOLARKA OKIENNA I DRZWIOWA |
|
|
|
48 d.1.2.6 |
KNR 4-01 0354-05 |
Wykucie z muru ościeżnic drewnianych o powierzchni ponad 2 m2 |
m2 |
|
|
|
|
1.40*2.0*6.0+1.40*2.0*4.0+1.10*2.0*2.0+1.40*2.0*2.0+1.15*1.20+1.15*1.45*3.0+1.10*1.20*4.0+1.15*1.45*3.0+1.15*1.20 |
m2 |
56.045 |
|
|
|
|
|
RAZEM |
56.045 |
49 d.1.2.6 |
KNR 0-19 1023-09 |
Montaż okien rozwieranych i uchylno-rozwieranych dwudzielnych z PCV z obróbką obsadzenia o pow. do 2.0 m2 |
m2 |
|
|
|
|
<07>1.15*1.45*5.0 |
m2 |
8.338 |
|
|
|
<08>1.15*1.20*5.0 |
m2 |
6.900 |
|
|
|
<09>1.10*1.20*1.0 |
m2 |
1.320 |
|
|
|
|
|
RAZEM |
16.558 |
50 d.1.2.6 |
KNR 0-19 1023-10 |
Montaż okien rozwieranych i uchylno-rozwieranych dwudzielnych z PCV z obróbką obsadzenia o pow. do 2.5 m2 |
m2 |
|
|
|
|
<05>1.40*2.0*12.0 |
m2 |
33.600 |
|
|
|
<06>1.10*2.0*2.0 |
m2 |
4.400 |
|
|
|
<10>1.40*1.90*1.0 |
m2 |
2.660 |
|
|
|
|
|
RAZEM |
40.660 |
51 d.1.2.6 |
KNR 4-01 0321-01 |
Obsadzenie podokienników z postformingu w ścianach z cegieł |
m |
|
|
|
|
1.40*12.0+1.10*2.0+1.40*1.0 |
m |
20.400 |
|
|
|
|
|
RAZEM |
20.400 |
52 d.1.2.6 |
KNR 4-01 0354-04 |
Wykucie z muru ościeżnic drewnianych o powierzchni do 2 m2 - drzwi |
szt. |
|
|
|
|
18.00 |
szt. |
18.000 |
|
|
|
|
|
RAZEM |
18.000 |
53 d.1.2.6 |
KNR 4-01 0318-02 |
Obsadzenie ościeżnic drewnianych o pow.otworu do 2.0 m2 w ścianach wewnętrznych z cegieł z opaskami i ćwierćwałkami w komplecie. |
szt. |
|
|
|
|
15.00 |
szt. |
15.000 |
|
|
|
|
|
RAZEM |
15.000 |
54 d.1.2.6 |
KNR-W 2-02 1022-01 |
Skrzydła drzwiowe płytowe wewnętrzne pełne jednoskrzydłowe fabrycznie wykończone. |
m2 |
|
|
|
|
<D1>1.10*2.05*6.0 |
m2 |
13.530 |
|
|
|
<D2>0.90*2.05*3.0 |
m2 |
5.535 |
|
|
|
<D3>1.0*2.05*2.0 |
m2 |
4.100 |
|
|
|
<D4 KW>0.90*2.05*2.0 |
m2 |
3.690 |
|
|
|
<D5>0.80*2.05*1.0 |
m2 |
1.640 |
|
|
|
<D7>1.10*2.05*1.0 |
m2 |
2.255 |
|
|
|
|
|
RAZEM |
30.750 |
55 d.1.2.6 |
KNR 4-01 0920-20 |
Założenie na nowym miejscu klamek z szyldami |
szt. |
|
|
|
|
15.00 |
szt. |
15.000 |
|
|
|
|
|
RAZEM |
15.000 |
56 d.1.2.6 |
KNR 4-01 0920-27 |
Założenie na nowym miejscu wkładek do zamków |
szt. |
|
|
|
|
15.00 |
szt. |
15.000 |
|
|
|
|
|
RAZEM |
15.000 |
57 d.1.2.6 |
KNR-W 2-02 1040-02 |
Drzwi aluminiowe DZ. |
m2 |
|
|
|
|
<DZ1>1.39*2.05*1.0 |
m2 |
2.850 |
|
|
|
<DZ3>1.10*2.05*1.0 |
m2 |
2.255 |
|
|
|
|
|
RAZEM |
5.105 |
58 d.1.2.6 |
KNR-W 2-02 1016-07 |
Wyłazy dachowe fabrycznie wykończone "VELUX" lub równoważne |
szt |
|
|
|
|
1.000 |
szt |
1.000 |
|
|
|
|
|
RAZEM |
1.000 |
59 d.1.2.6 |
NNRNKB 202 1027-01 |
(z.VI) Okna dachowe "FAKRO" lub równoważne. |
kpl. |
|
|
|
|
2.000 |
kpl. |
2.000 |
|
|
|
|
|
RAZEM |
2.000 |
2 |
|
PRZEWODY WENTYLACYJNE |
|
|
|
60 d.2 |
KNR 2-02 0510-04 analogia |
Rury wentylacyjne izolowane spiro o śr. 15 cm. |
m |
|
|
|
|
9.95*2.0+6.60*2.0 |
m |
33.100 |
|
|
|
6.60*4.0 |
m |
26.400 |
|
|
|
3.60*1.0 |
m |
3.600 |
|
|
|
4.45*2.0 |
m |
8.900 |
|
|
|
|
|
RAZEM |
72.000 |
61 d.2 |
KNR 2-05 0208-02 |
Konstrukcje stalowa osłon przewodów wentylacyjnych o masie elementu do 10 kg. |
t |
|
|
|
|
0.657 |
t |
0.657 |
|
|
|
|
|
RAZEM |
0.657 |
62 d.2 |
KNR 0-21 4007-02 |
Obudowa przewodów wentylacyjnych z płyt OSB GR. 22 MM. |
m2 |
|
|
|
|
2.80*3.02+2.34*1.95+1.05*1.95+1.71*2.23+1.62*2.23 |
m2 |
22.492 |
|
|
|
0.60+0.30+0.32+0.17 |
m2 |
1.390 |
|
|
|
|
|
RAZEM |
23.882 |
63 d.2 |
NNRNKB 202 0541-02 |
(z.VI) Obróbki blacharskie z blachy powlekanej o szer.w rozwinięciu ponad 25 cm (czapki z blachy powlekanej) |
m2 |
|
|
|
|
0.60+0.30+0.32+0.17 |
m2 |
1.390 |
|
|
|
|
|
RAZEM |
1.390 |
64 d.2 |
KNR K-04 0102-01 |
Przyklejenie płyt styropianowych na ścianach 4 CM (obudowa przewodów wentylacyjnych). |
m2 |
|
|
|
|
2.80*3.02+2.34*1.95+1.05*1.95+1.71*2.23+1.62*2.23 |
m2 |
22.492 |
|
|
|
|
|
RAZEM |
22.492 |
65 d.2 |
KNR K-04 0105-03 |
Wykonanie tynków mineralnych cienkowarstwowych na gotowym podłożu z zaprawy Poztynk SZ o uziarnieniu 2 mm i fakturze baranek |
m2 |
|
|
|
|
2.80*3.02+2.34*1.95+1.05*1.95+1.71*2.23+1.62*2.23 |
m2 |
22.492 |
|
|
|
|
|
RAZEM |
22.492 |
66 d.2 |
KNR K-04 0202-05 |
Dwukrotne malowanie powierzchni zewnętrznych tynków fakturowych bez gruntowania (farbami silikatowymi). |
m2 |
|
|
|
|
2.80*3.02+2.34*1.95+1.05*1.95+1.71*2.23+1.62*2.23 |
m2 |
22.492 |
|
|
|
|
|
RAZEM |
22.492 |
3 |
|
POCHYLNIA DLA NIEPEŁNOSPRAWNYCH |
|
|
|
67 d.3 |
NNRNKB 202 0541-02 |
(z.VI) Obróbki blacharskie z blachy powlekanej o szer.w rozwinięciu ponad 25 cm PARAPETY. |
m2 |
|
|
|
|
0.30*(0.90*3.0+0.90*2.0+0.80*4.0+1.40*12.0+1.10*2.0+1.15*10.0+1.10*1.0+1.40*1.0+0.65*3.0+1.70*2.0+0.90*1.0+1.30*1.0+1.45*1.0+1.15*9.0+1.15*1.0+1.10*2.0) |
m2 |
19.020 |
|
|
|
|
|
RAZEM |
19.020 |
68 d.3 |
KNR-W 4-01 0212-04 |
Mechaniczna rozbiórka elementów konstrukcji betonowych niezbrojonych o grubości ponad 15 cm |
m3 |
|
|
|
|
schody zewnętrzne |
|
|
|
|
|
0.30*0.77*2.02 |
m3 |
0.467 |
|
|
|
0.30*0.30*1.70 |
m3 |
0.153 |
|
|
|
|
|
RAZEM |
0.620 |
69 d.3 |
KNR 2-02 0206-01 |
Ściany betonowe proste grubości 20 cm wysokości do 3 m - ręczne układanie betonu POCHYLNIA |
m2 |
|
|
|
|
0.70*(5.35+8.10) |
m2 |
9.415 |
|
|
|
|
|
RAZEM |
9.415 |
70 d.3 |
KNNR 6 0106-05 |
Warstwy odcinające zagęszczane mechanicznie o grubości 10 cm POCHYLNIA |
m2 |
|
|
|
|
8.300 |
m2 |
8.300 |
|
|
|
|
|
RAZEM |
8.300 |
71 d.3 |
KNNR 6 0502-02 |
Chodniki z kostki brukowej betonowej grubości 6 cm na podsypce cementowo-piaskowej z wypełnieniem spoin piaskiem POCHYLNIA |
m2 |
|
|
|
|
8.300 |
m2 |
8.300 |
|
|
|
|
|
RAZEM |
8.300 |
72 d.3 |
KNR 2-02 1208-03 |
Pochwyt stalowy na wspornikach POCHYLNIA. |
m |
|
|
|
|
5.80+8.50 |
m |
14.300 |
|
|
|
|
|
RAZEM |
14.300 |
73 d.3 |
KNR 0-12 1120-03 |
Okładziny schodów z płytek o wymiarach 30 x 30 cm, układanych metodą zwykłą (GRES) |
m2 |
|
|
|
|
6.15+(0.15*2.0*2.92+0.30*2.92) |
m2 |
7.902 |
|
|
|
1.60+(0.15*3.0*1.83+0.33*2.0*1.83) |
m2 |
3.631 |
|
|
|
2.45*(0.15*3.26+0.15*3.80+0.30*3.80) |
m2 |
5.388 |
|
|
|
|
|
RAZEM |
16.921 |
74 d.3 |
KNR 0-12 1119-05 |
Cokoliki, na schodach z płytek o wymiarach 30 x 30 cmi wysokości cokolika równej 15 cm (GRES) |
m |
|
|
|
|
1.16<m/m2>*23.821 |
m |
27.632 |
|
|
|
|
|
RAZEM |
27.632 |