CSPS Iteration Plan 3.0
backPath = './../../';
Online Collegiate Paging Service
Iteration Plan
Version 3.0
Revision History
Date
Version
Description
Author
October 6, 1999
1.0
Initial version
Context Integration
October 27, 1999
2.0
Updated at start of Elaboration
Context Integration
November 20, 1999
3.0
Updated at start of first Construction iteration
Context Integration
Table of Contents
Introduction
Plan
Resources
Use Cases
Evaluation Criteria
Iteration Plan
Introduction
Purpose
This Iteration Plan describes the detailed plans for the first Construction
Iteration of the Collegiate Sports Paging System Project. During this iteration,
the four most critical use cases will be developed.
Scope
The first Construction Iteration Plan applies to the Collegiate Sports Paging
System project being developed by Context Integration for WebNewsOnLine . This
document will be used by the Project Manager and by the project team.
Definitions, Acronyms and Abbreviations
See Glossary document.
References
CSPS Use Case - Approve Story 1.0
CSPS Use Case - Edit Profile 1.0
CSPS Use Case - Read Content on Website 1.0
CSPS Use Case - Send Content 1.0
CSPS Use Case - Send Page 1.0
CSPS Supplementary Specification 1.0
Plan
The Construction Iteration will complete the four most critical use cases in
the Collegiate Sports Paging System.
Iteration Tasks
The following table illustrates the tasks with their planned start and end
dates.
Task
Start
End
Construction Kick-off
Mon 11/29/99
Tue 11/30/99
Bring Full development team on board
Mon 11/29/99
Mon 11/29/99
Bring Full Testing staff on board
Mon 11/29/99
Mon 11/29/99
Construction Kick-off Meeting
Mon 11/29/99
Tue 11/30/99
Prepare for construction kick-off meeting
Mon 11/29/99
Mon 11/29/99
Hold Construction Kick-off Meeting
Mon 11/29/99
Tue 11/30/99
Celebrate project construction start w/entire
team
Tue 11/30/99
Tue 11/30/99
Construction Kick-off Completed
Tue 11/30/99
Tue 11/30/99
First iteration
Tue 11/30/99
Thu 12/16/99
Do Technical Reviews
Tue 11/30/99
Tue 11/30/99
Technical Reviews 1
Tue 11/30/99
Tue 11/30/99
Technical Reviews 2
Tue 11/30/99
Tue 11/30/99
Test Planning
Tue 11/30/99
Tue 11/30/99
Software test plan for next iteration created,
reviewed, and signed off
Tue 11/30/99
Tue 11/30/99
Software test cases for next iteration created,
reviewed and signed off'
Tue 11/30/99
Tue 11/30/99
Software test plan and test cases for current
iteration updated
Tue 11/30/99
Tue 11/30/99
Iteration Planning
Tue 11/30/99
Tue 11/30/99
Integration Build Plan created, reviewed, and signed off
Tue 11/30/99
Tue 11/30/99
Detailed Software Construction Plan for current iteration including miniature milestones created, reviewed, and signed off
Tue 11/30/99
Tue 11/30/99
Update test plan, focusing on this iteration
Tue 11/30/99
Tue 11/30/99
Refine test cases for this iteration
Tue 11/30/99
Tue 11/30/99
Create test environment
Tue 11/30/99
Tue 11/30/99
Create software build instructions (make files)
for current iteration
Tue 11/30/99
Tue 11/30/99
Beginning-of-iteration planning completed
Tue 11/30/99
Tue 11/30/99
Develop First Iteration
Tue 11/30/99
Thu 12/16/99
Code & Test Use Case Approve Story
Tue 11/30/99
Wed 12/8/99
Do Detailed Design
Tue 11/30/99
Wed 12/1/99
Review & Refine Architecture Design
Wed 12/1/99
Wed 12/1/99
Review & Refine Database Design
Wed 12/1/99
Thu 12/2/99
Develop Code or Modify Generated Code (if
applicable)
Thu 12/2/99
Fri 12/3/99
Research and Resolve Development Tool Bugs (if
applicable)
Fri 12/3/99
Tue 12/7/99
Conduct Code Review
Tue 12/7/99
Tue 12/7/99
Unit Testing
Tue 12/7/99
Wed 12/8/99
Add code to configuration management
Wed 12/8/99
Wed 12/8/99
Code & Test Use Case Edit Profile
Tue 11/30/99
Wed 12/8/99
Do Detailed Design
Tue 11/30/99
Wed 12/1/99
Review & Refine Architecture Design
Wed 12/1/99
Wed 12/1/99
Review & Refine Database Design
Wed 12/1/99
Thu 12/2/99
Develop Code or Modify Generated Code (if
applicable)
Fri 12/3/99
Tue 12/7/99
Research and Resolve Development Tool Bugs (if
applicable)
Tue 12/7/99
Tue 12/7/99
Conduct Code Review
Tue 12/7/99
Tue 12/7/99
Unit Testing
Wed 12/8/99
Wed 12/8/99
Add code to configuration management
Wed 12/8/99
Wed 12/8/99
Code & Test Use Case Send Page
Tue 11/30/99
Thu 12/16/99
Do Detailed Design
Tue 11/30/99
Thu 12/2/99
Review & Refine Architecture Design
Thu 12/2/99
Thu 12/2/99
Review & Refine Database Design
Thu 12/2/99
Thu 12/2/99
Develop Code or Modify Generated Code (if
applicable)
Thu 12/9/99
Fri 12/10/99
Research and Resolve Development Tool Bugs (if
applicable)
Fri 12/10/99
Tue 12/14/99
Conduct Code Review
Tue 12/14/99
Wed 12/15/99
Unit Testing
Wed 12/15/99
Wed 12/15/99
Add code to configuration management
Thu 12/16/99
Thu 12/16/99
Code & Test Use Case Read Content on
Website
Tue 11/30/99
Thu 12/16/99
Do Detailed Design
Tue 11/30/99
Thu 12/2/99
Review & Refine Architecture Design
Thu 12/2/99
Thu 12/2/99
Review & Refine Database Design
Thu 12/2/99
Thu 12/2/99
Develop Code or Modify Generated Code (if
applicable)
Fri 12/10/99
Tue 12/14/99
Research and Resolve Development Tool Bugs (if
applicable)
Tue 12/14/99
Wed 12/15/99
Conduct Code Review
Wed 12/15/99
Wed 12/15/99
Unit Testing
Wed 12/15/99
Thu 12/16/99
Add code to configuration management
Thu 12/16/99
Thu 12/16/99
First Iteration Developed
Thu 12/16/99
Thu 12/16/99
Integration Testing
Wed 12/8/99
Fri 12/10/99
Integration with system
Wed 12/8/99
Thu 12/9/99
Conduct Integration Test
Thu 12/9/99
Thu 12/9/99
Document Problems
Thu 12/9/99
Thu 12/9/99
Modify Code As Applicable
Thu 12/9/99
Fri 12/10/99
Conduct Regression Test
Fri 12/10/99
Fri 12/10/99
Obtain Sign-off
Fri 12/10/99
Fri 12/10/99
Integration Test Complete
Fri 12/10/99
Fri 12/10/99
Installation
Fri 12/10/99
Mon 12/13/99
Install program created, reviewed, and signed
off
Fri 12/10/99
Fri 12/10/99
Install Software for User Acceptance Testing
Fri 12/10/99
Fri 12/10/99
User Manual/Specification/Help updated
Fri 12/10/99
Mon 12/13/99
Training Materials updated (if applicable)
Mon 12/13/99
Mon 12/13/99
Obtain Sign-off
Mon 12/13/99
Mon 12/13/99
Installation Complete
Mon 12/13/99
Mon 12/13/99
User Checkpoint
Mon 12/13/99
Mon 12/13/99
Prepare for User Checkpoint
Mon 12/13/99
Mon 12/13/99
User Checkpoint Meeting and Demonstration
Mon 12/13/99
Mon 12/13/99
Have team, including client project manager,
complete the work release sign-off form
Mon 12/13/99
Mon 12/13/99
First iteration code complete
Mon 12/13/99
Mon 12/13/99
User Acceptance Testing
Mon 12/13/99
Tue 12/14/99
Initiate User acceptance testing
Mon 12/13/99
Tue 12/14/99
Prepare for User sign-off meeting
Tue 12/14/99
Tue 12/14/99
Have team, including client project manager,
complete the work release sign-off form
Tue 12/14/99
Tue 12/14/99
First Iteration User Acceptance Test Complete
Tue 12/14/99
Tue 12/14/99
Wrap-up First Iteration
Tue 12/14/99
Thu 12/16/99
Conduct Quality Check Meeting with Client
Tue 12/14/99
Tue 12/14/99
Hold Client Business-focused Lessons Learned
Meeting
Tue 12/14/99
Tue 12/14/99
Hold Client Technical-focused Lessons Learned
Meeting
Tue 12/14/99
Tue 12/14/99
Hold Context Lessons Learned Meeting
Tue 12/14/99
Wed 12/15/99
Iterative Delivery Project Plan updated,
reviewed, and signed off
Wed 12/15/99
Wed 12/15/99
Software Development Plan updated, reviewed,
and signed off
Wed 12/15/99
Wed 12/15/99
Knowledge Transfer Plan updated, reviewed, and
signed off
Wed 12/15/99
Wed 12/15/99
Project estimates updated (accurate to +30%,
-20%)
Wed 12/15/99
Wed 12/15/99
Move appropriate deliverables from Project
Homepage to IAN Artifacts
Wed 12/15/99
Thu 12/16/99
First Iteration Wrap-up Completed
Thu 12/16/99
Thu 12/16/99
The following deliverables or artifacts will be generated and reviewed during
the first Construction Iteration:
Artifact Set
Deliverable
Responsible
Owner
Design Set
Implementation Model
Ken Perch
Implementation Set
Integration Build Plan
Test Drivers, Stubs, Data, & Scripts
Test Procedures
Test Evaluation Report
Components
Mary Durham
Mike Hunziker
Chris Curvey
Mary Durham
Justin Woddis
Management Set
Iteration Plan
Project Plan (update)
Project Schedule (update)
Project Risk List (update)
Status Assessment
Iteration Assessment
Test Plan
Mary Durham
Mary Durham
Mary Durham
Mary Durham
Mary Durham
Mary Durham
Mary Durham
Resources
Staffing
The project staffing for this iteration can be viewed as follows:
Financial Resources
The budget for this iteration is $150,000. WebNewsOnLine has secured this
funding.
Use Cases
Use cases to be implemented during this iteration are:
Approve Story
Edit Profile
Send Content
Read Content on Web Site
Send Page
Evaluation Criteria
The primary goal of this iteration is to implement the defined set of use
cases.
Each deliverable developed during the iteration will be peer reviewed and
subject to approval from the team.
Formal test plans will be the basis for evaluating the success of this
iteration.
Copyright