CSPS Iteration Plan 4.0
backPath = './../../';
Online Collegiate Paging Service
Iteration Plan
Version 4.0
Revision History
Date
Version
Description
Author
October 6, 1999
1.0
Initial version
Context Integration
October 27, 1999
2.0
Updated at start of Elaboration
Context Integration
November 20, 1999
3.0
Updated at start of first Construction iteration
Context Integration
February 11, 2000
4.0
Updated for Transition
Context Integration
Table of Contents
Introduction
Plan
Resources
Use Cases
Evaluation Criteria
Introduction
Purpose
This Iteration Plan describes the detailed plans for the Transition Iteration
of the Project. During this iteration, the WebNewsOnLine staff will be prepared
to maintain the Collegiate Sports Paging System.
Scope
The Transition Iteration Plan applies to the Collegiate Sports Paging System
project being developed by Context Integration for WebNewsOnLine . This document
will be used by the Project Manager and by the project team.
Definitions, Acronyms and Abbreviations
See Glossary.
References
None
Plan
The Transition Iteration prepares the WebNewsOnLine staff to support and
maintain the system going forward.
Iteration Tasks
The following table illustrates the tasks with their planned start and end
dates.
Task
Start
End
Hold Transition Kick-off Meeting
Mon 2/14/00
Tue 2/15/00
Production Preparation
Tue 2/15/00
Wed 2/16/00
Release Procedures
Tue 2/15/00
Tue 2/15/00
"Release checklist created, reviewed, and
baselined"
Tue 2/15/00
Tue 2/15/00
Release approval signed by all parties
Tue 2/15/00
Tue 2/15/00
Operations Procedures
Tue 2/15/00
Wed 2/16/00
"Detailed Contingency and Disaster
Recovery Plan created, reviewed, and baselined"
Tue 2/15/00
Tue 2/15/00
Complete Operations Training materials
Tue 2/15/00
Tue 2/15/00
Train Operations Team
Tue 2/15/00
Wed 2/16/00
Obtain Sign-off
Wed 2/16/00
Wed 2/16/00
Release & Operations Procedures Completed
Wed 2/16/00
Wed 2/16/00
Production Environment
Wed 2/16/00
Wed 2/16/00
"Production hardware acquired, installed
and configured"
Wed 2/16/00
Wed 2/16/00
Network configuration completed
Wed 2/16/00
Wed 2/16/00
Production data loaded
Wed 2/16/00
Wed 2/16/00
Integration with legacy/external systems
completed
Wed 2/16/00
Wed 2/16/00
Full system testing
Wed 2/16/00
Mon 2/21/00
Conduct Functionality testing
Wed 2/16/00
Wed 2/16/00
Conduct Performance testing
Wed 2/16/00
Thu 2/17/00
Conduct Load Testing
Thu 2/17/00
Fri 2/18/00
"Modify System for Functionality, or
Performance as necessary"
Fri 2/18/00
Mon 2/21/00
"Conduct Regression Testing for
Functionality, Performance & Load "
Mon 2/21/00
Mon 2/21/00
Full System Testing Completed
Mon 2/21/00
Mon 2/21/00
Final Acceptance Testing
Mon 2/21/00
Tue 2/22/00
Perform User Acceptance Test (1)
Mon 2/21/00
Mon 2/21/00
Performance Tuning
Mon 2/21/00
Tue 2/22/00
Perform User Acceptance Test (2)
Tue 2/22/00
Tue 2/22/00
User Acceptance Testing Complete
Tue 2/22/00
Tue 2/22/00
Business User Training
Tue 2/22/00
Wed 2/23/00
User training materials completed
Tue 2/22/00
Wed 2/23/00
"User Training environment (training data,
etc.) created"
Wed 2/23/00
Wed 2/23/00
Business User Training Complete
Wed 2/23/00
Wed 2/23/00
Transition Wrap-up
Wed 2/23/00
Wed 2/23/00
Conduct Quality Check Meeting with Client
Wed 2/23/00
Wed 2/23/00
Review Transition Wrap-up Checklist for
Completion
Wed 2/23/00
Wed 2/23/00
"Have team, including client project
manager, complete the work release sign-off form"
Wed 2/23/00
Wed 2/23/00
Move appropriate deliverables from Project
Homepage to IAN Artifacts
Wed 2/23/00
Wed 2/23/00
Transition Complete - System in production
Wed 2/23/00
Wed 2/23/00
The following deliverables or artifacts will be generated and reviewed during
the Transition Iteration:
Artifact Set
Deliverable
Responsible
Owner
Implementation Set
Test Evaluation Report
Mary Durham
Management Set
Iteration Plan
Project Plan (update)
Project Schedule (update)
Project Risk List (update)
Status Assessment
Iteration Assessment
Mary Durham
Mary Durham Mary Durham Mary Durham Mary Durham Mary Durham
Resources
Staffing
The project staffing for this iteration can be viewed as follows:
Financial Resources
The budget for this iteration is $20,000. WebNewsOnLine has secured this
funding.
Use Cases
All use cases have been implemented.
Evaluation Criteria
The primary goal of this iteration is to hand the system off to WebNewsOnLine
staff. Success will be measured by final user acceptance and operations
acceptance.
Copyright
1987 - 2003 Rational Software Corporation
Wyszukiwarka
Podobne podstrony:
ex itplan1ex itplan2ex itplan3ex uc prtadrpt1ex uc subsc1La porte de l etre d eveil (ex Le Soutra de Lotus)Ex OblivioneJoint Venture Scheiß auf?ine ExROZG EXexex tstplnWentyleVentureTD EXRM 1 ewaluacja ex post NPRex uc sndpg2więcej podobnych podstron