AGH UNIVERSITY OF SCIENCE AND TECHNOLOGY
FACULTY OF MINING AND GEOENGINEERING
DEPARTMENT OF GEOMECHANICS, CIVIL ENGINEERING AND GEOTECHNICS
CIVIL ENGINEERING
Underground Engineering
ROCK MASS CLASSIFICATION
Evaluation of the rock mass quality in the tunnel (chamber) area with the initial proposal for support
UNIVERSITY TEACHER: MSc Eng. Agnieszka Stopkowicz
AUTHOR: Katarzyna Ziobro
group: 3
number of project: 67
date: 2013-06-01
The tasks of the project
Defining indices of the RMR system (according to Bieniawski) and of Q (according to Barton, Lien and Lunde) and classification of rock mass.
Comparison of RMR and Q indices and comment on the rock mas quality and their correlations.
The initial proposal for lining the excavation site on the basis of the Q index.
Design data
No. | Parameter | Value or description |
---|---|---|
1. | Shape, dimensions and destination of tunnel (chamber) | road tunnel, circular cross-section with a 5,5 m radius |
2. | Average depth [m] | 85 |
3. | General characteristics of the rock mass in the area of tunnel (chamber) drilling | concise, block |
4. | Average compressive strength of the surrounding rocks [MPa] | 28 |
5. | Average tensile strength of the surrounding rocks [MPa] | 3 |
6. | RQD [%], core diameter of 55 mm | as in the picture below |
7. | Amount and average spacing of discontinuities | two discontinuity sets with an average spacing of 0.6 m |
8. | Condition of discontinuities | rough, irregular, flat walls of a clay-filled joints (separation < 5 mm thick) |
9. | Groundwater conditions | Large supply of water (more than 30l/min) |
10. | Orientation of discontinuities relative to the direction of tunnel (chamber) drive | extension parallel to the long axis of the tunnel, dip 15 ° |
11. | Method of drilling | mechanical drilling |
Rock Quality Designation (RQD) $\text{RQD} = \frac{\sum_{}^{}{\text{Length\ of\ core\ pieces\ } > \ 10\ \text{cm}\ }}{\text{Total\ length\ of\ core\ run}} \times 100\%$
$\text{RQD} = \frac{19 + 14 + 12 + 12 + 15 + 10}{94} \times 100\% = 87,23\%$
1) Strength of intact rock material
uniaxial compressive strength is 28 MPa
rating: 4 /15
2) Drill core Quality RQD
the proportion of the intact core pieces longer than 100 mm to the total length of core is 87,23%
rating: 15/20
3) Spacing of discontinuities
two discontinuity sets with an average spacing of 0,6 m
rating: 10 /20
4) Condition of discontinuities
rough, irregular, flat walls of a clay-filled joints (separation < 5 mm thick)
rating: 15 /30
5) Groundwater
Large supply of water (more than 30l/min)
rating: 4 /15
extension parallel to the long axis of the tunnel, dip 15 °– fair
rating: -5
total rating: 43/100
class number: III
description: fair rock
Modified RMR factor:
Factor | Note | Comments |
---|---|---|
AB (0,8-1,0) (Excavation method) |
0,9 | The medium value, because excavation is carried out by machines , which cause additional (minimal) failure of rock mass. |
AS (0,6-1,2) (In – situ stress) |
1,0 | Rough separations, walls og a clay-filled joints. |
S (0,7-1,0) (Condition of rock mass (joints)) |
0,7 | Two sets of discontinuities with unfavourable spacing and shape. |
AB . AS . S = 0,9 . 1,0 . 0,7 = 0.63 > 0.5
RMRMODIFIED = RMRBASIC . AB . AS . S = 43 . 0,9 . 1,0 . 0,7= 27,09
class number: IV
description: poor rock
average stand-up time: 10hours for2, 5 m span
cohesion of rock mass: 100-200 kPa
friction angle of rock mass: 15-25 deg
Bieniawski and Serafim & Pereira:
Em = 10(RMR − 10)/40 [GPa] for RMR < 50
Hoek & Brown:
$E_{m} = \frac{\sqrt{R_{c}}}{10}10^{(\text{RMR} - 10)/40}$
Verman:
$$E_{m} = 0,3H^{\propto}10^{\frac{\text{RMR} - 10}{40}}$$
∝ = 0, 22
Young’s module | For RMRBASIC | For RMRMODIFIED |
---|---|---|
Bieniawski and Serafim & Pereira | 6,68 GPa | 2,67 GPa |
Hoek and Brown | 4,72 GPa | 1,89 GPa |
Verman | 6,58 GPa | 3,41 GPa |
Hoek:
$${R_{\text{crm}} = \sqrt{s}\ R_{c}}{s_{1} = e^{\frac{\text{RMR} - 100}{9}}}$$
Aydan & Kawamoto:
Rcrm = 0, 0016 RMR2, 5
Kalamaras & Bieniawski:
$R_{\text{crm}} = \frac{R_{c}}{2}\frac{\text{RMR} - 15}{85}$
Uniaxial compressive strenght of rock mass | For RMRBASIC | For RMRMODIFIED |
---|---|---|
Hoek | 2,63 MPa | 0,89 MPa |
Aydan & Kawamoto | 19,40 MPa | 6,11 MPa |
Kalamaras & Bieniawski | 8,23 MPa | 3,56 MPa |
$$Q = \frac{\text{RQD}}{J_{n}} \times \frac{J_{r}}{J_{a}} \times \frac{J_{w}}{\text{SRF}}$$
where
RQD is the Rock Quality Designation
Jn is the joint set number
Jr is the joint roughness number
Ja is the joint alteration number
Jw is the joint water reduction factor
SRF is the stress reduction factor
1) Rock quality designation
The proportion of the intact core pieces longer than 100 mm to the total length of core is 0%, very poor. Where RQD is reported or measured as ≤ 10 (including 0), a nominal value of 10 is used to evaluate Q.
RQD = 87
2) Joint set number
two discontinuity sets with an average spacing of 0.6 m
Jn = 4
3) Joint roughness number
rough, irregular
Jr = 1.5
4) Joint alteration number
flat walls of a clay-filled joints (separation < 5 mm thick)
Ja = 8.0
5) Joint water reduction
Large supply of water (more than 30l/min)
Jw = 0.33
6) Stress reduction factor
Medium stress
SRF = 1.0
$$\frac{\text{RQD}}{J_{n}} = \frac{87}{4} = 21,75$$
represents the structure of rock mass
crude measurement of block or particle size
$$\frac{J_{r}}{J_{a}} = \frac{1,5}{8,0} = 0.188$$
represents roughness and frictional characteristics of joint walls or infill material
$$\frac{J_{w}}{\text{SRF}} = \frac{0.33}{1.0} = 0.33$$
consists of two stress parameters
SRF can be regarded as a total stress parameter of
loosening load in competent rock
rock stress in competent rock
squeezing loads in plastic incompetent rock
Jw is a measure of water pressure
$Q = \frac{\text{RQD}}{J_{n}} \times \frac{J_{r}}{J_{a}} \times \frac{J_{w}}{\text{SRF}} = 21.75 \bullet 0.188 \bullet 0.33 = 1,35$
Excavation Support Ratio (ESR)
(D) Power stations, major road and railway tunnels, civil defense chambers, portal intersections.
ESR = 1.0
Equivalent Dimension De
Circular cross-section with a 5,5 m radius. Excavation span is 11 m.
$$D_{e} = \frac{Excavation\ span,\ diameter\ or\ height\ (m)}{\text{Excavation\ Support\ Ratio\ }\text{ESR}} = \frac{11\ m}{1.0} = 11\text{\ m}$$
Estimated support category based on the tunneling quality index Q
Description of the rock mass: Poor.
Reinforcement category:
(5) Fibre reinforced shotcrete, 50–90 mm, and bolting.
Fibre reinforced shotcrete 90 mm
Bolt spacing in shotcreted area: 2.50 m
Length of the bolts
roof:
$$L = \frac{2 + 0.15s}{\text{ESR}} = \frac{2 + 0.15 \bullet 11\ m}{1.0} = 3,65\ m \approx 3.7\ m$$
walls:
$$L = \frac{2 + 0.15H}{\text{ESR}} = \frac{2 + 0.15 \bullet 11\ m}{1.0} = 3.625\ m \approx 3.7\ m$$
Young’s modulus:
$$E = 10^{3}\sqrt[3]{Q\frac{R_{c}}{3}} = 10^{3}\sqrt[3]{1,39 \bullet \frac{50}{3}} = 2,85\ \text{GPa}$$
RMR | Q | |
---|---|---|
Value | 27,09 /100 | 1,39 /1000 |
Description of the rock mass | poor | poor |
Young’s modulus (E) [GPa] according to Bieniawski and Serafim &Pereira | 2,67 | 2,85 |
RMR-Q Correlation
RMRbasic = 43
RMRmod = 27, 09
Q = 1, 35
Source of case studies | Correlation | RMR(Q) | Comments |
---|---|---|---|
New Zealand | RMR = 13.5 log Q + 43 | 44,76 | Civil engineering tunnels |
Diverse origin | RMR = 9 ln Q + 44 | 45,17 | Civil engineering tunnels |
Spain | RMR = 12.5 log Q + 55.2 | 56,83 | Civil engineering tunnels |
S. Africa | RMR = 5 ln Q + 60.8 | 61,45 | Civil engineering tunnels |
Spain | RMR = 43.89 – 9.19 ln Q | 42,69 | Mining tunnels, soft rock |
Spain | RMR = 10.5 ln Q + 41.8 | 43,16 | Mining tunnels, soft rock |
Canada | RMR = 12.11 log Q + 50.81 | 52,39 | Mining tunnels, hard rock |
Canada | RMR = 8.7 ln Q + 38 | 39,13 | Civil engineering tunnels |
Canada | RMR = 10 ln Q + 39 | 40,30 | Mining tunnels, hard rock |
India | RMR = 21,8 ln Q + 31 | 33,84 | Coal mines, civil engineering tunnels |
Conclusions
Section 2.E.:
The first difference calculations appear with the use of different methods of calculation modules Young and the uniaxial compressive strenght of rock mass. Maximum differences oscillate between 2GPa (Young's modulus for both the basic RMR and modified). The calculation of uniaxial compression, you will see a clear difference in the obtained values depend on the method of calculation. The maximum difference shows a comparison of methods Hoek by Aydan and Kawamoto-is 17MPa (for RMR modified-difference of 5 MPa, but it is because the values obtained are much smaller). The most comparable methods for the Young's modulus are the methods of time Bieniawskiego vs Verma.
Section 3.:
In this section we classify the rock on the basis of Q. To calculate the value of Q, we need to define other parameters, and on the basis of the coefficients, which are often determined based on experience and subjective assessments of the rock mass parameters. Finally, after selecting the appropriate parameters, our rock is classified as poor , and has been adapted housing tunnel (Fibre reinforced shotcrete 90 mm; bolt spacing in shotcreted area: 2.50 m). Young's modulus calculated based on the value of the Q parameter is similar to that obtained by using the RMR Bieniawskiego modified. Compared to E obtained from RMR basic, values significantly different from each other (approximately 2.5 fold).
Section 4.:
The correlation between RMR and Q shows us that our conditions are similar to those in Spain in mining tunnels with soft rock. RMR (Q) is compared to a basic RMR (not RMR modified).
ALL:
Despite the differences in calculation and testing methods used, the final statement of the quality of the rock is the same both by Q and RMR. Although we have received similar features rocks can not be equated with these two methods together. Each method takes into account the different characteristics of the rock mass (eg, number of cracks in the Q when you do not take into RMR). In the assessment of the rock mass and the award of points for a particular trait given table are helpful, but in some cases are not clear such determination slightly, on average they are not related to a specific defined ranges of values, because subjectivity is a key element of this value. To properly reflect the assessment of the rock mass at the points, you have a lot of experience. At the design stage using the same calculation, the values obtained approached with reserve and distance, and treat them as an aid to further design.