Nr |
Czynności >0 |
Czas |
Dat.roz. |
Dat.zak. |
1 | ||||
1. |
POMIARY PRZY POWIERZCHNIOWYCH ROBOTACH ZIEMNYCH |
1 |
2.1.12 |
2.1.12 |
1,< | ||||
2. |
USUNIĘCIE I WYWÓZ HUMUSU |
1 |
3.1.12 |
3.1.12 |
2.; | ||||
3. |
WYKOPY POD STOPY FUNDAMENTOWE |
2 |
4.1.12 |
5.1.12 | |||||
4. |
PODKŁAD BETONOWY POD STOPY FUNDAMENTOWE |
1 |
7.1.12 |
7.1.12 | |||||
5. |
ZBROJENIE STÓP FUNDAMENTOWYCH |
3 |
8.1.12 |
10.1.12 | |||||
6. |
SZALOWANIE I BETONOWANIE STÓP FUND. |
4 |
11.1.12 |
14.1.12 | |||||
7. |
ZASYPANIE STÓP FUNDAMENTOWYCH |
11 |
15.1.12 |
25.1.12 | |||||
8. |
PODSYPKA PIASKOWA |
15 |
26.1.12 |
10. 2.12 | |||||
9. |
PODKŁAD Z CHUDEGO BETONU |
3 |
11.2.12 |
13. 2.12 | |||||
10. |
OBSADZENIE SŁUPÓW ŻELBETOWYCH W STOPACH KIELICHOWYCH |
1 |
14. 2.12 |
14. 2.12 | |||||
11. |
MONTAŻ DŹWIGARÓW DACHOWYCH ŻELBETOWYCH PREF. |
1 |
15. 2.12 |
15. 2.12 | |||||
12. |
MONTAŻ PŁYTDACHOWYCH ŻELBETOWYCH PREF. |
1 |
16. 2.12 |
16. 2.12 | |||||
13. |
PODSYPKA PIASKOWA POD POSADZKĘ |
1 |
16. 2.12 |
16. 2.12 | |||||
14. |
PODKŁAD BETONOWY POD POSADZKĘ |
1 |
17. 2.12 |
17. 2.12 | |||||
15. |
BETON POSADZKI |
2 |
18. 2.12 |
19. 2.12 |
PRACOWNICY 1.pracownicy
12 prac.
0.00 prac.
Zestawienia miesięczne:
8| 15,
1.; 1,0,0 Wersja edukacyjn
169,00