Document Number: EDS 06-0001
Version: 4.0
Date: 27/09/2016
T
HI
S
I
S
AN U
NC
ON
T
RO
L
L
E
D DO
CUM
E
N
T
, T
HE
RE
AD
E
R M
US
T
CO
NF
IR
M
I
T
S
V
AL
IDI
T
Y
B
E
F
O
RE
U
S
E
ENGINEERING DESIGN STANDARD
EDS 06-0001
EARTHING STANDARD
Network(s):
EPN, LPN, SPN
Summary:
This standard outlines the earthing design and construction requirements for the
distribution network at all voltage levels and the associated substations.
Author:
Stephen Tucker
Date:
27/09/2016
Approved By:
Paul Williams
Approved Date:
10/10/2016
This document forms part of the Company’s Integrated Business System and its requirements are mandatory throughout UK
Power Networks. Departure from these requirements may only be taken with the written approval of the Director of Asset
Management. If you have any queries about this document please contact the author or owner of the current issue.
Applicable To
UK Power Networks
External
All UK Power Networks
G81 Website
Asset Management
Contractors
Capital Programme
ICPs/IDNOs
Connections
Meter Operators
HSS&TT
Network Operations
UK Power Networks Services
Other
Earthing Standard
Document Number: EDS 06-0001
Version: 4.0
Date: 27/09/2016
© UK Power Networks 2016 All rights reserved
2 of 11
Revision Record
Version
4.0
Review Date
27/09/2021
Date
27/09/2016
Author
Stephen Tucker
Why has the document been updated: Periodic review and minor revision to ensure consistency
with other earthing standards
What has changed:
•
Statutory requirements added (Section 4).
•
Construction and testing requirements added (Section 6).
•
Reference to EDS 06-0019 added (Section 7).
•
Earthing inspection, assessment and maintenance added (Section 9).
• Responsibilities section added (Section 14)
Version
3.1
Review Date
27/10/2016
Date
22/08/2012
Author
Stephen Tucker
COLD and HOT site definitions corrected. Reviewed for publishing on G81 website
Version
3.0
Review Date
30/09/2016
Date
30/09/2011
Author
Stephen Tucker
Revised to reflect the reclassification of Earthing Manual into design and construction standards
Version
2.0
Review Date
31/03/2016
Date
31/03/2011
Author
Stephen Tucker
Reviewed and updated to reflect the new Earthing Design Manual and Earthing Construction Manual
structure
Version
1.0
Review Date
31/03/2013
Date
31/03/2008
Author
Stephen Tucker
Original
Earthing Standard
Document Number: EDS 06-0001
Version: 4.0
Date: 27/09/2016
© UK Power Networks 2016 All rights reserved
3 of 11
Contents
1
Introduction ................................................................................................................ 4
2
Scope .......................................................................................................................... 4
3
Glossary and Abbreviations ..................................................................................... 4
4
Statutory Requirements ............................................................................................ 4
5
Background ................................................................................................................ 5
6
Application .................................................................................................................. 5
6.1
New Substations ......................................................................................................... 5
6.2
Existing Substations .................................................................................................... 5
7
Earthing Design .......................................................................................................... 6
8
Earthing Construction ............................................................................................... 7
9
Earthing Assessment and Maintenance .................................................................. 7
10
HOT Sites .................................................................................................................... 7
11
Substation Earthing Database .................................................................................. 7
12
Records ....................................................................................................................... 7
13
Further Advice ............................................................................................................ 7
14
Responsibilities .......................................................................................................... 8
14.1
Asset Management ..................................................................................................... 8
14.2
Infrastructure Planning ................................................................................................ 8
14.3
Capital Programme ..................................................................................................... 8
14.4
Distribution Planning ................................................................................................... 8
14.5
Network Operations .................................................................................................... 9
14.6
Connections Design .................................................................................................... 9
14.7
Competition-in-Connections ........................................................................................ 9
14.8
Engineering Audit ........................................................................................................ 9
14.9
ICPs and IDNOs ........................................................................................................ 10
15
References ................................................................................................................ 11
15.1
UK Power Networks Standards ................................................................................. 11
15.2
National Standards .................................................................................................... 11
Tables
Table 7-1 – Earthing Design Standards ................................................................................... 6
Table 8-1 – Earthing Construction Standards .......................................................................... 7
Earthing Standard
Document Number: EDS 06-0001
Version: 4.0
Date: 27/09/2016
© UK Power Networks 2016 All rights reserved
4 of 11
1
Introduction
This standard outlines the earthing design and construction requirements for the UK Power
Networks’ distribution networks and the associated substations.
2
Scope
This standard applies to:
• New electrical installations, connections and substations at all voltage levels from 230V
to 132kV.
• Existing substations where there is a material alteration or a substantial increase in earth
fault current.
3
Glossary and Abbreviations
Term
Definition
APP
Asset Portfolio Plan
EPR
Earth potential rise
COLD Site
A substation where the EPR is less than 430V or 650V (high reliability
protection)
HOT Site
A substation where the EPR is greater than 430V or 650V (high
reliability protection)
ICP
Independent Connection Provider
IDNO
Independent Distribution Network Operator
NAMP
UK Power Networks Network Asset Management Plan
ROEP
Rise of earth potential
4
Statutory Requirements
Earthing design and construction shall be carried out with due regard to the statutory
regulations detailed below:
• Health & Safety at Work Act 1974.
• Construction (Design and Management) Regulations 2015.
• Electricity Safety, Quality and Continuity Regulations 2002.
• Electricity Act 1989.
The following documents form the basis for earthing design and construction:
• ENA TS 41-24.
• ENA EREC S34.
• ENA EREC S36.
• BS EN 50522.
• BS 7430.
Earthing Standard
Document Number: EDS 06-0001
Version: 4.0
Date: 27/09/2016
© UK Power Networks 2016 All rights reserved
5 of 11
5
Background
When a fault occurs on an electricity transmission or distribution network, it is possible for a
large current to flow in the general mass of earth. This current can cause a considerable
rise in potential on earthed metalwork, which may be accessible to the public and staff,
particularly those who are carrying out fault switching. In addition, without adequate
safeguards it is possible for this excessive rise in potential to be transferred onto adjacent
power cables and communication cables creating potential danger to anyone who might be
in contact which may be some distance from the actual fault. It is therefore essential that the
earthing and bonding arrangements for equipment associated with public electricity supply is
properly designed, correctly installed, and regularly tested and maintained.
The function of earthing and bonding is to:
• Provide a low impedance path to enable earth fault current at any point on the network to
be returned to the transformer neutral, without thermal or mechanical damage to the
connected equipment and to enable protection equipment to operate correctly.
• Limit the voltage rise on all metalwork and the surface of the ground to which persons
have normal access, to a safe value under all reasonably perceived conditions for faults
at each voltage level associated with the substation. The earthing system should be
constructed so as to prevent the establishment of dangerous potential differences
between parts of the substation, which a person may be contacting simultaneously.
6
Application
6.1
New Substations
The following shall be carried out at all new substations:
• Design a suitable earthing system.
• Determine the earth potential rise at the substation and update the substation earthing
database accordingly (refer to EDS 06-0002).
• Construct and test the earthing system.
• Carry out a post-construction earth resistance measurement and verify the design
values.
6.2
Existing Substations
The following shall be carried out prior to all major asset refurbishment, replacement or
extension works at a grid or primary substations:
• Carry out an earthing survey and assessment to confirm the suitability and integrity of
the existing earthing system
• Determine the earth potential rise at the substation and update the substation earthing
database accordingly (refer to EDS 06-0002).
• Design a suitable earthing system.
• Rectify any deficiencies highlighted by the survey.
• Construct and test the earthing system in accordance with this standard.
• Carry out a post-construction earth resistance measurement and verify the design
values.
Earthing Standard
Document Number: EDS 06-0001
Version: 4.0
Date: 27/09/2016
© UK Power Networks 2016 All rights reserved
6 of 11
Note: These requirements may be excluded where robust records can demonstrate a survey
and assessment was completed in the last five years, the existing earthing system is
appropriate, the substation earthing database is up-to-date and the remaining service life will
match that of the new plant and equipment.
A provision shall be included in a project to cover the costs associated with the design of the
earthing system including the survey, assessment and any measurements. However any
remedial works associated with an existing earthing system shall be covered by the
appropriate maintenance APP line.
7
Earthing Design
The earthing design standards and their application are based on ENA TS 41-24 and
ENA EREC S34 but include the requirements of other standards where this is considered
appropriate and experience gained from previous earthing assessments and measurements.
Also, to ensure a consistent approach at sites shared with National Grid, the appropriate
practices have been included from NGTS 3.1.2. The criteria for designing earthing systems
are outlined in EDS 06-0012.
When designing earthing systems it is important to recognise that they perform differently at
high frequencies than at the lower frequency used for power distribution (50Hz). The
standards are mainly concerned with power frequency performance but some specific
designs have been included, where appropriate, to cater for high frequency aspects.
Earthing design shall be carried out in accordance with the standards detailed in Table 7-1.
Note: For any area of earthing not covered by the UK Power Networks’ earthing standards
refer to the guidelines detailed in ENA TS 41-24.
Table 7-1 – Earthing Design Standards
Description
New
Earthing
Design
Standard
Old
Earthing
Design
Manual
Old
Earthing
Manual
Earthing Design Criteria
EDS 06-0012 Section 2
Section 2
Grid and Primary Substation Design
EDS 06-0013 Section 3
Section 3
Secondary Distribution Substation Earthing Design
EDS 06-0014 Section 4
Section 5
Pole-Mounted Equipment Earthing Design
EDS 06-0015 Section 5
Section 6
LV Network Earthing Design
EDS 06-0016 Section 6
Section 7
Customer EHV and HV Connections (including
Generation) Earthing Design and Construction
Guidelines
EDS 06-0019 n/a
n/a
Customer LV Installation Earthing Design
EDS 06-0017 Section 7
Section 7
NetMap
Earthing Information System
EDS 06-0018 Section 8
n/a
1
UK Power Networks GIS system.
Earthing Standard
Document Number: EDS 06-0001
Version: 4.0
Date: 27/09/2016
© UK Power Networks 2016 All rights reserved
7 of 11
8
Earthing Construction
Earthing construction, testing and measurements shall be carried out in accordance with the
standards detailed in Table 8-1.
Table 8-1 – Earthing Construction Standards
Standard
New Earthing
Construction
Standard
Old Earthing
Construction
Manual
Old
Earthing
Manual
Grid and Primary Substation Earthing Construction
ECS 06-0022
Section 2
Section 4
Secondary Distribution Network Earthing
Construction
ECS 06-0023
Section 3
Section 5
Earthing Testing and Measurements
ECS 06-0024
Section 4
Section 8
9
Earthing Assessment and Maintenance
Earthing inspection, assessment and maintenance shall be carried in accordance with
EMS 10-0601.
10
HOT Sites
The earthing design and construction standards cover the requirements for HOT sites and
include the obligations to third parties.
The HOT site register (EDS 06-0003) provides details of how third parties can obtain HOT
site information for substations owned by UK Power Networks.
UK Power Networks internal process for managing and recording HOT sites is detailed in
EDS 06-0002.
11
Substation Earthing Database
The substation earthing database contains the earthing related data for all grid and primary
substations together with the substation classification. Refer to EDS 06-0002 for further
information.
12
Records
All earthing drawings and reports (survey, design, measurement, post-construction etc.)
shall be sent to
earthingenquiries@ukpowernetworks.co.uk
database and document management system.
13
Further Advice
Specialist advice on all aspects of earthing is available from the author of this document.
Earthing Standard
Document Number: EDS 06-0001
Version: 4.0
Date: 27/09/2016
© UK Power Networks 2016 All rights reserved
8 of 11
14
Responsibilities
14.1
Asset Management
Asset Management is responsible for providing advice on all aspects of earthing.
14.2
Infrastructure Planning
Infrastructure Planning Engineer is responsible for ensuring that all infrastructure projects
include an allocation for earthing design, construction and testing.
14.3
Capital Programme
The Design Engineer is responsible for:
• Ensuring that all new substations or changes to existing substations have an earthing
design in accordance the relevant earthing standards.
• Where required, providing the relevant data to customers to allow them to carry out the
earthing design.
• Ensuring any customer earthing design is in accordance with the relevant earthing
standards.
• Ensuring that all substations are safe and COLD wherever practical and any remedial
actions are incorporated into the substation design.
• Ensuring that all earthing related data is sent
earthingenquiries@ukpowernetworks.co.uk
for inclusion in the substation earthing
database.
The Project Manager is responsible for:
• Ensuring that all secondary substations are constructed and tested in accordance with
the relevant earthing construction standards.
• Ensuring that all earthing related data is sent
earthingenquiries@ukpowernetworks.co.uk
for inclusion in the substation earthing
database.
14.4
Distribution Planning
The Distribution Planning Engineer is responsible for:
• Ensuring that all new secondary substations or changes to existing secondary
substations have an earthing design in accordance the relevant earthing standards.
• Advising telecommunications operators when designing a new substation in the vicinity
of a telecommunications exchange.
• Sending the earthing design and construction forms to Network Operations.
Earthing Standard
Document Number: EDS 06-0001
Version: 4.0
Date: 27/09/2016
© UK Power Networks 2016 All rights reserved
9 of 11
14.5
Network Operations
Network Operations are responsible for:
• Ensuring that all secondary substations are constructed and tested in accordance with
the relevant earthing construction standards.
• Ensuring that all earthing design and construction data is sent
earthingenquiries@ukpowernetworks.co.uk
for inclusion in the substation earthing
database.
14.6
Connections Design
The Connections Designer or Project Manager is responsible for:
• Ensuring that all new substations or changes to existing substations have an earthing
design in accordance the relevant earthing standards.
• Where required, providing the relevant data to customers to allow them to carry out the
earthing design.
• Ensuring any customer earthing design is in accordance with the relevant earthing
standards.
• Advising telecommunications operators when designing a new substation in the vicinity
of a telecommunications exchange.
• Sending the earthing design and construction forms to Network Operations.
14.7
Competition-in-Connections
The Competition-in-Connections team are responsible for:
• Providing the relevant data to ICPs to allow them to carry out the earthing design.
• Assessing submitted ICP earthing designs and ensuing compliance with the relevant
earthing standards.
• Ensuring that all earthing related data is sent
earthingenquiries@ukpowernetworks.co.uk
for inclusion in the substation earthing
database.
14.8
Engineering Audit
The Audit Engineer is responsible for:
• Ensuring that all substations are constructed and tested in accordance with the relevant
earthing construction standards.
Earthing Standard
Document Number: EDS 06-0001
Version: 4.0
Date: 27/09/2016
© UK Power Networks 2016 All rights reserved
10 of 11
14.9
ICPs and IDNOs
Independent Connection Providers (ICP) and Independent Distribution Network Operators
(IDNO) are responsible for:
• Ensuring that all UK Power Networks’ substations are designed, constructed and tested
in accordance with the relevant earthing standards.
• Providing sufficient data to allow UK Power Networks to review and assess substation
earthing designs.
• Advising telecommunications operators when a new substation is situated in the vicinity
of a telecommunications exchange.
• Ensuring that all earthing related data is sent to UK Power Networks’ Competition-in-
Connections Delivery Project Manager for inclusion in the substation earthing database.
Earthing Standard
Document Number: EDS 06-0001
Version: 4.0
Date: 27/09/2016
© UK Power Networks 2016 All rights reserved
11 of 11
15
References
15.1
UK Power Networks Standards
EDS 06-0002
HOT Site Requirements (internal document only)
EDS 06-0003
HOT Site Register
EDS 06-0004
Earth Fault Loop Impedance Requirements (internal document only)
EAS 06-0011
Earthing Materials
EDS 06-0012
Earthing Design Criteria
EDS 06-0013
Grid and Primary Substation Earthing Design
EDS 06-0014
Secondary Distribution Substation Earthing Design
EDS 06-0015
Pole-Mounted Equipment Earthing Design
EDS 06-0016
LV Network Earthing Design
EDS 06-0017
Customer Installation Earthing Design
EDS 06-0018
NetMap Earthing Information System (internal document only)
EDS 06-0019
Customer EHV and HV Connections (including Generation) Earthing Design
and Construction Guidelines
ECS 06-0022
Grid and Primary Substation Earthing Construction
ECS 06-0023
Secondary Distribution Network Earthing Construction
ECS 06-0024
Earthing Testing and Measurements
EMS 10-0601
Earthing Inspection, Assessment and Maintenance (internal document only)
15.2
National Standards
ENA TS 41-24
Guidelines for the Design, Installation, Testing and Maintenance of Main
Earthing Systems in Substations
ENA EREC S34
A Guide for Assessing the Rise of Earth Potential at Substation Sites
ENA EREC S36
Procedure to Identify and Record HOT Substations
NG TS 3.1.2
Earthing
BS EN 50522
Earthing of Power Installations Exceeding 1kV AC
BS 7430
Code of Practice for Protective Earthing of Electrical Installations
2
Available from www.energynetworks.org.