Project Management
(Part Two)
Harry Kogetsidis
School of Business
Lecture’s topics
• What is project crashing?
• How can we reduce the expected
completion time of a project?
Critical Path Method (CPM)
A simple network-based method which can
estimate how long a project will take and
which
activities are
critical
for its on time
completion.
Expected duration of a project
Once the expected completion time of a
project
has been estimated, it may be necessary or
desirable to try to reduce it.
This would normally imply an extra cost.
Expected duration of a project
Project managers should therefore decide
whether
to use extra resources in order to reduce the
expected completion time of a project.
time/cost trade-of
Project crashing
Project crashing
is the process of reducing
the
expected completion time of a project.
Project crashing
Some points to remember:
• Reducing the expected completion time of a
project will involve shortening a number of its
activities.
• Shortening activities would normally imply a
cost.
• There might be some activities that cannot be
shortened.
Project crashing
Some points to remember:
• The activities to be shortened must be on the
critical path.
• The process of project crashing could create
more critical paths.
Example
Activity Preceding activity Duration
A
-
5
B
-
4
C
A
2
D
C
4
E
B
5
F
B
5
G
B,C 4
H
F
3
CPM network
CPM network
Solution
• Expected project completion time: 12 weeks.
• Critical path: B-F-H
.
• Critical activities: B, F and H
.
slack = 0
• Non-critical activities: A, C, D, E, and G
.
slack =
1
slack = 3
slack = 1 slack = 1 slack = 1
Example (continued)
Activity Normal
Crash Normal Crash
time time cost cost
A
5
4 3000 3300
B
4
3 2100 2450
C
2
1 3250 4000
D
4
4 2200 2200
E
5
3 3400 3900
F
5
2 2800 3400
G
4
3 3000 3650
H
3
1 6000 7500
Bonus ofered
There is a bonus of
€500
if the project is completed in 11
weeks.
What should the project manager do?
Example (continued)
Activity Normal
Crash Normal Crash
Max
time Crash
time time cost cost
reduction
cost/wk
A
5
4 3000 3300
B
4
3 2100 2450
C
2
1 3250 4000
D
4
4 2200 2200
E
5
3 3400 3900
F
5
2 2800 3400
G
4
3 3000 3650
H
3
1 6000 7500
Maximum time reduction
Max. time reduction = normal time – crash
time
(1)
Crash Cost
crash cost – normal cost
Crash cost / week = -----------------------------------
(2)
max. time reduction
Paths in the project
• ACD
5 + 2 + 4 = 11 wks
• ACG
5 + 2 + 4 = 11 wks
• BG
4 + 4 = 8 wks
• BFH
4 + 5 + 3 =12 wks
critical path
• BE
4 + 5 = 9 wks
Example (continued)
Activity Normal
Crash Normal Crash
Max
time Crash
time time cost cost
reduction
cost/wk
A
5
4 3000 3300
1
300
B
4
3 2100 2450
1
350
x
C
2
1 3250 4000
1
750
D
4
4 2200 2200
0
-
E
5
3 3400 3900
2
250
F
5 4 2 2800 3400
3 2 200
x
G
4
3 3000 3650
1
650
H
3
1 6000 7500
2
750
x
Conclusion
• Shorten activity F by one week at a cost of
€200
.
Bonus =
€500
go for the bonus!
Total cost =
€200
Second Bonus ofered
There is another bonus of
€1000
if the project is
completed in
10 weeks.
What should the project manager do?
Paths in the project
• ACD
5 + 2 + 4 = 11 wks
critical path
• ACG
5 + 2 + 4 = 11 wks
critical path
• BG
4 + 4 = 8 wks
• BFH
4 + 5 4 + 3 =11 wks
critical path
• BE
4 + 5 = 9 wks
Example (continued)
Activity Normal
Crash Normal Crash
Max
time Crash
time time cost cost
reduction
cost/wk
A
5 4 4 3000 3300
1 0 300
#
!
B
4
3 2100 2450
1
350
x
C
2
1 3250 4000
1
750
#
!
D
4
4 2200 2200
0
-
#
E
5
3 3400 3900
2
250
F
5 4 3
2 2800 3400
3 2 1
200
x
G
4
3 3000 3650
1
650
!
H
3
1 6000 7500
2
750
x
Conclusion
• Shorten activity F by one week at a cost of
€200
.
• Shorten activity A by one week at a cost of
€300
.
Bonus =
€1000
go for the bonus!
Total cost =
€500
Problem 1
Activity Preceding activity Duration
A
-
3
B
-
6
C
A
2
D
B,C
5
E
D
4
F
E
3
G
B,C
9
H
F,G
3
Problem 1 (continued)
Activity Normal
Crash Normal Crash
time time cost cost
A
3
2 200 250
B
6
4 400 440
C
2
2 400 400
D
5
4 750 850
E
4
3 600 680
F
3
3 460 460
G
9
7 450 520
H
3
3 500 500
Problem 1 (continued)
There is a bonus of
€100
if the project completion time is
reduced by one week.
There is another bonus of
€100
if the project completion time
is
reduced by a second week.
There is a third bonus of
€100
if the project completion time is
reduced by a third week.
What should the project manager do?
Problem 2
Activity Preceding activity
A
-
B
-
C
-
D
B
E
D
F
A
G
A
H
E,C
I
F
J
G,H
Problem 2 (continued)
Activity Normal
Crash Normal Crash
time time cost cost
A
12
11 150 200
B
8
7 200 250
C
14
12 250 300
D
4
2 250 350
E
1
1 400 400
F
12
12 350 350
G
9
7 450 500
H
8
6 400 450
I
3
1 450
500
J
7
5 400 480
Problem 2 (continued)
There is a bonus of
€75
if the project completion time is
reduced by one week.
There is another bonus of
€75
if the project completion
time is
reduced by a second week.
What should the project manager do?
Problem 3
Activity Preceding activity
A
-
B
-
C
-
D
A
E
B
F
B
G
C
H
F,G
I
D
J
D
K
E,I
L
K,H
M
L
Problem 3 (continued)
Activity Normal
Crash Normal Crash
time time cost cost
A
3
2 750 550
B
4
2 600 200
C
3
3 300 300
D
3
2 400 250
E
4
4 400 400
F
3
3 350 350
G
3
2 450 300
H
2
1 400 250
I
4
2 450
250
J
6
4 400 100
K
1
1 550
550
L
1
1 650 650
M
1
1 400 400
Problem 3 (continued)
There is a bonus of
€250
if the project completion time is
reduced by two weeks.
What should the project manager do?