Project Management
(Part One)
Harry Kogetsidis
School of Business
Lecture’s topics
• What is a project?
• What is project management?
• How can network analysis methods help in
project management?
Projects
A
project
is a unique set of activities
designed to
accomplish a specific set of objectives.
e.g. building a new factory, introducing a new product to the
market etc.
Projects
As projects may consist of many activities, they
need
to be carefully planned, coordinated and controlled
in
order to:
(a) accomplish their objectives
(b) meet time and cost targets
Project Management
Project management
involves the process of
planning,
coordinating and controlling projects that
consist of
various activities.
sequential and interrelated
Example
Activity Preceding activity Duration
A
-
5
B
-
4
C
A
2
D
C
4
E
B
5
F
B
5
G
B,C
4
H
F
3
* activity expected durations given in
weeks.
Project completion time
As a number of activities can take place at the
same
time (
concurrent activities
), the expected
completion
time of the project will be less than the sum of
the
completion times of all its activities.
Network Analysis
Network analysis
involves the use of
network-
based methods that can be used as tools in
the
analysis and management of projects.
Critical Path Method (CPM)
A simple network-based method which can
estimate how long a project will take and
which
activities are
critical
for its on time
completion.
Critical Path Method (CPM)
Two ways of drawing CPM diagrams:
• activities represented by lines
• activities represented by nodes
The second approach is adopted here.
Critical Path Method (CPM)
Activity example
The amount of time an activity can be delayed without
delaying the overall completion time of the project.
CPM network
CPM network
Solution
• Expected project completion time: 12 weeks.
• Critical path: B-F-H
.
• Critical activities: B, F and H
.
slack = 0
• Non-critical activities: A, C, D, E, and G
.
slack =
1
slack = 3
slack = 1 slack = 1 slack = 1
Problem 1
Activity Preceding activity Duration
A
-
3
B
-
6
C
A
2
D
B,C
5
E
D
4
F
E
3
G
B,C 9
H
F,G
3
Use the Critical Path Method to identify the critical path
for this project and to estimate its expected completion
time.
Problem 2
Activity Preceding activity Duration
A
-
12
B
-
8
C
-
14
D
B
4
E
D
1
F
A
12
G
A
9
H
E,C
8
I
F
4
J
G,H
7
Use the Critical Path Method to identify the critical
path
for this project and to estimate its expected
completion
time.
Problem 3
Activity Preceding activity Duration
A
-
5
B
-
4
C
-
6
D
A
3
E
B
7
F
B
2
G
C
5
H
F,G
8
I
D
4
J
D
4
K
E,I
2
L
K,H
6
M
L
5
Use the Critical Path Method to identify the critical
path
for this project and to estimate its expected
completion
time.