Ch14 11

Ch 14-11 Build a Model Solution





3/6/2001










Chapter 14. Solution to Ch 14-11 Build a Model




















Webmasters.com has developed a powerful new server that would be used for corporations’ Internet activities. It would cost $10 million to buy the equipment necessary to manufacture the server, and $3 million of net working capital would be required. The servers would sell for $24,000 per unit, and Webmasters believes that variable costs would amount to $17,500 per unit. The company’s fixed costs would also rise by $1 million per year. It would take one year to buy the required equipment and set up operations, and the server project would have a life of 4 years. Conditions are expected to remain stable during each year of the operating life, i.e., unit sales, the sales price, and costs would be unchanged. If the project is undertaken, it must be continued for the entire 4 years. Also, the project’s returns are expected to be highly correlated with returns on the firm’s other assets.
The equipment would be depreciated over a 5-year period, using MACRS rates as described in Appendix 12A. The estimated market value of the equipment at the end of the project’s 4-year life is $500,000. Webmasters’ federal-plus-state tax rate is 40%. Its cost of capital is 10% for average risk projects, defined as projects with a coefficient of variation for NPV between 0.8 and 1.2. Low risk projects are evaluated with a WACC of 8%, and high risk projects at 13%.










a. Develop a spreadsheet model and use it to find the project’s NPV, IRR, and payback.


























Key Output: NPV = $2,863
Part 1. Input Data (in thousands of dollars)





IRR = 18.8%







MIRR = 15.6%
Equipment cost

$10,000





Net Operating WC

$3,000
Market value of equipment in 2005

$500
First year sales (in units)

1,000
Tax rate

40%
Sales price per unit

$24.00
WACC

10%
Variable cost per unit

$17.50





Fixed costs

$1,000















Part 2. Depreciation and Amortization Schedule


Years Accum'd
Year

Initial Cost 1 2 3 4 Depr'n










Equipment Depr'n Rate


20.0% 32.0% 19.0% 12.0%

Equipment Depr'n, Dollars


$2,000 $3,200 $1,900 $1,200 $8,300
Ending Bk Val: Cost - Accum Dep'rn

10,000


$1,700











Part 3. Net Salvage Values, in 2005



Equipment



Estimated Market Value in 2005



$500



Book Value in 2005



1,700



Expected Gain or Loss



-1,200



Taxes paid or tax credit



-480



Net cash flow from salvage



$980













Part 4. Projected Net Cash Flows (Time line of annual cash flows)










Years, 1-4 basis 0 1 2 3 4


Years, actual year basis 2001 2002 2003 2004 2005
Investment Outlays at Time Zero:








Equipment


(10,000)




Increase in Net Operating WC


(3,000)














Operating Cash Flows over the Project's Life:








Units sold



1,000 1,000 1,000 1,000
Sales price



$24.00 $24.00 $24.00 $24.00










Sales revenue



$24,000 $24,000 $24,000 $24,000
Variable costs



17,500 17,500 17,500 17,500
Fixed operating costs



1,000 1,000 1,000 1,000
Depreciation (equipment)



2,000 3,200 1,900 1,200
Oper. income before taxes (EBIT)



3,500 2,300 3,600 4,300
Taxes on operating income (40%)



1,400 920 1,440 1,720
Net Operating Profit After Taxes (NOPAT)



2,100 1,380 2,160 2,580
Add back depreciation



2,000 3,200 1,900 1,200
Operating cash flow



$4,100 $4,580 $4,060 $3,780
Terminal Year Cash Flows:








Return of net operating working capital






$3,000
Net salvage value






980
Total termination cash flows






$3,980










Net Cash Flow (Time line of cash flows)


($13,000) $4,100 $4,580 $4,060 $7,760










Part 5. Key Output: Appraisal of the Proposed Project


















Net Present Value (at 10%)

$2,863





IRR

18.85%





MIRR

15.61%















Payback (See calculation below)

Applies MIN function to Row 73 to find first year when payback is positive. 0.00














Data for Payback Years


0 1 2 3 4

Cumulative CF from Row 53

(13,000) (8,900) (4,320) (260) 7,500

IF Function to find payback


0.00 0.00 0.00 3.03




















b. Now conduct a sensitivity analysis to determine the sensitivity of NPV to changes in the sales price, variable costs








per unit, and number of units sold. Set these variables’ values at 10% and 20% above and below their base case








values. Include a graph in your analysis.


















Part 6. Evaluating Risk: Sensitivity Analysis


















I. Sensitivity of NPV to Changes in Inputs. Here we use an Excel "Data Table" to find NPV








different unit sales, holding other thing constant.


















% Deviation 1st YEAR UNIT SALES
% Deviation WACC


from Units NPV
from
NPV


Base Case Sold NPV at 10%. Base Case $2,863
Base Case WACC 2,863


-20% 800 $390
-20% 8.0% $3,650


-10% 900 $1,627
-10% 9.0% $3,249


0% 1,000 $2,863
0% 10.0% $2,863


10% 1,100 $4,099
10% 11.0% $2,491


20% 1,200 $5,335
20% 12.0% $2,133












% Deviation VARIABLE COSTS
% Deviation SALES PRICE


from Variable NPV
from Sales NPV


Base Case Costs $2,863
Base Case Price $2,863


-20% $14.00 $9,520
-20% $19.20 -$6,266


-10% $15.75 $6,191
-10% $21.60 -$1,702


0% $17.50 $2,863
0% $24.00 $2,863


10% $19.25 -$465
10% $26.40 $7,428


20% $21.00 -$3,794
20% $28.80 $11,992












% Deviation FIXED COSTS






from Fixed NPV






Base Case Costs $2,863






-20% $800 $3,243






-10% $900 $3,053






0% $1,000 $2,863






10% $1,100 $2,673






20% $1,200 $2,483

















































Deviation NPV at Different Deviations from Base



from Sales Variable
Fixed




Base Case Price Cost/Unit Units Sold Cost WACC



-20% ($6,266) $9,520 $390 $3,243 $3,650



-10% ($1,702) $6,191 $1,627 $3,053 $3,249



0% $2,863 $2,863 $2,863 $2,863 $2,863



10% $7,428 ($465) $4,099 $2,673 $2,491



20% $11,992 ($3,794) $5,335 $2,483 $2,133













Range 18,258 13,313 5,726 761 1,516





















c. Now conduct a scenario analysis. Assume that there is a 25% probability that “best case” conditions, with each of








the variables discussed in Part b being 20% better than its base case value, will occur. There is a 25% probability








of “worst case” conditions, with the variables 20% worse than base, and a 50% probability of base case conditions.


















Part 7. Evaluating Risk: Scenario Analysis





Squared








Deviation




Sales Unit Variable
Times

Scenario Probability Price Sales Costs NPV Probability











Best Case 25% $28.80 1,200 $14.00 $22,453 The deviation (NPV of the scenario minus expected NPV ) squared times the probability. 85264821
Manually changed the Part 1 inputs, then put the
Base Case 50% $24.00 1,000 $17.50 $2,863 629768
NPV as calculated with the modified variables here.
Worst Case 25% $19.20 800 $21.00 ($12,238) 65798132
Took deviations from the expected values, squared







151692721
them, and multiplied by the probabilities to get the


Expected NPV = sum, prob times NPV


$3,985

numbers shown.


Standard Deviation = Sq Root of column H sum


$9,268

Summed the squared deviations and took sq root


Coefficient of Variation = Std Dev / Expected NPV


2.33

Std Dev divided by Expected NPV
a. Probability Graph










Probability


















50%




























25%


















0






2,863


NPV ($)



Most Likely Mean of distribution
























The scenario analysis suggests that the project could be highly profitable, but also that it is quite risky. There is a








25% probability that the project would result in a loss of $12.2 million. There is also a 25% probability that it could








produce an NPV of $22.5 million. The standard deviation is high, at $9.2 million, and the coefficient of variation is a








high 2.33.


















d. If the project appears to be more or less risky than an average project, find its risk-adjusted NPV, IRR, and payback.










With the high CV, we must re-evaluate the project using a higher WACC, 13%. That results in:









Risk adjusted NPV = $1,788







IRR = IRR does not change. 18.85%







Payback = Paypack does not change. $0.00
















e. Based on the information in the problem, would you recommend that the project be accepted?










At this point, the project looks risky but acceptable. There is a good chance that it will produce a positive NPV, but








there is also a chance that the NPV could quite low.


















The problem gave no information about the size of the project relative to the total corporation. If the company were quite








large, and this were but one of many projects, and if the projects were independent of one another, then it should be








accepted. However, if the firm were relatively small, and this project under bad conditions could bankrupt the company,








then the decision is not clear. If management is highly risk averse, they might turn it down. However, well-diversified








investors would probably prefer to see it accepted. So, to maximize the stock price, it should be accepted.


















We indicate in the problem that this project's returns will tend to be highly correlated with the firm's other projects'








returnst. Thus, its stand-alone risk (which is what we have been analyzing) also reflects its within-firm risk. If this








were not true, then we would need to make further risk adjustments.










Wyszukiwarka

Podobne podstrony:
Zarz[1] finan przeds 11 analiza wskaz
11 Siłowniki
11 BIOCHEMIA horyzontalny transfer genów
PKM NOWY W T II 11
wyklad 11
R1 11
CALC1 L 11 12 Differenial Equations
Prezentacje, Spostrzeganie ludzi 27 11
zaaw wyk ad5a 11 12
budzet ue 11 12
EP(11)
W 11 Leki działające pobudzająco na ośrodkowy układ
Zawal serca 20 11 2011
11 Resusc 2id 12604 ppt
11 pomiay dlugosci tasma
Psychologiczne podstawy edukacji 11
11 Ch organiczna AMINOKWASY I BIAŁKAid 12388 ppt

więcej podobnych podstron